Permit Application Status
SPRSF241394
In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
| Date Returned | Name |
|---|---|
| 11/15/2024 | SOLARSHADINGPLAN_STEAMBOATDUPLEX_AD-2_24042.PDF (Stamped) |
| 07/22/2025 | ARCHITECTURAL 07.15.2025 (Stamped) |
| 07/22/2025 | Narrative for changes 07.15.2025 (Stamped) |
| 11/15/2024 | C3 - SITE PLAN.PDF (Received) (Stamped) |
| 12/04/2024 | 24042_Footing Letter (Stamped) |
| 12/04/2024 | 24042_Foundation Changes Letter (1) (Stamped) |
| 01/02/2025 | StructuralDrawings_Revision2_24042 (Stamped) |
| 01/02/2025 | 24042_Revision 2 Narrative (Stamped) |
| 07/22/2025 | New Header Letter 07.15.2025 (Stamped) |
| 07/22/2025 | Driveway Wall 07.15.2025 (Stamped) |
| 11/15/2024 | Civil Plan Set Revised 10-16-2024 (Stamped) |
| 11/15/2024 | C5 - Utility Plan (Received) (Stamped) |
| 08/25/2025 | 24042_Fire Separation (Stamped) |
| Review Type | Outcome | Est. Completion Date | Completed |
|---|---|---|---|
| Building Code Review | Approved | 09/09/2025 | 09/04/2025 |
|
Todd Carr
|
|||
| Updated Arch, truss layout, truss plans, and engineer's letter. 09.02.2025: All documents have been reviewed and approved. | |||
| Building Code Review | Approved | 09/25/2024 | 08/27/2025 |
|
Todd Carr
|
|||
| New fire assemblies approved for separation between dwelling units. | |||
| Building Code Review | Approved | 08/28/2025 | 08/25/2025 |
|
Todd Carr
|
|||
| 8/22- Fire separation details and information: Addendum approved per adopted code exceptions. | |||
| Planning Review | Approved | 07/22/2025 | 07/22/2025 |
|
Jeremy Brown
|
|||
|
Miscellaneous
Resolved
07/22/2025
|
|||
| See narrative, Driveway wall, Header letter and Architectural Plans dated 07.15.2025 | |||
| Building Code Review | Approved | 07/22/2025 | 07/16/2025 |
|
Ted Allen
|
|||
| See narrative, Driveway wall, Header letter and Architectural Plans dated 07.15.2025 | |||
| Building Code Review | Approved | 01/03/2025 | 01/02/2025 |
|
Ted Allen
|
|||
| 12.26.24 Addendum- see narrative | |||
| Building Code Review | Approved | 12/10/2024 | 12/04/2024 |
|
Ted Allen
|
|||
| 12.3.24 Structural letters | |||
| Utilities Review - City | Approved | 11/13/2024 | 11/14/2024 |
|
Amber Gregory
|
|||
|
Miscellaneous
Resolved
11/14/2024
please provide the square footage of irrigated area as well as number of hose bibs associated with each half of the building for proper tap fee assessment.
|
|||
| Planning Review | Approved | 11/13/2024 | 11/13/2024 |
|
Jeremy Brown
|
|||
|
Miscellaneous
Outstanding
11/06/2024
CDC 436.H.1.b Side loaded garages shall provide windows or other architectural details that mimic the features of the living portion of the dwelling on the facade of the garage facing the street.
|
|||
| Construction Site Management Review | Approved | 11/13/2024 | 11/08/2024 |
|
Scott Slamal
|
|||
|
Miscellaneous
Outstanding
11/06/2024
Add additional check dams along Sundance Ct and Steamboat Blvd.
Remove random strings of straw wattles shown off the property.
|
|||
| Building Code Review | Approved | 11/13/2024 | 11/06/2024 |
|
Ted Allen
|
|||
|
Miscellaneous
Resolved
11/06/2024
The following building codes shall be noted on approved plans, with emphasis on the following items:
2021 International Residential Code Fireplaces, labelled gas vented on plans shall include specifications in addition to type of fuel, tight-fitting doors, outside combustion air and provide for manufacturer’s installation and labelling in bedrooms. Fireplaces located in great room shall also include specifications to include type of fuel, tight-fitting doors, outside combustion air and see our local code amendments for Indoor Wood Burning and Pellet Stove Fireplaces as applicable. Interior divider separation wall shall be provided regardless of whether interior garage or a lot line exists between the two dwelling units or not. Two-family houses are considered duplexes and the notes/specifications shown should reference 2021 IRC Section R302.3 Two-family dwellings and include protection of openings such as bathroom penetrations for plumbing, electrical and mechanical systems as applicable.
