Permit Application Status
SPRMU230307
In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
Date Returned | Name |
---|---|
03/05/2025 | L1.0 Landscape w Irrigation Notes (Stamped) |
03/05/2025 | L1.0_25-0212 - CLEAN (Stamped) |
12/27/2023 | Basecamp TH_1 Arch_ - Permit Response 3 (Stamped) |
07/21/2023 | Basecamp TH_1 - Civil Site Plan0 (Final) (Stamped) |
12/27/2023 | Basecamp TH_1 MEP - Permit Response 3 (Stamped) |
01/27/2025 | 2025-01-16 Oneline (Stamped) |
12/27/2023 | Basecamp TH_1 Struct_ - Permit Response 3 (Stamped) |
04/28/2025 | Basecamp Townhomes RFI 0045, RFI 0046 - ASE Response (Stamped) |
07/21/2023 | Civil Plans - Basecamp Phase 2 - CDs Rev1 - 5_18_23 (Final) (Stamped) |
05/01/2024 | 2387-004-Ph2-CDs-C_210 Water P&P (Stamped) |
07/21/2023 | Basecamp TH_1 - UTILITY PLANS markup - Applicant Response (Final) (Stamped) |
07/21/2023 | Basecamp TH_1 - UTILITY PLANS 2 of 3 (Final) (Stamped) |
10/23/2023 | Basecamp - Micro Pile Reports (Stamped) |
Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
COO Review - GIS Land Development | Approved | 06/12/2025 | 06/12/2025 |
Colten Yoast
|
|||
review for TCO, make sure addresses are in permit Addresses are added for the farthest NW building. | |||
COO Review - Utilities - City | TCO Approved | 06/12/2025 | 06/12/2025 |
Amber Gregory
|
|||
Review for TCO/CO | |||
COO Review - Fire Code | Failed | 06/12/2025 | 06/12/2025 |
Shannon Yaconiello
|
|||
Final alarm and sprinkler inspections must pass before CO sign-off. [Shannon Yaconiello @ 06/12/2025 2:38 PM] | |||
COO Review - Planning | TCO Approved | 06/12/2025 | 06/12/2025 |
Kelly Douglas, AICP
|
|||
Review for TCO/CO _ Planning TCO inspection 6/11/25. Critical improvements ok. Landscaping incomplete. TCO ok. [Kelly Douglas @ 06/12/2025 8:07 AM] | |||
COO Review - Engineering | TCO Approved | 06/18/2025 | 06/11/2025 |
Emrick Soltis, P.E., CFM
|
|||
COO Review - Building Code | TCO Approved | 06/12/2025 | 06/11/2025 |
Heidi Spengler
|
|||
Unit 1867 only okay for TCO | |||
COO Review - Finance Department | Approved | 06/12/2025 | 06/09/2025 |
Sondra Spratta
|
|||
Review for TCO/CO | |||
Building Code Review | Approved | 05/01/2025 | 04/28/2025 |
Ted Allen
|
|||
4.24.25: Window film specification meeting ANSI Z97.1 Class B and CPSC Category 1 testing requirements for tempered glass. Approval for Window film based on conversation with Todd Carr and Silas field inspection. 4.18.25: Letter from the Engineer of Record regarding two RFI's. Approved | |||
Utilities Review - City | Approved | 03/04/2025 | 03/05/2025 |
Amber Gregory
|
|||
Miscellaneous
Resolved
03/05/2025
update landscape plan to provide mi 5' separation from the service and irrigation box. Also provide square footage of irrigated area.
|
|||
Miscellaneous
Outstanding
03/05/2025
|
|||
2.25.25 Addendum: 1. Updated landscape plan to provide mi 5' separation from the service and irrigation box. 2. Square footage of irrigated area. | |||
Engineering Review | Approved | 03/04/2025 | 03/04/2025 |
Emrick Soltis, P.E., CFM
|
|||
2.25.25 Addendum: 1. Updated landscape plan to provide mi 5' separation from the service and irrigation box. 2. Square footage of irrigated area. | |||
Engineering Review | Approved | 02/06/2025 | 02/10/2025 |
Emrick Soltis, P.E., CFM
|
|||
1.30.25 Addendum- see narrative | |||
Planning Review | Approved | 02/06/2025 | 02/05/2025 |
Kelly Douglas, AICP
|
|||
1.30.25 Addendum- see narrative _ 1.30.25 Addendum OK [Kelly Douglas @ 02/05/2025 10:52 AM] | |||
Utilities Review - City | Failed | 02/06/2025 | 02/05/2025 |
Amber Gregory
|
|||
Miscellaneous
Carried Forward
02/25/2025
update landscape plan to provide mi 5' separation from the service and irrigation box. Also provide square footage of irrigated area.
