Permit Application Status
SPRAD210636
In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
| Review Type | Outcome | Est. Completion Date | Completed |
|---|---|---|---|
| Building Code Review | Approved | 08/22/2024 | 08/19/2024 |
|
Todd Carr
|
|||
| New mechancial plans for Big iron coffee recieved and approved. | |||
| COO Review - Building Code | Approved | 08/21/2024 | 08/19/2024 |
|
Rick Melzer
|
|||
| - Waiting on addendum review | |||
| Building Code Review | Failed | 08/21/2024 | 08/19/2024 |
|
Todd Carr
|
|||
| Addendum 8.15.24: Mechanical letter: Sent an email to applicants telling them I need the mechanical plans updated for this exhaust fan change, I cannot accept a letter but rather need new stamped Mechanical plans. | |||
| Utilities Review - City | Approved | 06/10/2024 | 06/10/2024 |
|
Amber Gregory
|
|||
| 5/31/24- Tenant finish for Big Iron Coffee | |||
| Planning Review | Approved | 06/10/2024 | 06/10/2024 |
|
Kelly Douglas, AICP
|
|||
| 5/31/24- Tenant finish for Big Iron Coffee _ OK - Consistent with DPVC-21-06, PL20230012, PL20210086 approved plans. [Kelly Douglas @ 06/10/2024 9:56 AM] | |||
| Building Code Review | Approved | 06/10/2024 | 06/07/2024 |
|
Todd Carr
|
|||
| 5/31/24- Tenant finish for Big Iron Coffee: Plans have been reviewed and approved. | |||
| Fire Code Review | Approved | 06/10/2024 | 06/06/2024 |
|
Charles Brookshire
|
|||
| 5/31/24- Tenant finish for Big Iron Coffee. Conditionally Approved – NO INSPECTIONS pending submittal of Fire Alarm permits by sub-contractor to Fire Prevention. Per adopted building code for live/work units with 2-hour fire separation. Visit www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms. NB [Charles Brookshire @ 06/06/2024 7:50 PM] | |||
| COO Review - Finance Department | Approved | 06/11/2024 | 06/04/2024 |
|
Sondra Spratta
|
|||
| COO Review - Building Code | TCO Approved | 01/17/2024 | 01/17/2024 |
|
Heidi Spengler
|
|||
| Please see conditions | |||
| COO Review - Building Code | TCO Approved | 12/15/2023 | 12/15/2023 |
|
Heidi Spengler
|
|||
| Suite 1 space for steamboat Fit has all life safety and final building items complete. Approved to occupy this area. | |||
| COO Review - Building Code | TCO Approved | 11/30/2023 | 11/30/2023 |
|
Heidi Spengler
|
|||
| TCO approved for unit #2 golf simulator business, call back for final in other units. | |||
| COO Review - Fire Code | Approved | 10/31/2023 | 11/17/2023 |
|
Shannon Yaconiello
|
|||
| CO for Commercial Side is Approved - SY | |||
| COO Review - Planning | Approved | 10/31/2023 | 11/02/2023 |
|
Kelly Douglas, AICP
|
|||
| Inspected 10/17/23 and 10/31/23. Consistent with DPVC-21-06, PL20230012, PL20210086 approved plans, critical improvements ok. CO ok. KD | |||
| COO Review - Building Code | Failed | 10/31/2023 | 10/31/2023 |
|
Heidi Spengler
|
|||
| Need to pass all finals. | |||
| COO Review - Engineering | Approved | 10/31/2023 | 10/30/2023 |
|
Emrick Soltis, P.E., CFM
|
|||
| COO Review - Finance Department | TCO Approved | 10/31/2023 | 10/24/2023 |
|
Amy Camilletti
|
|||
| Utilities Review - City | Approved | 10/13/2023 | 10/16/2023 |
|
Amber Gregory
|
|||
|
Miscellaneous
Outstanding
10/11/2023
Provide documents that show what areas were originally submitted for building permit versus what this addendum is showing. I did not see the former plans to be able to identify new fixtures.
|
|||
| 10.6.23 Submittal | |||
| Building Code Review | Approved | 10/11/2023 | 10/06/2023 |
|
Ted Allen
|
|||
|
Miscellaneous
Outstanding
10/04/2023
Thank you for your time preparing and submitting the addendum and revisions for Phase 1A portion of the Basecamp project. While there are references for revisions to the building “core” such as deleting ladder accessing the roof deleting some of the records such as Mechanical COMcheck approved for the building, most of the work appears to add future rooms, walls and equipment to schedule for rough-in fixtures including sinks and floor sinks for Health Department requirements, water heaters, meters, counters and peninsulas, sewer drains and vents for retail, golf simulator and future bar in tenant spaces that are currently designated as "shells." Provide narrative of lease space requirements for future tenant finish permits and why proposed floor plan and PEM plans are not applicable if not adequate to start and finish these future permits. For example, the A101 tenant was to be leased out as existing, with one existing unisex restroom to be reused.
Please review and let us know your thoughts as we ramp the team up in preparation for a TCO of the new multi-family building SPRMU220151, and partial on the existing building for the lobby room area only of SPRAD210636.
|
|||
| Addendum documents submitted 10/03/2023 | |||
| Building Code Review | Failed | 09/22/2023 | 09/28/2023 |
|
Ted Allen
|
|||
|
Miscellaneous
Carried Forward
10/04/2023
Thank you for your time preparing and submitting the addendum and revisions for Phase 1A portion of the Basecamp project. While there are references for revisions to the building “core” such as deleting ladder accessing the roof deleting some of the records such as Mechanical COMcheck approved for the building, most of the work appears to add future rooms, walls and equipment to schedule for rough-in fixtures including sinks and floor sinks for Health Department requirements, water heaters, meters, counters and peninsulas, sewer drains and vents for retail, golf simulator and future bar in tenant spaces that are currently designated as "shells." Provide narrative of lease space requirements for future tenant finish permits and why proposed floor plan and PEM plans are not applicable if not adequate to start and finish these future permits. For example, the A101 tenant was to be leased out as existing, with one existing unisex restroom to be reused.
Please review and let us know your thoughts as we ramp the team up in preparation for a TCO of the new multi-family building SPRMU220151, and partial on the existing building for the lobby room area only of SPRAD210636.
|
|||
| Letter in response to failed review on 9/12/23 | |||
| Utilities Review - City | Failed | 09/14/2023 | 09/20/2023 |
|
Amber Gregory
|
|||
|
Miscellaneous
Carried Forward
10/11/2023
Provide documents that show what areas were originally submitted for building permit versus what this addendum is showing. I did not see the former plans to be able to identify new fixtures.
|
|||
| Addendum submitted 9.6.23 | |||
| Planning Review | Approved | 09/14/2023 | 09/14/2023 |
|
Kelly Douglas, AICP
|
|||
| Addendum submitted 9.6.23 Addendum ok. Consistent with PL20230012 and DPVC-21-06. KD | |||
| Building Code Review | Failed | 09/14/2023 | 09/12/2023 |
|
Ted Allen
|
|||
|
Miscellaneous
Carried Forward
09/18/2023
Thank you for your time preparing and submitting the addendum and revisions for Phase 1A portion of the Basecamp project. While there are references for revisions to the building “core” such as deleting ladder accessing the roof deleting some of the records such as Mechanical COMcheck approved for the building, most of the work appears to add future rooms, walls and equipment to schedule for rough-in fixtures including sinks and floor sinks for Health Department requirements, water heaters, meters, counters and peninsulas, sewer drains and vents for retail, golf simulator and future bar in tenant spaces that are currently designated as "shells." Provide narrative of lease space requirements for future tenant finish permits and why proposed floor plan and PEM plans are not applicable if not adequate to start and finish these future permits. For example, the A101 tenant was to be leased out as existing, with one existing unisex restroom to be reused.