|
|||
|
Miscellaneous
Resolved
11/06/2024
2023 State of Colorado Model Electric and Solar Ready Code documents shall include, but are not limited to location and size of the solar-ready zone, EV power transfer infrastructure requirements per 104.2.2 Electric Vehicle Ready and unless HVAC is electric, similar consideration (as applicable) from location of the panel to Electric receptacle or junction box within 3 feet of the combustion equipment or appliances that meets the requirements of Section RE302.5, and pathways for routing of conduit to the electrical service panel and circuits labelled on panel.
Informational: I have set conditions for deferred heat load calculations, and blower door test to be completed with either an Energy Recovery Ventilator (ERV) or Heat Recovery Ventilator (HRV) installed subject to field inspection (STFI). The thickness of ceiling insulation shall be written in inches (mm) on markers that are installed at not less than one for every 300 square feet (28 m2) throughout the attic space as per R303.1.1.1. Buildings with combustible ceiling or roof construction shall have an attic access opening to attic areas in accordance with Section R807.1
|
|||
|
Miscellaneous
Carried Forward
11/06/2024
Retaining wall references 2 tiers of 6' max height boulder walls where a licensed geotechnical engineer, registered in the state of Colorado, shall be appointed to review the feasibility of the dry stack boulder wall alternative presented on this plan sheet. What is meant by this is boulder retaining walls shall be designed to ensure stability against overturning and sliding. Approved structural design shall be designed for a safety factor of 1.5 against lateral sliding, overturning while supporting a surcharge equivalent to service vehicles including fire trucks. Final designs for construction purposes must be performed by a Colorado registered Professional Engineer, submitted to RCRBD using the actual conditions of the proposed site. All plans submitted to RCRBD for review shall be signed and sealed in accordance with Colorado State Law.
|
|||
| Utilities Review - City | Failed | 10/30/2024 | 10/31/2024 |
|
Amber Gregory
|
|||
|
Miscellaneous
Resolved
10/31/2024
Architectural plans state the address is 150 Steamboat Boulevard. Upload the correct arch drawings as well as complete drawings showing the floor plans for tap fee assessment.
|
|||
|
Miscellaneous
Resolved
10/31/2024
Sewer pipe between the building and cleanout is Schedule 40 PVC, not SDR 40. Revise.
|
|||
|
Miscellaneous
Resolved
10/31/2024
Water service calls out a 3/4" split, however the mainline service is identified as 1". Provide a correct callout and identify the new curb stops and any lengths of pipe between the fitting and the curb stops.
|
|||
|
Miscellaneous
Carried Forward
11/06/2024
please provide the square footage of irrigated area as well as number of hose bibs associated with each half of the building for proper tap fee assessment.
|
|||
| Construction Site Management Review | Failed | 10/30/2024 | 10/31/2024 |
|
Scott Slamal
|
|||
|
Miscellaneous
Carried Forward
11/06/2024
Add additional check dams along Sundance Ct and Steamboat Blvd.
Remove random strings of straw wattles shown off the property.
|
|||
| Planning Review | Failed | 10/30/2024 | 10/30/2024 |
|
Jeremy Brown
|
|||
|
Miscellaneous
Resolved
10/30/2024
RN-1 Zone district requires a 20' principal building front setback and a 25' attached garage setback. As a corner lot, it is possible to apply for a setback determination, but that will still require 15' setbacks for the principal building and attached garage. It appears now that you are accounting for 10'
|
|||
|
Miscellaneous
Carried Forward
11/06/2024
CDC 436.H.1.b Side loaded garages shall provide windows or other architectural details that mimic the features of the living portion of the dwelling on the facade of the garage facing the street.
|
|||
|
Miscellaneous
Resolved
10/30/2024
Per access standards in 436.D please show sidewalks from front doors to driveway or public sidewalk.