|
|||
1.30.25 Addendum- see narrative | |||
Electrical Review | Approved | 01/24/2025 | 01/21/2025 |
Tom Cook
|
|||
1.17.25- Updated one line | |||
Utilities Review - City | Approved | 04/30/2024 | 05/01/2024 |
Amber Gregory
|
|||
Miscellaneous
Resolved
05/01/2024
Provide a profile of the fire water line.
|
|||
Resubmittal from 4/18 Addendum: updated plan that includes the requested profile for the fire water line. | |||
Fire Code Review | Approved | 04/18/2024 | 04/18/2024 |
Mike Middleton
|
|||
There are new utility plans uploaded on 04/10/2024 in the documents, two different plans related to water lines entry to the the Fire Riser Room to be reviewed. I simply added Fire due to the fact this water line is related to the Fire Riser room. [Mike Middleton @ 04/22/2024 10:52 AM] | |||
Utilities Review - City | Failed | 04/18/2024 | 04/18/2024 |
Amber Gregory
|
|||
Miscellaneous
Carried Forward
04/24/2024
Provide a profile of the fire water line.
|
|||
There are new utility plans uploaded on 04/10/2024 in the documents, two different plans related to water lines entery the the Fire Riser Room to be reviewed. | |||
Planning Review | Approved | 12/27/2023 | 12/26/2023 |
Kelly Douglas, AICP
|
|||
Addendum: Permit response #3 __ Addendum #3 ok [Kelly Douglas @ 12/26/2023 1:54 PM] | |||
Building Code Review | Approved | 12/27/2023 | 12/20/2023 |
Ted Allen
|
|||
Miscellaneous
Resolved
12/20/2023
Provide details of all required fire-resistive construction with complete assemblies to include fire walls, party walls, rated floor and roof ceilings, fire partition and penetrations of wall or floor-ceiling assemblies required to protect penetrations in fire-resistance-rated assemblies in accordance with IBC Section 714. Include STC ratings between all units and public spaces. OUTSTANDING: An example of a typical building of Type VA construction is a wood frame building in which the interior and exterior load-bearing walls, floors, roofs [those members that are less than 20 feet (6096 mm) to the lowest member] and all structural members are protected to provide a minimum 1-hour fire-resistance rating. See General Explanatory Note 11 of GA-600-2009 Fire Resistive Design Manual for the addition of excessive insulation.OUTSTANDING Only two items that appear in the plans with a rating: M30 Fire Test U305 (garage separation) and N60S per GA FILE NO. WP 3242 (walls separating dwelling units in the same building shall be constructed as fire partitions). While there do not appear to be any fire walls or party walls, rated floor and roof ceilings are required due to building of Type VA construction. All structural walls (exterior and interior as referenced in Section 704.10), floor construction and associated secondary members (including decks, cantilevers and floor rim boards), roofs and metal canopies shall be rated as per fire-rated assemblies attached to plans. Please include assembly notes for additional layers of gyp board due to excessive insulation or additional nail/screw length due to structural sheathing.
|
|||
Miscellaneous
Resolved
12/20/2023
Many of these systems have furring channels or multiple layers required for fire or sound. Check to see that all materials required in the assembly are represented in the drawings and verify the assemblies apply to the structural members specified on the structural plans. For example, when not specified as a component of a fire-resistance rated wall or partition system, how are wood structural panels permitted to be added to one or both sides? Provide general explanatory notes added to drawings. OUTSTANDING: See plans for 2SW2 and Detail 10/S0060 and General Explanatory Note 22 of GA-600-2009 Fire Resistive Design Manual.
|
|||
Miscellaneous
Resolved
12/20/2023
Informational:
Efficiency Package Reduced Air Infiltration Option requires Blower Door Test Results submitted prior to Certificate of Occupancy/Completion.