Please review and let us know your thoughts as we ramp the team up in preparation for a TCO of the new multi-family building SPRMU220151, and partial on the existing building for the lobby room area only of SPRAD210636.
|
|||
| Addendum submitted 9.6.23 Thank you for your time preparing and submitting the addendum and revisions for Phase 1A portion of the Basecamp project. While there are references for revisions to the building “core” such as deleting ladder accessing the roof deleting some of the records such as Mechanical COMcheck approved for the building, most of the work appears to add future rooms, walls and equipment to schedule for rough-in fixtures including sinks and floor sinks for Health Department requirements, water heaters, meters, counters and peninsulas, sewer drains and vents for retail, golf simulator and future bar in tenant spaces that are currently designated as "shells." Provide narrative of lease space requirements for future tenant finish permits and why proposed floor plan and PEM plans are not applicable if not adequate to start and finish these future permits. For example, the A101 tenant was to be leased out as existing, with one existing unisex restroom to be reused. Please review and let us know your thoughts as we ramp the team up in preparation for a TCO of the new multi-family building SPRMU220151, and partial on the existing building for the lobby room area only of SPRAD210636. | |||
| Electrical Review | Approved | 04/07/2023 | 04/10/2023 |
|
Tom Cook
|
|||
| Addendum: final approval subject to field inspection | |||
| Building Code Review | Approved | 03/01/2023 | 02/24/2023 |
|
Ted Allen
|
|||
|
Miscellaneous
Outstanding
02/22/2023
Architectural plans shall clearly show new or existing materials such as roof and ceilings. For example is the roof hatch new or existing. Plans to be resubmitted only when signed and sealed as per CO State Law with
correct date. Civil, Structural and MEP plans appear outdated and shall be resubmitted when coordinated with updated and revised Architectural plans. UNRESOLVED. Structural plans signed and dated 11/12/2021 appear outdated with second floor framing and modifications to existing on Sheet A0321 that appear to create unstable condition and shall be resubmitted when coordinated with updated and revised Architectural plans.Location of the roof hatch has been revised to coordinate better with the existing structure, so that no additional modification of the structure is necessary. Please reference revised sheets A0201, A0202, A0211 which show the new location. While the other plans appear resolved, Structural plans signed and dated 11/12/2021 appear outdated with second floor framing and modifications to existing appear to require resubmittal of Structural Plans and Architectural only if applicable.
|
|||
|
Miscellaneous
Resolved
02/22/2023
According to the LIFE SAFETY Plan on Sheet G0005, occupancy separations are shown with a 1 Hour rating. Please state the charging language from code for these and show materials of construction, whether non-rated and fire resistance rated assemblies as applicable, and where fire resistance provided for code purposes provide details of continuity of fire partitions, whether there is a rated ceiling or walls extend to roof deck, and protection assemblies of penetrations. This is similar to the gas piping clarification requested under Phase 1b - gas main location, how the main is regulated, enters the building and how certain fire-resistive structures are protected that is still outstanding (submittal was expected 9/15/22).RESOLVED WITH EXCEPTION OF GAS PIPING CLARIFICATION.
This clarification requires penetration of 3-Hour Rated Wall that was actually a deferred submittal requested under Phase 1b permit SPRMU220151. As a DEFERRED SUBMITTAL, those portions of the design that are not submitted at the time of the application and that are to be submitted to the building official within a specified period. Work shall be installed in accordance with the approved construction documents, and any changes made during construction that are not in compliance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents. RCRBD notes penetrations into or through interior exit stairways and passageways are prohibited except for certain exceptions per IBC Section 1023.5 and 1024.5. Provide a time frame for resubmittal under separate permit SPRMU220151 with documentaton of location and if allowed within floor-ceiling rated assembly an equal T-Rating and flex connection similar to expansion between buildings shall be provided. RESOLVED - This will be formally submitted no later than 2/23/2023, under permit SPRMU220151
|
|||
| ALL OUTSTANDING ITEMS RESOLVED AND FULL PERMIT APPROVED 2/24/2023 TA | |||
| Planning Review | Approved | 02/20/2023 | 02/17/2023 |
|
Kelly Douglas, AICP
|
|||
|
Miscellaneous
Resolved
02/17/2023
Significant changes are proposed with this addendum to the uses and floor plan approved with DPVC-21-06. Substantial Conformance approval is required prior to approval of this addendum.
__________________
PL20230012 Substantial conformance approved. Addendum OK. kd
|
|||
|
Miscellaneous
Resolved
02/17/2023
Please provide a narrative that clearly explains each change proposed with this addendum.
|
|||
| Fire Code Review | Approved | 02/20/2023 | 02/15/2023 |
|
Mike Middleton
|
|||
|
Miscellaneous
Outstanding
02/13/2023
Revised Drawings reflecting the reduced scope of work (no longer completing an addition with a mezzanine, no longer furnishing a commercial kitchen, etc.) It is not clear how this will change sprinkler and alarm coverage.
|
|||
| Building Code Review | Failed | 02/20/2023 | 02/14/2023 |
|
Ted Allen
|
|||
|
Miscellaneous
Carried Forward
02/22/2023
Architectural plans shall clearly show new or existing materials such as roof and ceilings. For example is the roof hatch new or existing. Plans to be resubmitted only when signed and sealed as per CO State Law with
correct date. Civil, Structural and MEP plans appear outdated and shall be resubmitted when coordinated with updated and revised Architectural plans. UNRESOLVED. Structural plans signed and dated 11/12/2021 appear outdated with second floor framing and modifications to existing on Sheet A0321 that appear to create unstable condition and shall be resubmitted when coordinated with updated and revised Architectural plans.
|
|||
|
Miscellaneous
Resolved
02/14/2023
The occupant load of Gymnasium and also lobby require two exits. The electrical plans referenced show two exits, however the door swing from the Phase 1b doors and inspected under 1a is incorrect and either needs to be corrected or illumination eliminated. The doors for water and electrical room rating of 20 minutes is incorrect for 1-Hour. Also, do any of these need to swing out for exit? Either way, panic and fire exit hardware shall be provided as applicable to all doors regardless of phase. Please update CODE ANALYSIS on Sheet G0003, submit hardware set(s) referenced in Door Schedule and Electrical revisions as applicable to exit lighting.
|
|||
|
Miscellaneous
Resolved
02/14/2023
In reference to ACCESSIBILITY AND TYPICAL MOUNTING HEIGHTS on Sheet G0004, all required signage for accessibility is in this contract. Submit plans showing accessible routes and where directional signage may be required. For example, at least one of each type of exercise machine and equipment shall be on an accessible route, the 2 new doors shown in Gymnasium should be shown on route as applicable or have signage. Also details of accessible showers shall indicate clearance, clear floor space and grab bars as per ICC A117.1-2009 in lieu of 2010 ADAAG as referenced along with the height of mirror shown in BATHROOM NORTH ELEVATION 2/A0501 appears incorrect when compared to notes and figures on Sheet G0004.
|
|||
|
Miscellaneous
Carried Forward
02/22/2023
According to the LIFE SAFETY Plan on Sheet G0005, occupancy separations are shown with a 1 Hour rating. Please state the charging language from code for these and show materials of construction, whether non-rated and fire resistance rated assemblies as applicable, and where fire resistance provided for code purposes provide details of continuity of fire partitions, whether there is a rated ceiling or walls extend to roof deck, and protection assemblies of penetrations. This is similar to the gas piping clarification requested under Phase 1b - gas main location, how the main is regulated, enters the building and how certain fire-resistive structures are protected that is still outstanding (submittal was expected 9/15/22).RESOLVED WITH EXCEPTION OF GAS PIPING CLARIFICATION.
