Permit Application Status
B-21-625
In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
Date Returned | Name |
---|---|
09/27/2021 | BP3_RFI_081R1_Fut_BldB_HW_CH_Acc_RESP (Stamped) |
09/27/2021 | BP3_RFI_014_Boiler_Plant_UG_Plumb_Conf_R (Stamped) |
10/25/2021 | BP3_RFI_097_Art_Brand_Wall_Supple_RESP (Stamped) |
Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
COO Review - Engineering | Approved | 01/05/2023 | 01/05/2023 |
Emrick Soltis, P.E., CFM
|
|||
COO Review - Planning | Approved | 12/28/2022 | 01/03/2023 |
Bob Keenan, AICP
|
|||
COO Review - Building Code | Approved | 12/28/2022 | 12/28/2022 |
Heidi Spengler
|
|||
All building items complete | |||
Planning Review | TCO Approved | 12/06/2021 | 12/09/2021 |
Bob Keenan, AICP
|
|||
Miscellaneous
Outstanding
12/09/2021
The applicant shall complete the entirety of the project prior to final CO. TCO shall expire January 31, 2022.
|
|||
The applicant shall complete the entirety of the project prior to final CO. TCO shall expire January 31, 2022. | |||
Engineering Review | TCO Approved | 12/06/2021 | 12/07/2021 |
Emrick Soltis, P.E., CFM
|
|||
Miscellaneous
Outstanding
12/07/2021
A completion letter submitted by the Engineer of Record is required prior final inspection. TCO not approved.
|
|||
TCO/CO/CC Approval | |||
Finance Department Review | TCO Approved | 12/06/2021 | 12/06/2021 |
Amy Camilletti
|
|||
TCO/CO/CC Approval The City of Steamboat Springs Finance department has approved a TEMPORARY CERTIFICATE on this project. A construction use tax reconciliation must be completed within 90 days to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department. Please do one reconciliation for the entire project, accounting for all permits and city use tax deposits associated with this project. | |||
Building Code Review | TCO Approved | 12/06/2021 | 12/06/2021 |
Heidi Spengler
|
|||
Miscellaneous
Outstanding
12/06/2021
Needs to pass final inspection.
|
|||
Need Todd's approval, and to pass final inspection. | |||
Utilities Review - Mt. Werner | TCO Approved | 12/06/2021 | 11/30/2021 |
Richard Buccino
|
|||
Miscellaneous
Outstanding
11/30/2021
Based on previous sewer video survey and discussions with the contractors the following items need correction:
1. the sewer main in the SSRC garage is leaking badly into the sewer pipe bedding and gravel pack where it enters the One Steamboat Place Parking garage.
2. the sewer service to the old/demolished Ski School building was never abandoned at the sewer main in the SSRC parking garage.
3. the sewer main from the existing clean out in the Sheraton Gas Room to the point of abandonment in the SSRC Parking Garage needs to abandoned with either flow fill.
4. an as-built drawing needs to be submitted per MWW Rules Regulations and Specifications.
A Corrective Action Plan and schedule to make these repairs ASAP needs to be submitted to MWW and the RC Building Department. After this plan is submitted, reviewed, and approved, MWW will sign the CO/TCO.
|
|||
Based on previous sewer video survey and discussions with the contractors the following items need correction: 1. the sewer main in the SSRC garage is leaking badly into the sewer pipe bedding and gravel pack where it enters the One Steamboat Place Parking garage. 2. the sewer service to the old/demolished Ski School building was never abandoned at the sewer main in the SSRC parking garage. 3. the sewer main from the existing clean out in the Sheraton Gas Room to the point of abandonment in the SSRC Parking Garage needs to abandoned with either flow fill. 4. An As-Built drawing needs to be submitted to MWW per Rules, Regulations and Specifications. A Corrective Action Plan and schedule to make these repairs ASAP needs to be submitted to MWW and the RC Building Department. After this plan is submitted, reviewed, and approved, MWW will sign the CO/TCO. | |||
Fire Code Review | TCO Approved | 12/06/2021 | 11/29/2021 |
Shannon Yaconiello
|
|||
Miscellaneous
Outstanding
11/29/2021
Sprinkler Visual inspection did not pass:
1. Need two heads under stairs of Gold Walk, they were short.
2. Fill hole in same area to seal off crawl space that is non combustible. Talked with Reno/w Saunders
and he will take care of it.