|
|||
| Building Code Review | Failed | 10/30/2024 | 10/24/2024 |
|
Ted Allen
|
|||
|
Miscellaneous
Carried Forward
11/06/2024
The following building codes shall be noted on approved plans, with emphasis on the following items:
2021 International Residential Code Fireplaces, labelled gas vented on plans shall include specifications in addition to type of fuel, tight-fitting doors, outside combustion air and provide for manufacturer’s installation and labelling in bedrooms. Fireplaces located in great room shall also include specifications to include type of fuel, tight-fitting doors, outside combustion air and see our local code amendments for Indoor Wood Burning and Pellet Stove Fireplaces as applicable. Interior divider separation wall shall be provided regardless of whether interior garage or a lot line exists between the two dwelling units or not. Two-family houses are considered duplexes and the notes/specifications shown should reference 2021 IRC Section R302.3 Two-family dwellings and include protection of openings such as bathroom penetrations for plumbing, electrical and mechanical systems as applicable.
|
|||
|
Miscellaneous
Resolved
10/24/2024
U-factors of windows and doors will be required. This will apply for all glazing in windows and doors installed on-site including large garage doors. The builder shall leave the National Fenestration Rating Council (NFRC) labels on all windows and doors with glazing at time of rough inspections so inspectors can verify the glazing requirements
|
|||
|
Miscellaneous
Resolved
10/24/2024
2021 International Wild-Land Urban Interface Code (metal corrugated roofing must have approved Class A Roofing Material per Section 504.2 Roof Assembly, Roof Eaves and Soffits on commercial and residential new construction buildings only shall be protected on the exposed underside by one of the items per Section 504.3 including non-combustible materials or ignition resistant material in accordance with Section 503.2. Where provided, Gutters and Downspouts shall be constructed of noncombustible material. Attics and enclosed rafter spaces formed where ceilings are applied directly to the underside of roof rafters shall have cross ventilation for each separate space by ventilating openings per R806.1 Ventilation required. Single Soffit Vents shall not exceed 144 square inches each, continuous Soffit Vents shall not exceed 2 ½” in width. Such vents shall be covered with non-combustible corrosion resistant mesh with openings not to exceed ¼”, or shall be designed and approved to prevent flame or ember penetration into the structure as applicable.
|
|||
|
Miscellaneous
Carried Forward
11/06/2024
2023 State of Colorado Model Electric and Solar Ready Code documents shall include, but are not limited to location and size of the solar-ready zone, EV power transfer infrastructure requirements per 104.2.2 Electric Vehicle Ready and unless HVAC is electric, similar consideration (as applicable) from location of the panel to Electric receptacle or junction box within 3 feet of the combustion equipment or appliances that meets the requirements of Section RE302.5, and pathways for routing of conduit to the electrical service panel and circuits labelled on panel.
Informational: I have set conditions for deferred heat load calculations, and blower door test to be completed with either an Energy Recovery Ventilator (ERV) or Heat Recovery Ventilator (HRV) installed subject to field inspection (STFI). The thickness of ceiling insulation shall be written in inches (mm) on markers that are installed at not less than one for every 300 square feet (28 m2) throughout the attic space as per R303.1.1.1. Buildings with combustible ceiling or roof construction shall have an attic access opening to attic areas in accordance with Section R807.1
|
|||
|
Miscellaneous
Carried Forward
11/06/2024
Retaining wall references 2 tiers of 6' max height boulder walls where a licensed geotechnical engineer, registered in the state of Colorado, shall be appointed to review the feasibility of the dry stack boulder wall alternative presented on this plan sheet. What is meant by this is boulder retaining walls shall be designed to ensure stability against overturning and sliding. Approved structural design shall be designed for a safety factor of 1.5 against lateral sliding, overturning while supporting a surcharge equivalent to service vehicles including fire trucks. Final designs for construction purposes must be performed by a Colorado registered Professional Engineer, submitted to RCRBD using the actual conditions of the proposed site. All plans submitted to RCRBD for review shall be signed and sealed in accordance with Colorado State Law.
|
|||
| Planning Review | Failed | 09/26/2024 | 10/02/2024 |
|
Jeremy Brown
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
RN-1 Zone district requires a 20' principal building front setback and a 25' attached garage setback. As a corner lot, it is possible to apply for a setback determination, but that will still require 15' setbacks for the principal building and attached garage. It appears now that you are accounting for 10'
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
CDC 436.H.1.b Side loaded garages shall provide windows or other architectural details that mimic the features of the living portion of the dwelling on the facade of the garage facing the street.