This clarification requires penetration of 3-Hour Rated Wall that was actually a deferred submittal requested under Phase 1b permit SPRMU220151. As a DEFERRED SUBMITTAL, those portions of the design that are not submitted at the time of the application and that are to be submitted to the building official within a specified period. Work shall be installed in accordance with the approved construction documents, and any changes made during construction that are not in compliance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents. RCRBD notes penetrations into or through interior exit stairways and passageways are prohibited except for certain exceptions per IBC Section 1023.5 and 1024.5. Provide a time frame for resubmittal under separate permit SPRMU220151 with documentaton of location and if allowed within floor-ceiling rated assembly an equal T-Rating and flex connection similar to expansion between buildings shall be provided.
|
|||
|
Miscellaneous
Resolved
02/14/2023
Occupied space not provided with natural ventilation in accordance with Section 1202.5 shall have mechanical ventilation in accordance with the International Mechanical Code. Outdoor air introduced into a space by an exhaust system shall be considered as contributing to the outdoor airflow required by Table 403.3.1.1 Exhaust airflow rate shall be provided in accordance with the requirements of Table 403.3.1.1. For example, the plans shall show how light and ventilation conforming to this code shall be provided to the new Leasing room and Storage room if this is used as office space in Fitness Area (if built under this permit as applicable).
|
|||
|
Miscellaneous
Resolved
02/14/2023
IBC Chapter 29 regulates the minimum number of plumbing fixtures that must be provided for every type of building. The regulations in this chapter come directly from Chapters 3 and 4 of the International Plumbing Code (IPC). The approved plans shall show drinking fountain location(s) that are to be provided to include “HI-LO” provisions for accessibility (as applicable per ICC A117.1-2009 for all required fixtures) and service sinks. Additional protection for the building occupants includes requirements to maintain the plumbing in a safe and sanitary condition, as well as privacy for those occupants. Where there are practical difficulties involved in carrying out the provisions of this code, the code official shall have the authority to grant modifications for individual cases, upon application, provided that the code official shall first find that special individual reason makes the strict letter of this code impractical and the modification conforms to the intent and purpose of this code and that such modification does not lessen health, life and fire safety requirements. The details of action granting modifications shall be recorded and entered in the files of the plumbing inspection department as per IPC Section 105.1 Modifications. Please compose a Code Modification Request letter under Section 104.10 of the IBC for the Building Official to review with respect to the Uni-Sex Restrooms and Showers and total plumbing fixtures provided in comparison to what the code would required for male/female fixtures in the restroom/shower areas.
|
|||
|
Miscellaneous
Resolved
02/14/2023
Any change in the use of energy between the existing and new tenant fitup such as addition of equipment and level of conditioning or openings for new doors, garage door replacement or storefront is considered an addition. Also, provide narrative of the area(s) to be served by the new boilers, water heaters and add the third boiler to the mechanical boiler schedule. The plans need to show how these requirements are to be insulated and fenestration U-factors of windows and doors that will be required. This will apply for all glazing in windows and doors installed on-site. The builder shall leave the National Fenestration Rating Council (NFRC) labels on all windows and doors with glazing at time of rough inspections so inspectors can verify the glazing requirements. U-factors shall be determined by an accredited, independent laboratory, and labeled and certified by the manufacturer. While there are exceptions, building entrances shall be protected with an enclosed vestibule, with all doors opening into and out of the vestibule equipped with self-closing devices as per IECC Section C402.5.7. Provide compliance option used for IECC commercial of spaces under this permit. For example, the Future Res Lobby appears over the allowable budgt factor for interior lighting. Also need additional efficiency package option chosen (similar to tenant spaces), exterior lighting calculation and electrical plans updated with mandatory lighting controls and location(s) of occupant sensor controls.
|
|||
|
Miscellaneous
Resolved
02/14/2023
Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet (4877 mm) above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches (762 mm) in height or walking on roofs having a slope greater than 4four units vertical in 12 units horizontal (33-percent slope). Such access shall not require the use of portable ladders as per IMC Section 306.5 Equipment and appliances on roofs or elevated structures. Also note if RTU 4 is still needed and if it is resting on new patio.
|
|||
| Utilities Review - City | Approved | 01/12/2023 | 01/13/2023 |
|
Amber Gregory
|
|||
| Revised Drawings reflecting the reduced scope of work (no longer completing an addition with a mezzanine, no longer furnishing a commercial kitchen, etc.) | |||
| Fire Code Review | Failed | 01/12/2023 | 01/12/2023 |
|
Mike Middleton
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
Revised Drawings reflecting the reduced scope of work (no longer completing an addition with a mezzanine, no longer furnishing a commercial kitchen, etc.) It is not clear how this will change sprinkler and alarm coverage.
|
|||
| Revised Drawings reflecting the reduced scope of work (no longer completing an addition with a mezzanine, no longer furnishing a commercial kitchen, etc.) It is not clear how this will change sprinkler and alarm coverage. | |||
| Electrical Review | Approved | 01/12/2023 | 01/12/2023 |
|
Tom Cook
|
|||
| Revised Drawings reflecting the reduced scope of work (no longer completing an addition with a mezzanine, no longer furnishing a commercial kitchen, etc.) | |||
| Building Code Review | Failed | 01/12/2023 | 01/12/2023 |
|
Ted Allen
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
Architectural plans shall clearly show new or existing materials such as roof and ceilings. For example is the roof hatch new or existing. Plans to be resubmitted only when signed and sealed as per CO State Law with correct date. Civil, Structural and MEP plans appear outdated and shall be resubmitted when coordinated with updated and revised Architectural plans.
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
The occupant load of Gymnasium and also lobby require two exits. The electrical plans referenced show two exits, however the door swing from the Phase 1b doors and inspected under 1a is incorrect and either needs to be corrected or illumination eliminated. The doors for water and electrical room rating of 20 minutes is incorrect for 1-Hour. Also, do any of these need to swing out for exit? Either way, panic and fire exit hardware shall be provided as applicable to all doors regardless of phase. Please update CODE ANALYSIS on Sheet G0003, submit hardware set(s) referenced in Door Schedule and Electrical revisions as applicable to exit lighting.
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
In reference to ACCESSIBILITY AND TYPICAL MOUNTING HEIGHTS on Sheet G0004, all required signage for accessibility is in this contract. Submit plans showing accessible routes and where directional signage may be required. For example, at least one of each type of exercise machine and equipment shall be on an accessible route, the 2 new doors shown in Gymnasium should be shown on route as applicable or have signage. Also details of accessible showers shall indicate clearance, clear floor space and grab bars as per ICC A117.1-2009 in lieu of 2010 ADAAG as referenced along with the height of mirror shown in BATHROOM NORTH ELEVATION 2/A0501 appears incorrect when compared to notes and figures on Sheet G0004.
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
According to the LIFE SAFETY Plan on Sheet G0005, occupancy separations are shown with a 1 Hour rating. Please state the charging language from code for these and show materials of construction, whether non-rated and fire resistance rated assemblies as applicable, and where fire resistance provided for code purposes provide details of continuity of fire partitions, whether there is a rated ceiling or walls extend to roof deck, and protection assemblies of penetrations. This is similar to the gas piping clarification requested under Phase 1b - gas main location, how the main is regulated, enters the building and how certain fire-resistive structures are protected that is still outstanding (submittal was expected 9/15/22).
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
Occupied space not provided with natural ventilation in accordance with Section 1202.5 shall have mechanical ventilation in accordance with the International Mechanical Code. Outdoor air introduced into a space by an exhaust system shall be considered as contributing to the outdoor airflow required by Table 403.3.1.1 Exhaust airflow rate shall be provided in accordance with the requirements of Table 403.3.1.1. For example, the plans shall show how light and ventilation conforming to this code shall be provided to the new Leasing room and Storage room if this is used as office space in Fitness Area (if built under this permit as applicable).