|
|||
Addendum: Permit response #3 | |||
Planning Review | Approved | 10/31/2023 | 10/31/2023 |
Kelly Douglas, AICP
|
|||
Addendum submitted 10/23 & 10/24 _ Addendum OK. kd | |||
Building Code Review | Failed | 10/31/2023 | 10/24/2023 |
Ted Allen
|
|||
Miscellaneous
Carried Forward
12/19/2023
Provide details of all required fire-resistive construction with complete assemblies to include fire walls, party walls, rated floor and roof ceilings, fire partition and penetrations of wall or floor-ceiling assemblies required to protect penetrations in fire-resistance-rated assemblies in accordance with IBC Section 714. Include STC ratings between all units and public spaces. OUTSTANDING: An example of a typical building of Type VA construction is a wood frame building in which the interior and exterior load-bearing walls, floors, roofs [those members that are less than 20 feet (6096 mm) to the lowest member] and all structural members are protected to provide a minimum 1-hour fire-resistance rating. See General Explanatory Note 11 of GA-600-2009 Fire Resistive Design Manual for the addition of excessive insulation.OUTSTANDING Only two items that appear in the plans with a rating: M30 Fire Test U305 (garage separation) and N60S per GA FILE NO. WP 3242 (walls separating dwelling units in the same building shall be constructed as fire partitions). While there do not appear to be any fire walls or party walls, rated floor and roof ceilings are required due to building of Type VA construction. All structural walls (exterior and interior as referenced in Section 704.10), floor construction and associated secondary members (including decks, cantilevers and floor rim boards), roofs and metal canopies shall be rated as per fire-rated assemblies attached to plans. Please include assembly notes for additional layers of gyp board due to excessive insulation or additional nail/screw length due to structural sheathing.
|
|||
Miscellaneous
Carried Forward
12/19/2023
Many of these systems have furring channels or multiple layers required for fire or sound. Check to see that all materials required in the assembly are represented in the drawings and verify the assemblies apply to the structural members specified on the structural plans. For example, when not specified as a component of a fire-resistance rated wall or partition system, how are wood structural panels permitted to be added to one or both sides? Provide general explanatory notes added to drawings. OUTSTANDING: See plans for 2SW2 and Detail 10/S0060 and General Explanatory Note 22 of GA-600-2009 Fire Resistive Design Manual.
|
|||
Miscellaneous
Carried Forward
12/19/2023
Informational:
Efficiency Package Reduced Air Infiltration Option requires Blower Door Test Results submitted prior to Certificate of Occupancy/Completion.
|
|||
Addendum submitted 10/23 & 10/24 | |||
Engineering Review | Approved | 07/27/2023 | 07/21/2023 |
Emrick Soltis, P.E., CFM
|
|||
Planning Review | Approved | 07/27/2023 | 07/21/2023 |
Kelly Douglas, AICP
|
|||
Miscellaneous
Resolved
07/21/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
Prior to Building Permit issuance, the developer shall pay their proportionate share of potential future roadway and/or intersection improvements at Downhill Drive at US 40 intersection, calculated at 0.62% of 8,333,132.02 or $51,665.42
|
|||
Utilities Review - City | Approved | 06/29/2023 | 07/05/2023 |
Amber Gregory
|
|||
See Document Markups
Outstanding
06/22/2023
relocate the irrigation line from the blowoff
|
|||
See Document Markups
Outstanding
06/22/2023
provide lengths of new 4" pipe between fittings. How large is the deflection?
|
|||
See Document Markups
Outstanding
06/22/2023
provide lengths between fittings and bend sizes
|
|||
See Document Markups
Outstanding
06/22/2023
bend?
|
|||
Miscellaneous
Outstanding
06/22/2023
Identify the number of hose bibs that will be attached to each building.
|
|||
Miscellaneous
Outstanding
06/22/2023
Identify the square footage, if any, associated with the building.
|
|||
Engineering Review | Failed | 06/29/2023 | 07/03/2023 |
Emrick Soltis, P.E., CFM
|
|||
Miscellaneous
Carried Forward
07/20/2023
Traffic contribution associated with DPVC-21-16 is required prior to BP approval.
|
|||
Planning Review | Failed | 06/29/2023 | 06/30/2023 |
Kelly Douglas, AICP
|
|||
Miscellaneous
Carried Forward
07/20/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
Prior to Building Permit issuance, the developer shall pay their proportionate share of potential future roadway and/or intersection improvements at Downhill Drive at US 40 intersection, calculated at 0.62% of 8,333,132.02 or $51,665.42
|
|||
Miscellaneous
Resolved
06/30/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
A development agreement shall be recorded to document phasing prior to building permit approval.
|
|||
Miscellaneous
Resolved
06/30/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
Prior to Building Permit issuance for Phase A, the mural on the commercial container will require approval through the Substantial Conformance process.