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
Per access standards in 436.D please show sidewalks from front doors to driveway or public sidewalk.
|
|||
| Construction Site Management Review | Failed | 09/25/2024 | 09/27/2024 |
|
Scott Slamal
|
|||
|
Miscellaneous
Outstanding
10/31/2024
Add additional check dams along Sundance Ct and Steamboat Blvd.
|
|||
| Utilities Review - City | Failed | 09/26/2024 | 09/27/2024 |
|
Amber Gregory
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
Architectural plans state the address is 150 Steamboat Boulevard. Upload the correct arch drawings as well as complete drawings showing the floor plans for tap fee assessment.
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
Sewer pipe between the building and cleanout is Schedule 40 PVC, not SDR 40. Revise.
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
Water service calls out a 3/4" split, however the mainline service is identified as 1". Provide a correct callout and identify the new curb stops and any lengths of pipe between the fitting and the curb stops.
|
|||
| GIS Land Development Review | Approved | 09/26/2024 | 09/26/2024 |
|
Colten Yoast
|
|||
| Second address is 202 Sundance Court | |||
| Fire Code Review | Approved | 09/26/2024 | 09/26/2024 |
|
Charles Brookshire
|
|||
| Any fire alarm/sprinkler work will require a permit/plans to be submitted to Fire Prevention. See www.steamboatsprings.net, Fire and EMS Services, Fire Prevention, Downloadable Permits and Forms. NB [Charles Brookshire @ 09/26/2024 3:48 PM] | |||
| External Agencies Review | Approved | 09/26/2024 | 09/26/2024 |
|
Malea Michael-Ferrier
|
|||
| Building Code Review | Failed | 09/26/2024 | 09/25/2024 |
|
Ted Allen
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
The following building codes shall be noted on approved plans, with emphasis on the following items:
2021 International Residential Code (garage shall be sloped to facilitate the movement of liquids to a drain or toward the main vehicle entry doorway. The garage shall be separated from the residence and attics as required by Table R302.6. Openings in garage walls shall comply with Section R302.5 as applicable. Fireplaces, labelled gas vented on plans shall include specifications in addition to type of fuel, tight-fitting doors, outside combustion air and provide for manufacturer’s installation and labelling in bedrooms. Fireplaces located in great room shall also include specifications to include type of fuel, tight-fitting doors, outside combustion air and see our local code amendments for Indoor Wood Burning and Pellet Stove Fireplaces as applicable. Interior divider separation wall shall be provided regardless of whether interior garage or a lot line exists between the two dwelling units or not. Two-family houses are considered duplexes and the notes/specifications shown should reference 2021 IRC Section R302.3 Two-family dwellings and include protection of openings such as bathroom penetrations for plumbing, electrical and mechanical systems as applicable.
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
U-factors of windows and doors will be required. This will apply for all glazing in windows and doors installed on-site including large garage doors. The builder shall leave the National Fenestration Rating Council (NFRC) labels on all windows and doors with glazing at time of rough inspections so inspectors can verify the glazing requirements
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
2021 International Wild-Land Urban Interface Code (metal corrugated roofing must have approved Class A Roofing Material per Section 504.2 Roof Assembly, Roof Eaves and Soffits on commercial and residential new construction buildings only shall be protected on the exposed underside by one of the items per Section 504.3 including non-combustible materials or ignition resistant material in accordance with Section 503.2. Where provided, Gutters and Downspouts shall be constructed of noncombustible material. Attics and enclosed rafter spaces formed where ceilings are applied directly to the underside of roof rafters shall have cross ventilation for each separate space by ventilating openings per R806.1 Ventilation required. Single Soffit Vents shall not exceed 144 square inches each, continuous Soffit Vents shall not exceed 2 ½” in width. Such vents shall be covered with non-combustible corrosion resistant mesh with openings not to exceed ¼”, or shall be designed and approved to prevent flame or ember penetration into the structure as applicable.
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
2023 State of Colorado Model Electric and Solar Ready Code documents shall include, but are not limited to location and size of the solar-ready zone, EV power transfer infrastructure requirements per 104.2.2 Electric Vehicle Ready and unless HVAC is electric, similar consideration (as applicable) from location of the panel to Electric receptacle or junction box within 3 feet of the combustion equipment or appliances that meets the requirements of Section RE302.5, and pathways for routing of conduit to the electrical service panel and circuits labelled on panel.