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
IBC Chapter 29 regulates the minimum number of plumbing fixtures that must be provided for every type of building. The regulations in this chapter come directly from Chapters 3 and 4 of the International Plumbing Code (IPC). The approved plans shall show drinking fountain location(s) that are to be provided to include “HI-LO” provisions for accessibility (as applicable per ICC A117.1-2009 for all required fixtures) and service sinks. Additional protection for the building occupants includes requirements to maintain the plumbing in a safe and sanitary condition, as well as privacy for those occupants. Where there are practical difficulties involved in carrying out the provisions of this code, the code official shall have the authority to grant modifications for individual cases, upon application, provided that the code official shall first find that special individual reason makes the strict letter of this code impractical and the modification conforms to the intent and purpose of this code and that such modification does not lessen health, life and fire safety requirements. The details of action granting modifications shall be recorded and entered in the files of the plumbing inspection department as per IPC Section 105.1 Modifications. Please compose a Code Modification Request letter under Section 104.10 of the IBC for the Building Official to review with respect to the Uni-Sex Restrooms and Showers and total plumbing fixtures provided in comparison to what the code would required for male/female fixtures in the restroom/shower areas.
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
Any change in the use of energy between the existing and new tenant fitup such as addition of equipment and level of conditioning or openings for new doors, garage door replacement or storefront is considered an addition. Also, provide narrative of the area(s) to be served by the new boilers, water heaters and add the third boiler to the mechanical boiler schedule. The plans need to show how these requirements are to be insulated and fenestration U-factors of windows and doors that will be required. This will apply for all glazing in windows and doors installed on-site. The builder shall leave the National Fenestration Rating Council (NFRC) labels on all windows and doors with glazing at time of rough inspections so inspectors can verify the glazing requirements. U-factors shall be determined by an accredited, independent laboratory, and labeled and certified by the manufacturer. While there are exceptions, building entrances shall be protected with an enclosed vestibule, with all doors opening into and out of the vestibule equipped with self-closing devices as per IECC Section C402.5.7. Provide compliance option used for IECC commercial of spaces under this permit. For example, the Future Res Lobby appears over the allowable budgt factor for interior lighting. Also need additional efficiency package option chosen (similar to tenant spaces), exterior lighting calculation and electrical plans updated with mandatory lighting controls and location(s) of occupant sensor controls.
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet (4877 mm) above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches (762 mm) in height or walking on roofs having a slope greater than 4four units vertical in 12 units horizontal (33-percent slope). Such access shall not require the use of portable ladders as per IMC Section 306.5 Equipment and appliances on roofs or elevated structures. Also note if RTU 4 is still needed and if it is resting on new patio.
|
|||
| Revised Drawings reflecting the reduced scope of work (no longer completing an addition with a mezzanine, no longer furnishing a commercial kitchen, etc.) | |||
| Planning Review | Failed | 01/12/2023 | 01/09/2023 |
|
Kelly Douglas, AICP
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
Significant changes are proposed with this addendum to the uses and floor plan approved with DPVC-21-06. Substantial Conformance approval is required prior to approval of this addendum.
|
|||
|
Miscellaneous
Carried Forward
02/13/2023
Please provide a narrative that clearly explains each change proposed with this addendum.
|
|||
| Revised Drawings reflecting the reduced scope of work (no longer completing an addition with a mezzanine, no longer furnishing a commercial kitchen, etc.) | |||
| Engineering Review | Approved | 08/04/2022 | 08/03/2022 |
|
Emrick Soltis, P.E., CFM
|
|||
|
Miscellaneous
Resolved
08/03/2022
DPVC-21-06 Condition of Approval #1 to be resolved prior to construction permit approval. DPVC-21-06 Condition of Approval #1: "The developer shall pay proportionate share of potential future roadway and/or intersection improvements at Downhill Drive/US40 intersection, calculated at 1.29% of $7,441,409.92 or $95,994.20. Payment shall be submitted prior to issuance of building permit."
|
|||
| Planning Review | Approved | 08/04/2022 | 08/03/2022 |
|
Kelly Douglas, AICP
|
|||
|
Miscellaneous
Resolved
08/03/2022
DPVC-21-06 Condition of Approval #1 to be resolved prior to construction permit approval. DPVC-21-06 Condition of Approval #1: "The developer shall pay proportionate share of potential future roadway and/or intersection improvements at Downhill Drive/US40 intersection, calculated at 1.29% of $7,441,409.92 or $95,994.20. Payment shall be submitted prior to issuance of building permit."
|
|||
| Building Code Review | Failed | 02/25/2022 | 08/02/2022 |
|
Todd Carr
|
|||
|
See Document Markups
Resolved
02/18/2022
The 1st submittal appears to be missing Civil Plans. Note that approved Civil plans are required prior to issuance of permits including Foundation Only. Please submit Civil plans that are complete for review and approval by RCRBD.
|
|||
|
See Document Markups
Resolved
02/18/2022
The objective of the phased permitting process is to allow construction to begin on large projects while remaining design details are approved. This approach allows the applicant to phase the permitting process while establishing obtainable deadlines for meeting Federal, State, and local requirements. When I asked Todd about the Party Wall that is shown in Detail 4/A0331 and at first he said we were specifically asked not to approve any work for Phase 1B. Detail 4/A0331 shows 2 NEW LAYERS TYPE-X GWB and therefore the hesitation in approving this work. Please remove work shown in Phase 1A documents such as but not limited to Party Wall. Also we ask statements be filed with RCRBD complying with pertinent requirements in accordance with IBC Section 107.3.3 and acknowledge as the holder of such permit for the parts or phase of a building or structure materials and details to safely proceed at the holder's own risk with the building operation and without assurance that a permit for the entire structure will be granted.
|
|||
|
Miscellaneous
Carried Forward
08/02/2022
Routt County Regional Building Department typically only reviews Civil Plans on certain sheets, such as the main site plan in most cases, that would show building setbacks, parking, accessible routes, etc. Provide site plan that shows continuous, unobstructed path of accessible route(s) from public transportation stops, accessible parking, accessible passenger loading zones, and public streets or sidewalks that complies with Chapter 11 to the building entrance(s) and egress doors served as applicable. Accessible routes shall be designed per ANSI A117 and designated graphically on the site plan complete with details of walking surfaces not be steeper than 1:20 unless a compliant ramp is proposed. The cross slope of a walking surface (and ramps) shall not be steeper than 1:48. This was not done, start with labelling all accessible building entrance(s) on accessible routes(s). Building entrances must be connected by an accessible route to public and common use areas that must be accessible include, but are not limited to, such spaces and elements as selected on-site walks, parking, aprons, rental offices, mailbox areas, trash/refuse disposal areas with at least one dumpster being accessible, and portions of common use tenant patio and picnic tables. Certain building entrances may be inaccessible if impractical based on site tests. Then provide accessible routes graphically on the site plan complete with details of floor surfaces (pavers, concrete and asphalt) not be steeper than 1:20 unless a compliant ramp is proposed. The cross slope of a walking surface (and ramps) shall not be steeper than 1:48 but adequate to prevent ice build-up. Include details of ramp(s) with guard and handrails per ANSI A119.5-15.
|
|||
| Engineering Review | Failed | 02/25/2022 | 08/02/2022 |
|
Todd Carr
|
|||
|
Miscellaneous
Carried Forward
08/02/2022
DPVC-21-06 Condition of Approval #1 to be resolved prior to construction permit approval. DPVC-21-06 Condition of Approval #1: "The developer shall pay proportionate share of potential future roadway and/or intersection improvements at Downhill Drive/US40 intersection, calculated at 1.29% of $7,441,409.92 or $95,994.20. Payment shall be submitted prior to issuance of building permit."
|
|||
| Traffic Contribution needs to be paid | |||
| Planning Review | Failed | 02/25/2022 | 08/02/2022 |
|
Todd Carr
|
|||
|
Miscellaneous
Carried Forward
08/02/2022
DPVC-21-06 Condition of Approval #1 to be resolved prior to construction permit approval. DPVC-21-06 Condition of Approval #1: "The developer shall pay proportionate share of potential future roadway and/or intersection improvements at Downhill Drive/US40 intersection, calculated at 1.29% of $7,441,409.92 or $95,994.20. Payment shall be submitted prior to issuance of building permit."