3. Some heads in parking garage where they extended coverage to east have deflector up against
ceiling and need to adjust hangers down to have one inch gap.
|
|||
TCO/CO/CC Approval - Sprinkler Visual inspection did not pass: 1. Need two heads under stairs of Gold Walk, they were short. 2. Fill hole in same area to seal off crawl space that is non combustible. Talked with Reno/w Saunders and he will take care of it. 3. Some heads in parking garage where they extended coverage to east have deflector up against ceiling and need to adjust hangers down to have one inch gap. | |||
GIS Land Development Review | Approved | 12/06/2021 | 11/29/2021 |
Heidi Spengler
|
|||
Approved. RCBD | |||
Building Code Review | Approved | 10/21/2021 | 10/25/2021 |
Todd Carr
|
|||
Addendum submitted 10/14/21 | |||
Building Code Review | Approved | 08/30/2021 | 08/16/2021 |
Todd Carr
|
|||
Addendum approved on all resubmittals on 8/16/21 | |||
Planning Review | Approved | 08/09/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Planning sysadmin - Jun 24 2021 10:50AM - Per BK: 1. Demonstrate compliance with the Conditions of Approval from the Development Plan. See attached. 2. Are the lighting fixtures shown in the proposed permit drawings? If so, please indicate where. I did not see them in my review. 3. Depict the plaza improvements that replace building B as proposed in the approved development plan. sysadmin - Jul 19 2021 8:26AM - OK per BK sysadmin - Aug 9 2021 1:36PM - Addendum received 8/9/2021 OK per BK | |||
Engineering Review | Approved | 07/15/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Engineering Dept | |||
Legacy Permitting Review | Approved w/ Conditions | 07/14/2021 | |
SysAdmin
|
|||
VP legacy plan review: Routt Building sysadmin - Jun 15 2021 9:58AM - Plan review process started sysadmin - Jun 29 2021 10:43AM - Site Plan requested to be submitted showing property lines in regards to the new strcutures and distances from property lines to the structures sysadmin - Jul 13 2021 4:17PM - Permit conditionally approved with Plan Review Letter attached on Deferred Submittal requirements. | |||
Fire Code Review | Approved | 07/14/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Fire Dept sysadmin - Jun 25 2021 3:55PM - Conditionally approved- pending resubmittal of site plan with access width, grade, turning radius, turnaround, and turnouts meeting Fire Dept. access requirements or if unable to meet requirements submittal of fire sprinkler and monitored fire alarm plans and permits. No inspections past foundation until the above is resolved.) www.steamboatsprings.net for details. sysadmin - Jul 14 2021 10:04AM - The drawings with the fire truck movements are acceptable for our purposes. The Fire Marshal has asked that the GC add those drawing to the plans that you submitted. | |||
External Agencies Review | Approved | 07/06/2021 | |
SysAdmin
|
|||
VP legacy plan review: YVEA | |||
External Agencies Review | Approved w/ Conditions | 07/06/2021 | |
SysAdmin
|
|||
VP legacy plan review: Atmos Energy sysadmin - Jul 6 2021 11:22AM - 2# Systems will not be allowed unless proof of an appliance requiring a MINIMUM of over 7" W.C. is provided to Atmos Energy COrp for personnel review. Meter location must be approved by an Atoms Energy Corp employee during a mandatory site visit to be scheduled after foundation is in place. Meters will not be allowed under a shedding roofline or where overhanging snow is a danger to the meter set. | |||
Legacy Permitting Review | Approved | 07/06/2021 | |
SysAdmin
|
|||
VP legacy plan review: Mt Werner Water District sysadmin - Jul 6 2021 1:55PM - Sarah with Gensler working on PIF quanity take off. sysadmin - Jul 6 2021 4:08PM - PIF fees complete. | |||
Legacy Permitting Review | Approved | 06/22/2021 | |
SysAdmin
|
|||
VP legacy plan review: Routt Electrical Plan Review | |||
GIS Land Development Review | Approved | 06/17/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Address | |||