Informational: I have set conditions for deferred heat load calculations, and blower door test to be completed with either an Energy Recovery Ventilator (ERV) or Heat Recovery Ventilator (HRV) installed subject to field inspection (STFI). The thickness of ceiling insulation shall be written in inches (mm) on markers that are installed at not less than one for every 300 square feet (28 m2) throughout the attic space as per R303.1.1.1. Buildings with combustible ceiling or roof construction shall have an attic access opening to attic areas in accordance with Section R807.1
|
|||
|
Miscellaneous
Carried Forward
10/23/2024
Retaining wall references 2 tiers of 6' max height boulder walls where a licensed geotechnical engineer, registered in the state of Colorado, shall be appointed to review the feasibility of the dry stack boulder wall alternative presented on this plan sheet. What is meant by this is boulder retaining walls shall be designed to ensure stability against overturning and sliding. Approved structural design shall be designed for a safety factor of 1.5 against lateral sliding, overturning while supporting a surcharge equivalent to service vehicles including fire trucks. Final designs for construction purposes must be performed by a Colorado registered Professional Engineer, submitted to RCRBD using the actual conditions of the proposed site. All plans submitted to RCRBD for review shall be signed and sealed in accordance with Colorado State Law. RCRBD interprets this to include all documents such as the Civil Plans prepared by FPSE.
|
|||
| Electrical Review | Approved | 09/26/2024 | 09/20/2024 |
|
Tom Cook
|
|||
| Final approval subject to field inspection | |||
| Finance Department Review | Approved | 09/26/2024 | 09/12/2024 |
|
Sondra Spratta
|
|||
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Foundation/Under Slab Insulation | Pending | |||
| Rough Site Inspection | Pending | |||
| Scott Slamal | ||||
| Roofing Inspection | Pending | |||
| Drywall Inspection | Pending | |||
| Final Site Inspection | Pending | |||
| Scott Slamal | ||||
| Building Final Inspection | Pending | |||
| Lath/Veneer Inspection | Pending | |||
| Foundation Drain Inspection | Pending | |||
| Foundation Inspection | Pending | |||
| Structural Inspection | Pending | |||
| Radon Piping | Pending | |||
| Footing Inspection | Pending | |||
| Footing Inspection | Partial Pass | 11/22/2024 | 11/22/2024 | |
| Ron Norton | ||||
| Foundation Inspection | Not Ready | 12/20/2024 (Afternoon) | 12/27/2024 | 12/27/2024 |
| Ron Norton | ||||
| Foundation Inspection | Partial Pass | 1/16/2025 | 01/16/2025 | |
| Ron Norton | ||||
| Foundation Inspection | Partial Pass | 1/16/2025 | 1/17/2025 | 01/17/2025 |
| Ron Norton | ||||
| Foundation Drain Inspection | Partial Pass | 1/30/2025 | 1/31/2025 | 01/31/2025 |
| Ron Norton | ||||
| Footing Inspection | Partial Pass | 2/18/2025 | 2/19/2025 | 02/19/2025 |
| Ron Norton | ||||
| Foundation Inspection | Partial Pass | 2/20/2025 | 2/21/2025 | 02/21/2025 |
| Jeff Yeiser | ||||
| Foundation Water Proofing | Passed | 02/25/2025 | ||
| Ron Norton | ||||
| Footing Inspection | Partial Pass | 02/25/2025 | ||
| Ron Norton | ||||
| Foundation Drain Inspection | Not Ready | 2/24/2025 | 2/25/2025 | 02/25/2025 |
| Ron Norton | ||||
| Foundation Drain Inspection | Partial Pass | 3/4/2025 | 3/4/2025 | 03/04/2025 |
| Ron Norton | ||||
| Footing Inspection | Partial Pass | 3/18/2025 | 3/18/2025 | 03/18/2025 |
| Ron Norton | ||||
| Footing Inspection | Partial Pass | 3/31/2025 | 3/31/2025 | 03/31/2025 |
| Ron Norton | ||||
| Foundation Inspection | Partial Pass | 3/31/2025 | 3/31/2025 | 03/31/2025 |
| Ron Norton | ||||
| Structural Inspection | Partial Pass | 4/7/2025 | 4/7/2025 | 04/07/2025 |
| Ron Norton | ||||
| Wall/Roof Sheeting | Passed | 4/7/2025 | 4/7/2025 | 04/07/2025 |
| Ron Norton | ||||
| Framing Inspection | Partial Pass | 5/2/2025 | 5/5/2025 | 05/05/2025 |
| Ron Norton | ||||
| Radon Piping | Partial Pass | 6/9/2025 | 6/9/2025 | 06/09/2025 |