|
|||
| Intersection improvement contribution amount due adjusted to $76,795.36 (proportional to phasing). Payment is required prior to approval. | |||
| Building Code Review | Approved | 08/04/2022 | 08/02/2022 |
|
Todd Carr
|
|||
|
Miscellaneous
Outstanding
08/02/2022
Routt County Regional Building Department typically only reviews Civil Plans on certain sheets, such as the main site plan in most cases, that would show building setbacks, parking, accessible routes, etc. Provide site plan that shows continuous, unobstructed path of accessible route(s) from public transportation stops, accessible parking, accessible passenger loading zones, and public streets or sidewalks that complies with Chapter 11 to the building entrance(s) and egress doors served as applicable. Accessible routes shall be designed per ANSI A117 and designated graphically on the site plan complete with details of walking surfaces not be steeper than 1:20 unless a compliant ramp is proposed. The cross slope of a walking surface (and ramps) shall not be steeper than 1:48. This was not done, start with labelling all accessible building entrance(s) on accessible routes(s). Building entrances must be connected by an accessible route to public and common use areas that must be accessible include, but are not limited to, such spaces and elements as selected on-site walks, parking, aprons, rental offices, mailbox areas, trash/refuse disposal areas with at least one dumpster being accessible, and portions of common use tenant patio and picnic tables. Certain building entrances may be inaccessible if impractical based on site tests. Then provide accessible routes graphically on the site plan complete with details of floor surfaces (pavers, concrete and asphalt) not be steeper than 1:20 unless a compliant ramp is proposed. The cross slope of a walking surface (and ramps) shall not be steeper than 1:48 but adequate to prevent ice build-up. Include details of ramp(s) with guard and handrails per ANSI A119.5-15.
|
|||
|
See Document Markups
Outstanding
01/10/2023
Architectural plans shall be resubmitted when signed and sealed as per CO State Law with correct date.
|
|||
|
See Document Markups
Outstanding
01/10/2023
The occupant load of Gymnasium and also lobby require two exits. The electrical plans referenced show two exits, however the door swing from the Phase 1b doors and inspected under 1a is incorrect and either needs to be corrected or illumination eliminated. The doors for water and electircal room rating of 20 minutes is incorrect, do any of these need to swing out? Either way, panic and fire exit hardware shall be provided as applicable to all doors regardless of phase. Please update Code Analysis on Sheet G0003, submit hardware set(s) referenced in Door Schedule and Electrical revisions as applicable.
|
|||
|
See Document Markups
Outstanding
01/10/2023
According to the Life Safety Plan on Sheet G0005, occupancy separations are shown with a 1 Hour rating. Please state the charging language from code for these and why the Storage room A106 is unrated. For example this could be sprinklered along with the rest of the VB building as declared on Sheet G0003. Either way, show materials of construction, whether non-rated and fire resistance rated assemblies, and fire resistance provided for penetrations, similar to the gas piping clarification requested under Phase 1b - gas main location, how the main is regulated, enters the building and how certain fire-resistive structures are protected that is still outstanding (expected 9/15/22).
|
|||
| New site plan under the 5-story neighboring building has taken care of the ada site plan issues. | |||
| Utilities Review - City | Approved | 02/25/2022 | 02/24/2022 |
|
Amber Gregory
|
|||
|
Miscellaneous
Outstanding
02/17/2022
Tap fee assessment sent to applicant. Needs tap fees paid.
|
|||
|
Miscellaneous
Outstanding
02/17/2022
approved plans need uploaded
|
|||
| Engineering Review | TCO Approved | 02/10/2022 | 02/14/2022 |
|
Stuart King, P.E.
|
|||
|
Miscellaneous
Carried Forward
02/17/2022
DPVC-21-06 Condition of Approval #1 to be resolved prior to construction permit approval. DPVC-21-06 Condition of Approval #1: "The developer shall pay proportionate share of potential future roadway and/or intersection improvements at Downhill Drive/US40 intersection, calculated at 1.29% of $7,441,409.92 or $95,994.20. Payment shall be submitted prior to issuance of building permit."
|
|||
| Utilities Review - City | TCO Approved | 02/10/2022 | 02/10/2022 |
|
Amber Gregory
|
|||
|
Miscellaneous
Resolved
02/24/2022
Tap fee assessment sent to applicant. Needs tap fees paid.
|
|||
|
Miscellaneous
Resolved
02/24/2022
approved plans need uploaded
|
|||
| Building Code Review | TCO Approved | 02/10/2022 | 02/10/2022 |
|
Ted Allen
|
|||
|
See Document Markups
Carried Forward
02/10/2022
While a 2-HR rated Fire Wall appears inadequate, IBC Section 503.1.2 Buildings on same lot presents an additional option where two or more buildings on the same lot shall be regulated as separate buildings. For example, the fire wall becomes two exterior walls and per 503.1.2 walls and openings in exterior walls shall comply with Tables 601 and 602. The distance to an adjacent lot line shall be determined in accordance with Table 602 and Section 705. In this instance the existing wood shear wall and new exterior wall constructed under Phase 1b would be constructed not less than the fire-resistance rating based on fire separation distance (as required by Table 602 for exterior walls based on the fire separation distance) and continue to parapets provided on exterior walls of buildings (see IBC Section 705) and insulation added per code. RCRBD is prepared to allow the imaginary lot line to extend vertically only where two exterior walls exist thereby allowing for openings in the upper stories in the 1b structure if allowed by the Architect. Todd Carr Notes: We would accept the 3-Hour Rated Wall to be made up of two independent fire walls, where the existing building exterior wall would become a 1-hour rated wall assembly that would require drywall to be installed on both sides of the existing building walls, so find an assembly where you cover the 3/4" plywood shear wall on the north side of the existing wall you want to keep. Then find a 2-hour rated wall assembly you can construct for the new building which will need to meet the requirements for parapets as well. Also review those existing window openings on the raised roof area of the existing building, to see these will be allowed in close proximity to the the area separation fire wall.
Applicant Response. Thank you, and noted for future “Area 1B” permit submission. The permit submission in question does not require a fire wall at Column Line 10, as the entire building is Type V-B, as exists.
RCRBD finds this direction as proposed to be flawed as in the example when a townhouse is constructed only as a duplex and friction is developed when it counts and after the fact. There is a need to understand what we are being asked to approve, for example it appears you are adding a layer of drywall but no rated assembly is specified inside or out? Why is the head of wall non-rated at this time while it is under construction and inspected by Routt County? Todd agrees, either the Party Wall comes out of the plans completely or upgraded to a tested assembly for some future purpose.
|
|||
|
See Document Markups
Carried Forward
02/10/2022
Required second exit door now shown with exit signs and emergency lighting.
|
|||
|
See Document Markups
Resolved
02/10/2022
Provide kitchen equipment shown 'by others" on mechanical plans. While sheets M2.31 and M4.11 have been revised, see Detail 4/M4.12 for kitchen equipment shown 'by others".
|
|||
|
See Document Markups
Carried Forward
02/17/2022
The 1st submittal appears to be missing Civil Plans. Note that approved Civil plans are required prior to issuance of permits including Foundation Only. Please submit Civil plans that are complete for review and approval by RCRBD.
|
|||
|
See Document Markups
Carried Forward
02/17/2022
The objective of the phased permitting process is to allow construction to begin on large projects while remaining design details are approved. This approach allows the applicant to phase the permitting process while establishing obtainable deadlines for meeting Federal, State, and local requirements. When I asked Todd about the Party Wall that is shown in Detail 4/A0331 and at first he said we were specifically asked not to approve any work for Phase 1B. Detail 4/A0331 shows 2 NEW LAYERS TYPE-X GWB and therefore the hesitation in approving this work. Please remove work shown in Phase 1A documents such as but not limited to Party Wall. Also we ask statements be filed with RCRBD complying with pertinent requirements in accordance with IBC Section 107.3.3 and acknowledge as the holder of such permit for the parts or phase of a building or structure materials and details to safely proceed at the holder's own risk with the building operation and without assurance that a permit for the entire structure will be granted.