___
Resolved. This COA is now required prior to building permit issuance for Phase B as per PL20230131.
|
|||
Miscellaneous
Resolved
06/30/2023
The plans for this permit (SPRMU230307) are not consistent with the phasing plan approved with DPVC-21-16. Substantial Conformance is required in order to amend the phasing plan.
___
Approval of Substantial Conformance application PL20230131 is required prior to approval.
|
|||
Existing Grade
Resolved
06/30/2023
Please add and label existing grade to all elevations in order to confirm compliance with overall height and average plate height standards.
|
|||
Building Code Review | Approved | 06/29/2023 | 06/27/2023 |
Ted Allen
|
|||
Miscellaneous
Outstanding
06/22/2023
Following is a list of items, found during a cursory review that will need to be addressed prior to re-submitting the plans for review. Complications relating to delegated design are not uncommon, though they often surface much later in the project during the inspection phase, or plan review stage following the time of inspections and concrete has been cast which can be an inopportune time. These complications often relate to misunderstandings of roles and responsibilities, whether contractual or design related. Effective implementation of delegated design in a project needs to be carefully coordinated during the Foundation Only approval of construction documents to avoid potential pitfalls and ensure a successfully completed project. Please read Foundation Only Policy and make sure these concerns have been addressed prior to signing and resubmitting for a Foundation Only Permit. These items and any subsequent review questions will need to be addressed prior to the Foundation Only Permit being issued:
1. Submittal documents consisting of statement of special inspections, reports and other data shown on Sheet S0003 designates the portions of the work that require special inspection and indicates the duties of the special inspectors. Include the following in statement of special inspections and responsibilities: RESOLVED per Building Department Conditions placed on the permit that may appear as a Stop Work Order allowing the permit to be issued that requires Final Micropile Special Inspection Report to be submitted to RCRBD prior to release for inspection of grade beams under Foundation Only.
a. The geotechnical report suggests contacting NWCC to coordinate with the micropile contractor, the foundation design and layout was provided without any mention of product or contractor. As a minimum, three (3) test piles shall be advanced at each building site so that a pre-production pull test may be conducted. The person or firm responsible for providing micropiles shall submit final shop drawings, stamped and signed as requested and approved by the Engineer of Record (EOR).
b. Provide frequency of testing per notes of the shop drawing submittal above.
c. Provide amount of time the reports and inspections for Phase I are to be submitted to the building department.
d. Otherwise note acceptance of the condition placed on the permit that may appear as a Stop Work Order allowing the permit to be issued that requires Final Micropile Special Inspection Report to be submitted to RCRBD prior to release for inspection of grade beams.
These items and any subsequent review questions will need to be addressed prior to the Building Permit being issued:
2. Looking at Tables 601 and Reference of Type VA Primary Structural Frame on Sheet G0003 appears to reflect Type IIIB where exterior bearing walls are 2-Hour. There are also references for FRT wood throughout the plans. Please verify type of construction and note the differences when designing with Type VA and furnish all required fire assemblies. OUTSTANDING: See Item 6 below for comments.
3. Also, the code analysis references COMcheck but was not submitted. RESOLVED: Note Reduced Air Infiltration requires blower door testing. I have set conditions for deferred truss submittal and blower door test to be completed. Truss drawings shall be submitted after they have been reviewed and approved prior to installation and inspections.