| Ron Norton | ||||
| Radon Piping | Partial Pass | 6/13/2025 | 6/13/2025 | 06/13/2025 |
| Ron Norton | ||||
| Footing Inspection | Partial Pass | 6/13/2025 | 6/13/2025 | 06/13/2025 |
| Ron Norton | ||||
| Framing Inspection | Partial Pass | 9/2/2025 | 9/2/2025 | 09/02/2025 |
| Ron Norton | ||||
| Insulation Inspection | Passed | 9/11/2025 | 9/11/2025 | 09/11/2025 |
| Todd Carr | ||||
| Shower Pan | Passed | 9/11/2025 | 9/11/2025 | 09/11/2025 |
| Todd Carr | ||||
| Framing Inspection | Passed | 9/11/2025 | 9/11/2025 | 09/11/2025 |
| Todd Carr | ||||
| Water Service Inspection | Passed | 9/25/2025 | 9/25/2025 | 09/25/2025 |
| Baseline Inspectors | ||||
| Sewer Service Inspection | Passed | 10/22/2025 | 10/22/2025 | 10/22/2025 |
| Baseline Inspectors | ||||
| Condition | Status | Category |
|---|---|---|
| Use Tax Reconciliation | Open | Prior to Issuance of CO/CC |
|
Finance
Use Tax Reconciliation
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Full Building Permit Issuance |
|
Building Department
Malea to create permit for unit 2 of duplex.
|
||
| Miscellaneous Conditions | Resolved | |
|
Fire Prevention
Any fire alarm/sprinkler work will require a permit/plans to be submitted to Fire Prevention. See www.steamboatsprings.net, Fire and EMS Services, Fire Prevention, Downloadable Permits and Forms. NB [Charles Brookshire @ 09/26/2024 3:48 PM]
|
||
| Final Fire Inspection Required | Open | Prior to Issuance of TCO/CO/CC |
|
Fire Prevention
Fire needs to be involved with TCO/CO/CC sign-off in case there is an alarm or sprinkler permit. [Shannon Yaconiello @ 09/26/2024 4:08 PM]
|
||
| Engineering Sf/Du CO Review | Open | Prior to Issuance of TCO/CO/CC |
|
Engineering
At the time of project completion, request the Final Site Inspection from the Department of Public Works Engineering Div. to ensure the project has been built in accordance with the approved plans. [Scott Slamal @ 09/27/2024 2:22 PM]
|
||
| Blower Door Test Results | Open | Prior to Certificate of Occupancy/Completion |
|
Building Department
Blower Door Test Results
|
||
| Heat Loss Calculations Deferred Submittal | Open | Prior to Mechanical Permit Issuance for Heat |
|
Building Department
Heat Load Calculations must be submitted, Reviewed and approved prior to any heating equipment being installed.
|
||
| Miscellaneous Conditions | Open | Prior to Issuance of CO/CC |
|
Engineering
Driveway valley section shall comply with site plan requiring -1.5% decline to valley section. [Scott Slamal @ 07/16/2025 3:55 PM]
|
||
| Miscellaneous Conditions | Open | Prior to Issuance of CO/CC |
|
Engineering
Access off Steamboat Blvd used during construction must be stabilized and revegetated.
|
||
| SFR/Dup Planning CO Review | Open | Prior to Issuance of TCO/CO/CC |
|
Planning Department
Prior to issuance of a Certificate of Occupancy, the Department of Planning and Community Development may conduct an onsite inspection to ensure the project has been built in accordance with the approved plans and the Community Development Code. In the event the planning department deems an inspection necessary, a planning representative will contact the applicant. The applicant need not call for inspections. The inspection may include but is not limited to general site planning and grading, outdoor lighting, parking, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
|
||
| FLC Submittal | Open | Prior to Issuance of TCO/CO/CC |
|
Planning Department
Foundation location certificate shall be provided
|
||
| Truss Drawings Deferred Submittal | Resolved | Prior to Issuance of TCO/CO/CC |
|
Building Department
Truss drawings shall be submitted, reviewed and approved prior to installation and inspections.
|
||
| Reference Number | Status | Type |
|---|---|---|
| SPREL241797 | Permit(s) Issued | Electrical |
| SPRMH251181 | Permit(s) Issued | Mechanical |
| SPRMH251253 | Permit(s) Issued | Mechanical |
| SPRMH251259 | Permit(s) Issued | Mechanical |
Powered by CityView