|
|||
|
Miscellaneous
Carried Forward
02/17/2022
Routt County Regional Building Department typically only reviews Civil Plans on certain sheets, such as the main site plan in most cases, that would show building setbacks, parking, accessible routes, etc. Provide site plan that shows continuous, unobstructed path of accessible route(s) from public transportation stops, accessible parking, accessible passenger loading zones, and public streets or sidewalks that complies with Chapter 11 to the building entrance(s) and egress doors served as applicable. Accessible routes shall be designed per ANSI A117 and designated graphically on the site plan complete with details of walking surfaces not be steeper than 1:20 unless a compliant ramp is proposed. The cross slope of a walking surface (and ramps) shall not be steeper than 1:48.
|
|||
| Planning Review | TCO Approved | 02/10/2022 | 02/08/2022 |
|
Kelly Douglas, AICP
|
|||
|
Miscellaneous
Resolved
02/08/2022
Building Permit not approved yet. CV-21-06 must be approved first.
|
|||
|
Miscellaneous
Carried Forward
02/17/2022
DPVC-21-06 Condition of Approval #1 to be resolved prior to construction permit approval. DPVC-21-06 Condition of Approval #1: "The developer shall pay proportionate share of potential future roadway and/or intersection improvements at Downhill Drive/US40 intersection, calculated at 1.29% of $7,441,409.92 or $95,994.20. Payment shall be submitted prior to issuance of building permit."
|
|||
| Construction Site Management Review | Approved | 02/10/2022 | 02/03/2022 |
|
Scott Slamal
|
|||
|
Miscellaneous
Outstanding
02/03/2022
CSMP required for this project along with completed CSMP checklist. Civil plans need to be uploaded also for further review.
|
|||
| Engineering Review | TCO Approved | 01/04/2022 | 01/07/2022 |
|
Stuart King, P.E.
|
|||
|
Miscellaneous
Resolved
02/14/2022
Upload approved civil site plans CV-21-06.
|
|||
| Utilities Review - City | TCO Approved | 01/04/2022 | 01/05/2022 |
|
Amber Gregory
|
|||
|
Miscellaneous
Resolved
01/04/2022
Existing floor plan must show existing utilities for proper assessment (i.e. toilets, water fountains, sinks, etc.)
|
|||
|
Miscellaneous
Resolved
01/04/2022
Proposed kitchen must show all fixtures (i.e. hand sink, 3 compartment sink, dishwasher, etc.). Laundry room must show number of washing machines for proper tap fee assessment.
|
|||
|
Miscellaneous
Carried Forward
02/03/2022
Tap fee assessment sent to applicant. Needs tap fees paid.
|
|||
|
Miscellaneous
Carried Forward
02/03/2022
approved plans need uploaded
|
|||
| Planning Review | TCO Approved | 01/04/2022 | 01/04/2022 |
|
Kelly Douglas, AICP
|
|||
|
Miscellaneous
Carried Forward
02/03/2022
Building Permit not approved yet. CV-21-06 must be approved first.
|
|||
| External Agencies Review | Approved | 01/04/2022 | 01/04/2022 |
|
Malea Michael-Ferrier
|
|||
| Environmental Health: Approved. See attached document titled Env Health Approval letter. | |||
| Building Code Review | TCO Approved | 01/04/2022 | 12/29/2021 |
|
Ted Allen
|
|||
|
See Document Markups
Resolved
12/29/2021
The required capacity of stairways shall be determined as specified in Section 1005.1, but the minimum width shall be not less than 48 inches (1219 mm). See Section 1009.3 for accessible means of egress stairways.
|
|||
|
See Document Markups
Resolved
12/29/2021
72' total exit travel from mezz OK
|
|||
|
See Document Markups
Carried Forward
02/03/2022
While a 2-HR rated Fire Wall appears inadequate, IBC Section 503.1.2 Buildings on same lot presents an additional option where two or more buildings on the same lot shall be regulated as separate buildings. For example, the fire wall becomes two exterior walls and per 503.1.2 walls and openings in exterior walls shall comply with Tables 601 and 602. The distance to an adjacent lot line shall be determined in accordance with Table 602 and Section 705. In this instance the existing wood shear wall and new exterior wall constructed under Phase 1b would be constructed not less than the fire-resistance rating based on fire separation distance (as required by Table 602 for exterior walls based on the fire separation distance) and continue to parapets provided on exterior walls of buildings (see IBC Section 705) and insulation added per code. RCRBD is prepared to allow the imaginary lot line to extend vertically only where two exterior walls exist thereby allowing for openings in the upper stories in the 1b structure if allowed by the Architect. Todd Carr Notes: We would accept the 3-Hour Rated Wall to be made up of two independent fire walls, where the existing building exterior wall would become a 1-hour rated wall assembly that would require drywall to be installed on both sides of the existing building walls, so find an assembly where you cover the 3/4" plywood shear wall on the north side of the existing wall you want to keep. Then find a 2-hour rated wall assembly you can construct for the new building which will need to meet the requirements for parapets as well. Also review those existing window openings on the raised roof area of the existing building, to see these will be allowed in close proximity to the the area separation fire wall.
Applicant Response. Thank you, and noted for future “Area 1B” permit submission. The permit submission in question does not require a fire wall at Column Line 10, as the entire building is Type V-B, as exists.
RCRBD finds this direction as proposed to be flawed as in the example when a townhouse is constructed only as a duplex and friction is developed when it counts and after the fact. There is a need to understand what we are being asked to approve, for example it appears you are adding a layer of drywall but no rated assembly is specified inside or out? Why is the head of wall non-rated at this time while it is under construction and inspected by Routt County?
|
|||
|
See Document Markups
Resolved
12/29/2021
RCRBD finds dimensions provided to be insufficient for verification of min code items. When certain accessibility features are provided on plan (turn circles, etc.) the barriers of accessibility may be determined and exception shall be discussed in the code analysis. Take the mezzanine for example; are the stairs accessible, or the upstairs shower? State the exception used.
|
|||
|
See Document Markups
Resolved
12/29/2021
Is shower room 114 required to be accessible? Provide additional details of accessibility or exception.
|
|||
|
See Document Markups
Carried Forward
02/03/2022
Required second exit door is not shown with exit signs or emergency lighting. Provide details of all required panic hardware providing free egress at all times on the plans.
Plans submitted do not appear revised to show exit sign and emergency lighting for the required second exit door, See sheet E2.11 for required exit on Grid A between Grids 3 and 5. This condition has been reported by Routt County inspectors when it comes up during Final Inspections and Fails because there are no exit lights and everything is drywalled. A similar issue comes up with the exit door hardware, please furnish door hardware schedule to RCRBD for review.
|
|||
|
See Document Markups
Resolved
12/29/2021
The statement above that automatic sprinkler system not required appears to RCRBD as incorrect. Provide type of system to be provided or exemption(s) used.
|
|||
|
See Document Markups
Carried Forward
12/29/2021
Many of the listed assemblies are “Proprietary,” meaning that very specific brand name products must be used in the construction of the assemblies. Use of these assemblies with substitute materials raises the question of whether the alternates exhibit or exceed the properties of the listed product. Substitutions shall be submitted the Architect and approved prior to submittal to the Building Official for review and approval.
Also note the code requires between dwelling units and public areas to have a minimum sound transmission class (STC) of 49. Materials and methods of construction used to protect joints and penetrations in fire-resistance-rated building elements shall not reduce the required fire-resistance rating. Submit required fire resistive assemblies to include the F and T rating criteria for penetration firestop systems in accordance with ASTM E 814 for head conditions, through penetrations, membrane penetrations and the rated wall assemblies themselves.