Utilities Review - City | Complete | 06/15/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Water & Sewer | |||
Finance Department Review | Approved | 06/15/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Finance Dept sysadmin - Jun 15 2021 11:07AM - City of Steamboat Springs Finance has approved City tax & permit fees of $118,530.21 on this permit. This is the City’s portion, made payable to the City of Steamboat Springs and submitted to the Routt County Regional Building Department. At the end of the project, City of Steamboat Springs Finance requires a construction use tax reconciliation be completed to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/approval with the Routt County Building Department. |
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Footing Inspection | Failed | 07/27/2021 | ||
SysAdmin | ||||
Foundation Inspection | Complete | 07/28/2021 | ||
SysAdmin | ||||
Legacy Permitting Inspection | Complete | 07/30/2021 | ||
SysAdmin | ||||
Foundation Inspection | Complete | 08/09/2021 | ||
SysAdmin | ||||
Legacy Permitting Inspection | Complete | 08/11/2021 | ||
SysAdmin | ||||
Foundation Inspection | Partial Pass | 8/24/2021 | 8/24/2021 | 08/24/2021 |
Don Marchbanks | ||||
Structural Inspection | Failed | 9/2/2021 | 9/2/2021 | 09/02/2021 |
Don Marchbanks | ||||
Foundation Inspection | Partial Pass | 9/14/2021 | 9/14/2021 | 09/14/2021 |
Don Marchbanks | ||||
Structural Inspection | Partial Pass | 10/7/2021 | 10/7/2021 | 10/07/2021 |
Don Marchbanks | ||||
Foundation Inspection | Partial Pass | 10/22/2021 | 10/22/2021 | 10/22/2021 |
Ted Allen | ||||
Structural Inspection | Partial Pass | 10/28/2021 | 10/28/2021 | 10/28/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 10/28/2021 | 10/28/2021 | 10/28/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 10/29/2021 | 10/29/2021 | 10/29/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 11/3/2021 | 11/3/2021 | 11/03/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 11/5/2021 | 11/5/2021 | 11/05/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 11/5/2021 | 11/5/2021 | 11/05/2021 |
Todd Carr | ||||
Drywall Inspection | Not Ready | 11/5/2021 | 11/5/2021 | 11/05/2021 |
Todd Carr | ||||
Drywall Inspection | Not Ready | 11/5/2021 | 11/5/2021 | 11/05/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 11/12/2021 | 11/12/2021 | 11/12/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 11/16/2021 | ||
Todd Carr | ||||
Building Final Inspection | Failed | 11/24/2021 | 11/24/2021 | 11/24/2021 |
Todd Carr | ||||
Corrections:
Miscellaneous
Carried Forward
11/24/2021
Prior to a TCO being approved on the escalator and stairs the below work should be completed.
1. Install handrails on the new stairs that meet clearance per the IBC Chapter 10 allowing a free 1 1/2" space between the finished wall (stone) and the handrail the whole way up the stairs on both sides, currently this is not met and in some cases touching the stone.
2. Caulk all penetration into the wall on the north side of the escalator where wires or other penetrations enter the wall to keep moisture and water out for the winter season.
3. Enclose the bottom of the plywood constructed cap that extends beyond the north foundation wall to keep this weather tight for the winter season.
4. To approve the TCO on use of the escalator I will need the Final Inspection approval letter from NWCOGG, also please provide me documentation as to when the escalator sensor is replaced that is broken, and also when final cleaning is completed as well.
|
||||
Final Site Inspection | Failed | 12/07/2021 | ||
Emrick Soltis, P.E., CFM | ||||
Building Final Inspection | Partial Pass | 12/10/2021 | 12/10/2021 | 12/10/2021 |
Todd Carr | ||||
Corrections:
Miscellaneous
Outstanding
12/10/2021
This permit is not closing, but rather construction work will pause for the winter season until April of CY2022 when work will resume after the ski season. All work will require new final inspections next summer during CY2022 when work is completed.