Applicant Response. Code Matrix updated to specify ASTM E814 at all fire rated penetrations. Remainder of comment is in reference to a future phase, and all guidance provided will be adhered to.
|
|||
|
See Document Markups
Carried Forward
02/03/2022
Provide kitchen equipment shown 'by others" on mechanical plans. While sheets M2.31 and M4.11 have been revised, see Detail 4/M4.12 for kitchen equipment shown 'by others".
|
|||
|
See Document Markups
Carried Forward
02/03/2022
The 1st submittal appears to be missing Civil Plans. Note that approved Civil plans are required prior to issuance of permits including Foundation Only. Please submit Civil plans that are complete for review and approval by RCRBD.
|
|||
| Construction Site Management Review | TCO Approved | 01/04/2022 | 12/23/2021 |
|
Scott Slamal
|
|||
|
Miscellaneous
Carried Forward
02/03/2022
CSMP required for this project along with completed CSMP checklist. Civil plans need to be uploaded also for further review.
|
|||
| External Agencies Review | TCO Approved | 12/13/2021 | 12/15/2021 |
|
Malea Michael-Ferrier
|
|||
| Other / Miscellaneous Environmental Health: You will need to complete our retail food application (attached) and apply for a retail food license (also attached). Here’s the link with more info: http://co.routt.co.us/490/Open-or-Remodel-a-Restaurant, which is also copied here: According to the Colorado Retail Food Establishment Rules & Regulations, a ‘Retail Food Establishment’ is defined as a retail operation that stores, prepares, or packages food for human consumption or serves or otherwise provides food for human consumption to consumers directly or indirectly through a delivery service, whether such food is consumed on or off the premises or whether there is a charge for such food. The following information outlines processes involved in the construction or remodel of your retail food establishment. Please contact the Building Department in your jurisdiction for building permit requirements. 1. Fill out a Plan Review Form online or visit us at 136 6th St., 2nd Floor, Steamboat Springs. 2. Submit the completed application and $200 fee made payable to Routt County Treasurer. Include a floor plan, proposed menu, plumbing details, equipment list and specification (cut) sheets so we can verify National Sanitation Foundation (NSF) approval. 3. A minimum of two weeks is necessary to review your plans. Construction and/or operation must not begin until your plans have been approved and you have received notification in writing. 4. Schedule a pre-operational inspection. During this pre-operational inspection, you’ll be given a Retail Food Service License Application requesting your State of Colorado Sales Tax License Number, Federal Employer Identification Number, type of ownership, and name of your establishment. The fee for operating a food service establishment is based on seating capacity for restaurants and square footage for grocery stores. Operating fees and applications will be collected at the pre-operational inspection. Food service licenses are not transferable and must be renewed in January of each year. If the restaurant is sold at any time during the year, the new owners must pay for a new license in their name. Thank you, Heather L. Savalox, MPA, REHS Senior Environmental Health Specialist Routt County Department of Environmental Health 136 6th St., Suite 201 Steamboat Springs, CO 80487 office (970) 870-5588 | |||
| Building Code Review | TCO Approved | 12/10/2021 | 12/13/2021 |
|
Todd Carr
|
|||
|
See Document Markups
Carried Forward
12/23/2021
The required capacity of stairways shall be determined as specified in Section 1005.1, but the minimum width shall be not less than 48 inches (1219 mm). See Section 1009.3 for accessible means of egress stairways.
|
|||
|
See Document Markups
Carried Forward
12/23/2021
72' total exit travel from mezz OK
|
|||
|
See Document Markups
Carried Forward
02/10/2022
While a 2-HR rated Fire Wall appears inadequate, IBC Section 503.1.2 Buildings on same lot presents an additional option where two or more buildings on the same lot shall be regulated as separate buildings. For example, the fire wall becomes two exterior walls and per 503.1.2 walls and openings in exterior walls shall comply with Tables 601 and 602. The distance to an adjacent lot line shall be determined in accordance with Table 602 and Section 705. In this instance the existing wood shear wall and new exterior wall constructed under Phase 1b would be constructed not less than the fire-resistance rating based on fire separation distance (as required by Table 602 for exterior walls based on the fire separation distance) and continue to parapets provided on exterior walls of buildings (see IBC Section 705) and insulation added per code. RCRBD is prepared to allow the imaginary lot line to extend vertically only where two exterior walls exist thereby allowing for openings in the upper stories in the 1b structure if allowed by the Architect. Todd Carr Notes: We would accept the 3-Hour Rated Wall to be made up of two independent fire walls, where the existing building exterior wall would become a 1-hour rated wall assembly that would require drywall to be installed on both sides of the existing building walls, so find an assembly where you cover the 3/4" plywood shear wall on the north side of the existing wall you want to keep. Then find a 2-hour rated wall assembly you can construct for the new building which will need to meet the requirements for parapets as well. Also review those existing window openings on the raised roof area of the existing building, to see these will be allowed in close proximity to the the area separation fire wall.
|
|||
|
See Document Markups
Carried Forward
12/23/2021
RCRBD finds dimensions provided to be insufficient for verification of min code items. When certain accessibility features are provided on plan (turn circles, etc.) the barriers of accessibility may be determined and exception shall be discussed in the code analysis. Take the mezzanine for example; are the stairs accessible, or the upstairs shower? State the exception used.
|
|||
|
See Document Markups
Carried Forward
12/23/2021
Is shower room 114 required to be accessible? Provide additional details of accessibility or exception.
|
|||
|
See Document Markups
Outstanding
02/10/2022
Provide details of all required panic hardware providing free egress at all times on the plans.
|
|||
|
See Document Markups
Carried Forward
12/23/2021
The statement above that automatic sprinkler system not required appears to RCRBD as incorrect. Provide type of system to be provided or exemption(s) used.
|
|||
|
See Document Markups
Carried Forward
12/23/2021
Many of the listed assemblies are “Proprietary,” meaning that very specific brand name products must be used in the construction of the assemblies. Use of these assemblies with substitute materials raises the question of whether the alternates exhibit or exceed the properties of the listed product. Substitutions shall be submitted the Architect and approved prior to submittal to the Building Official for review and approval.
Also note the code requires between dwelling units and public areas to have a minimum sound transmission class (STC) of 49. Materials and methods of construction used to protect joints and penetrations in fire-resistance-rated building elements shall not reduce the required fire-resistance rating. Submit required fire resistive assemblies to include the F and T rating criteria for penetration firestop systems in accordance with ASTM E 814 for head conditions, through penetrations, membrane penetrations and the rated wall assemblies themselves.
|
|||
|
See Document Markups
Carried Forward
12/23/2021
Provide kitchen equipment shown 'by others" on mechanical plans
|
|||
|
See Document Markups
Carried Forward
12/23/2021
The 1st submittal appears to be missing Civil Plans. Note that approved Civil plans are required prior to issuance of permits including Foundation Only. Please submit Civil plans that are complete for review.
|
|||
| Electrical Review | Approved | 12/10/2021 | 12/10/2021 |
|
Tom Cook
|
|||
| Utilities Review - City | TCO Approved | 12/10/2021 | 12/09/2021 |
|
Amber Gregory
|
|||
|
Miscellaneous
Carried Forward
12/23/2021
Existing floor plan must show existing utilities for proper assessment (i.e. toilets, water fountains, sinks, etc.)
|
|||
|
Miscellaneous
Carried Forward
12/23/2021
Proposed kitchen must show all fixtures (i.e. hand sink, 3 compartment sink, dishwasher, etc.). Laundry room must show number of washing machines for proper tap fee assessment.
|
|||
| Planning Review | TCO Approved | 12/10/2021 | 12/09/2021 |
|
Kelly Douglas, AICP
|
|||
|
Miscellaneous
Carried Forward
12/23/2021
Building Permit not approved yet. CV-21-06 must be approved first.
|
|||
| Construction Site Management Review | TCO Approved | 12/10/2021 | 12/06/2021 |
|
Scott Slamal
|
|||
|
Miscellaneous
Carried Forward
12/23/2021
CSMP required for this project along with completed CSMP checklist
|
|||
| Engineering Review | TCO Approved | 12/10/2021 | 12/06/2021 |
|
Stuart King, P.E.
|
|||
|
Miscellaneous
Carried Forward
12/23/2021
Upload approved civil site plans CV-21-06.
|
|||
| Fire Code Review | Approved | 12/10/2021 | 11/24/2021 |
|
Matt Workman
|
|||
| Conditionally Approved – pending deferred submittal of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net MW | |||
| Finance Department Review | Approved | 12/10/2021 | 11/22/2021 |
|
Sondra Spratta
|
|||
| City taxes and fees $77,625.00 | |||
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 08/12/2022 | ||
| Todd Carr | ||||
| Structural Inspection | Partial Pass | 5/9/2023 | 5/9/2023 | 05/09/2023 |
| Ron Norton | ||||
| Footing Inspection | Partial Pass | 5/16/2023 | 5/16/2023 | 05/16/2023 |
| Silas Ebbert | ||||
| Insulation Inspection | Partial Pass | 5/18/2023 | 5/19/2023 | 05/19/2023 |
| Silas Ebbert | ||||
| Foundation Inspection | Partial Pass | 5/18/2023 | 5/19/2023 | 05/19/2023 |
| Silas Ebbert | ||||
| Drywall Inspection | Partial Pass | 5/26/2023 | 5/26/2023 | 05/26/2023 |
| Todd Carr | ||||
| Insulation Inspection | Partial Pass | 5/31/2023 | 5/31/2023 | 05/31/2023 |
| Silas Ebbert | ||||
| Foundation Inspection | Partial Pass | 6/7/2023 | 6/7/2023 | 06/07/2023 |
| Silas Ebbert | ||||
| Structural Inspection | Partial Pass | 6/16/2023 | 6/16/2023 | 06/16/2023 |
| Silas Ebbert | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
06/16/2023
Building Department Corrections to be Completed
1. Need to add 2x6 blocking and A35 clips between trusses on top of new shear wall
|
||||
| Footing Inspection | Partial Pass | 6/20/2023 | 6/20/2023 | 06/20/2023 |
| Ron Norton | ||||
| Drywall Inspection | Partial Pass | 6/20/2023 | 6/20/2023 | 06/20/2023 |
| Ron Norton | ||||
| Structural Inspection | Partial Pass | 7/3/2023 | 7/3/2023 | 07/03/2023 |
| Jeff Yeiser | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
07/03/2023
Building Department Corrections to be Completed
1. Need to add 2x6 blocking and A35 clips between trusses on top of new shear wall
|
||||
| Framing Inspection | Partial Pass | 7/6/2023 | 7/7/2023 | 07/07/2023 |
| Ron Norton | ||||
| Drywall Inspection | Partial Pass | 7/13/2023 | 7/13/2023 | 07/13/2023 |
| Ron Norton | ||||
| Drywall Inspection | Partial Pass | 7/19/2023 | 7/19/2023 | 07/19/2023 |
| Ron Norton | ||||
| Insulation Inspection | Partial Pass | 7/25/2023 | 7/25/2023 | 07/25/2023 |
| Silas Ebbert | ||||
| Drywall Inspection | Partial Pass | 8/2/2023 | 8/2/2023 | 08/02/2023 |
| Silas Ebbert | ||||
| Framing Inspection | Partial Pass | 9/11/2023 | 9/11/2023 | 09/11/2023 |
| Ron Norton | ||||
| Drywall Inspection | Partial Pass | 9/15/2023 | 9/15/2023 | 09/15/2023 |
| Ron Norton | ||||
| Building Final Inspection | Not Ready | 10/24/2023 | 10/24/2023 | 10/25/2023 |
| Todd Carr | ||||
| Building Final Inspection | Partial Pass | 11/22/2023 | 11/22/2023 | 11/22/2023 |
| Todd Carr | ||||
| Building Final Inspection | Partial Pass | 12/14/2023 | 12/14/2023 | 12/14/2023 |
| Silas Ebbert | ||||
| Building Final Inspection | Partial Pass | 1/16/2024 | 1/16/2024 | 01/16/2024 |
| Silas Ebbert | ||||
| Building Final Inspection | Passed | 8/15/2024 | 08/15/2024 | |
| Silas Ebbert | ||||
| Condition | Status | Category |
|---|---|---|
| Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
|
Finance
Use Tax Reconciliation
|
||
| Miscellaneous Conditions | Resolved | Prior to Rough Building Wall Inspections |
|
Fire Prevention
Conditionally Approved – pending deferred submittal of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net MW
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
|
Fire Prevention
Must pass alarm & sprinkler final inspections before CC sign-off.
|
||
| Miscellaneous Conditions | Resolved | |
|
Planning Department
Please see DPVC-21-06 conditions of approval. All conditions shall be resolved by the specified time.
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
|
Planning Department
At the time of project completion, request certificate of occupancy inspections from the Department of Planning and Community Development to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, landscaping and revegetation, outdoor lighting, parking and parking lot striping, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Full Building Permit Issuance |
|
Building Department
Prior to Permit Issuance, we must receive for review the new submittal of the area separation fire wall that separates this building from the new 5-story building, this will need to be reviewed and approved by RCRBD prior to Issuance.
RESOLVED AND FULL PERMIT APPROVED 2/24/2023 TA
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Issuance of TCO/CO/CC |
|
Building Department
Prior to TCO of this building and space, an addendum shall be submitted to RCRBD for the area separation fire wall and must be completed prior to TCO for the 5-story building under 220151.
|
||
| Miscellaneous Conditions | Resolved | |
|
Fire Prevention
Addendum dated 1/12/23 - It is not clear how this will change sprinkler and alarm coverage. Resubmit.
|
||
| Miscellaneous Conditions | Resolved | |
|
Fire Prevention
Conditionally Approved –NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
|
Building Department
Environmental Health needs to inspect and license the Golf Simulator tenant finish space for retail food prior to TCO
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Issuance of CO/CC |
|
Building Department
Building Department Conditions to be Completed: Submit TAB Report for HVAC system
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Issuance of CO/CC |
|
Building Department
TCO Approved for Golf Simulator Unit #2
1. Complete Final inspections for all other units.
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Issuance of CO/CC |
|
Building Department
Building Department Conditions to be Completed
1. Submit a final As-Built Set of Architectural, MEP plans and Structrural for the entire building and all tennant finish areas that are listed under this permit, so we have one complete set of drawings.
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
|
Building Department
Environmental Health Plan Review fee of $200.00 required. Submit directly to Routt County Environmental Health https://www.co.routt.co.us/162/Food-Service . Environmental Health Pre-operational inspection also required.
|
||
| Fire Assemblies Deferred Submittal | Resolved | Prior to Rough Building Wall Inspections |
|
Fire Prevention
Tenant finish for Big Iron Coffee. Conditionally Approved –NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms [Nick Brookshire @ 06/12/2024 9:34 AM]
|
||
| Final Fire Inspection Required | Resolved | Prior to Issuance of CO/CC |
|
Fire Prevention
Tenant finish for Big Iron Coffee. Final Fire Alarm & Sprinkler Inspections Required
|
||
| Reference Number | Status | Type |
|---|---|---|
| SPRPL230305 | Closed | Plumbing |
| SPREL230514 | Closed | Electrical |
| SPRMH231521 | Closed | Mechanical |
| SPREL240805 | Closed | Electrical |
| SPRMH240896 | Closed | Mechanical |
| SPRPL240996 | Closed | Plumbing |