|
||||
Miscellaneous
Outstanding
12/10/2021
The exterior exit door that leads to the exterior from underneath the escalator will required plywood to be installed on the exterior side so it can be maintained over winter to lead to a temporary construction exit door that leads to the promenade area, the temp door must be freely open from inside the barricaded area to allow free exit, it may be locked on promenade side so the public does not enter the construction area. Please complete this work as soon as possible
|
||||
Final Site Inspection | Partial Pass | 12/21/2021 | ||
Emrick Soltis, P.E., CFM | ||||
Framing Inspection | Partial Pass | 5/11/2022 | 5/11/2022 | 05/11/2022 |
Todd Carr | ||||
Corrections:
Miscellaneous
Outstanding
05/11/2022
The steel stud framing on the north side of the escalator has been conditionally approved today, pending a Stamped Addendum to be received from the Architect of Record on the changes to the location of the exterior wall, and exterior wall finished over the steel studs. The wall has been moved outward now due to a change in exterior finished to the sheeting and exterior finish materials, the steel bottom plate is now projection over the concrete footer by about an 1", the wall was moved outward to accommodate the change in not installing stone on this wall per the framing contractor. Please have the Architect provide us with a full addendum on the changes to this wall and all exterior finishes and water proofing details.
|
||||
Framing Inspection | Partial Pass | 8/11/2022 | 8/11/2022 | 08/11/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 8/15/2022 | 8/15/2022 | 08/15/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 8/16/2022 | 8/16/2022 | 08/16/2022 |
Ron Norton | ||||
Building Final Inspection | Partial Pass | 9/23/2022 | 9/23/2022 | 09/23/2022 |
Todd Carr | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
09/23/2022
TCO approved:
1. Complete exterior wall on north side, and the pavers that lead you from the exit door to ski time square.
2. Complete the south side exterior wall along the escalator, or at minimum an addendum on how it will be finished per code for exterior finishes.
3. Fire Caulk penetration in electrical room under escalator.
4. Install stairs in ski corp facility tool room that lead up to the concrete floor that leads towards the electrical room and required exit door.
4. Complete all work per the plans, and provide RCRBD with any As-Built conditions that were altered from the original plans under this permit, and provide final copies of all special inspection reports.
|
||||
Framing Inspection | Partial Pass | 9/23/2022 | 9/23/2022 | 09/23/2022 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 9/27/2022 | 9/27/2022 | 09/27/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 9/29/2022 | 9/29/2022 | 09/29/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 10/4/2022 | 10/4/2022 | 10/04/2022 |
Jeff Yeiser | ||||
Building Final Inspection | Passed | 12/21/2022 | 12/21/2022 | 12/21/2022 |
Ron Norton | ||||
Corrections:
Miscellaneous
Resolved
12/21/2022
Prior to a TCO being approved on the escalator and stairs the below work should be completed.
1. Install handrails on the new stairs that meet clearance per the IBC Chapter 10 allowing a free 1 1/2" space between the finished wall (stone) and the handrail the whole way up the stairs on both sides, currently this is not met and in some cases touching the stone.
2. Caulk all penetration into the wall on the north side of the escalator where wires or other penetrations enter the wall to keep moisture and water out for the winter season.
3. Enclose the bottom of the plywood constructed cap that extends beyond the north foundation wall to keep this weather tight for the winter season.
4. To approve the TCO on use of the escalator I will need the Final Inspection approval letter from NWCOGG, also please provide me documentation as to when the escalator sensor is replaced that is broken, and also when final cleaning is completed as well.
|
Condition | Status | Category |
---|---|---|
Miscellaneous Conditions | Resolved | Prior to Certificate of Occupancy/Completion |
Building Department
05/01/2022
TCO approved:
1. Complete exterior wall on north side, and the pavers that lead you from the exit door to ski time square.
2. Complete the south side exterior wall along the escalator, or at minimum an addendum on how it will be finished per code for exterior finishes.
3. Fire Caulk penetration in electrical room under escalator.
4. Install stairs in ski corp facility tool room that lead up to the concrete floor that leads towards the electrical room and required exit door.
4. Complete all work per the plans, and provide RCRBD with any As-Built conditions that were altered from the original plans under this permit, and provide final copies of all special inspection reports.
|
||
Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
Finance
Use Tax Reconciliation
--------------------------------------
The City of Steamboat Springs Finance department has approved a TEMPORARY CERTIFICATE on this project. A construction use tax reconciliation must be completed within 90 days to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department.
Please do one reconciliation for the entire project, accounting for all permits and city use tax deposits associated with this project.
|
||
Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
Planning Department
The applicant shall complete the entirety of the project prior to final CO. TCO shall expire January 31, 2022.
|
Reference Number | Status | Type |
---|---|---|
SPRMH210082 | Expired | Mechanical |
SPRPL210192 | Closed | Plumbing |
SPRMH210774 | Closed | Mechanical |