4. Re: Partition Type N on Sheet A1000:
a. Fire-resistance ratings, STCs, FSTCs, and IICs are the results of tests conducted on systems composed of specific materials put together in a specified manner. Many UL listed assemblies are “Proprietary,” meaning that very specific brand name products must be used in the construction of the assemblies. Provide copies of fire-resistive assemblies to include testing of the desired STC rating. RESOLVED
b. Many of these systems have furring channels or multiple layers required for fire or sound. Check to see that all materials required in the assembly are represented in the drawings and verify the assemblies apply to the structural members specified on the structural plans. For example, when not specified as a component of a fire-resistance rated wall or partition system, how are wood structural panels permitted to be added to one or both sides? Provide general explanatory notes added to drawings. OUTSTANDING: See plans for 2SW2 and Detail 10/S0060 and General Explanatory Note 22 of GA-600-2009 Fire Resistive Design Manual.
c. Unless otherwise specified, the face layers of all systems shall have joints taped and fastener heads treated. Base layers in multi-layer systems shall not be required to have joints or fasteners taped. Note where the gypsum board extends above the ceiling to floor/roof deck requires joints to be taped and fasteners need to be covered unless an exception is provided. Where required the plans shall show fire-resistance rated partitions extending above the ceiling, not as depicted in Details 9/A0900, 11/A0901, 1/A0910, 2/A0910, Partition Type N on Sheet A1000. RESOLVED
5. While subject to compliance under Chapter 11 of the IBC, any development with seven or more units is subject to Title 9 Article 5 of The Colorado Revised Statutes amended and signed into law on April 29, 2003. Provide narrative to include details of compliance and schedule if dispersed throughout later phases of construction. RESOLVED
6. Provide details of all required fire-resistive construction with complete assemblies to include fire walls, party walls, rated floor and roof ceilings, fire partition and penetrations of wall or floor-ceiling assemblies required to protect penetrations in fire-resistance-rated assemblies in accordance with IBC Section 714. Include STC ratings between all units and public spaces. OUTSTANDING: An example of a typical building of Type VA construction is a wood frame building in which the interior and exterior load-bearing walls, floors, roofs [those members that are less than 20 feet (6096 mm) to the lowest member] and all structural members are protected to provide a minimum 1-hour fire-resistance rating. See General Explanatory Note 11 of GA-600-2009 Fire Resistive Design Manual for the addition of excessive insulation.OUTSTANDING Only two items that appear in the plans with a rating: M30 Fire Test U305 (garage separation) and N60S per GA FILE NO. WP 3242 (walls separating dwelling units in the same building shall be constructed as fire partitions). While there do not appear to be any fire walls or party walls, rated floor and roof ceilings are required due to building of Type VA construction. All structural walls (exterior and interior as referenced in Section 704.10), floor construction and associated secondary members (including decks, cantilevers and floor rim boards), roofs and metal canopies shall be rated as per fire-rated assemblies attached to plans. Please include assembly notes for additional layers of gyp board due to excessive insulation or additional nail/screw length due to structural sheathing.
7. While the calculations submitted include several notes regarding items to check and some with references to corrections made to the plans, there appear to be several items of concern as follows:
a. Solid sawn header RISA analyzed would fail. RESOLVED
b. Interior 2x4 bearing wall analyzed by Forte would fail by 8%. This may not seem to be much, however, considering the members appear to have been designed with a duration factor of 1.15. For our area use a duration factor of 1.0 (not reduced). RESOLVED
c. Several shear walls analyzes by Tekla failed due to excessive deflection and several other shear wall segments were not analyzed due to aspect ratio exceeding maximum allowable. RESOLVED
d. RCRBD finds the labelling of shear walls on the floor and roof plan to be inconsistent with the calculations and hold down callouts when referencing anchor bolts in concrete. RESOLVED
|
|||
Building Department Conditions placed on the permit that may appear as a Stop Work Order allowing the permit to be issued that requires Final Micropile Special Inspection Report to be submitted to RCRBD prior to release for inspection of grade beams under Foundation Only. | |||
Utilities Review - City | Failed | 05/30/2023 | 06/07/2023 |
Amber Gregory
|
|||
See Document Markups
Resolved
06/07/2023
5'- min separation required
|
|||
See Document Markups
Carried Forward
06/07/2023
10' min sep.
|
|||
See Document Markups
Resolved
06/07/2023
5' separation
|
|||
See Document Markups
Carried Forward
06/22/2023
relocate the irrigation line from the blowoff
|
|||
See Document Markups
Resolved
06/07/2023
svs cannot be right at bend/deflection
|
|||
See Document Markups
Resolved
06/07/2023
5-feet of separation is required between taps- apply to all locations
|
|||
See Document Markups
Carried Forward
06/22/2023
provide lengths of new 4" pipe between fittings. How large is the deflection?
|
|||
See Document Markups
Carried Forward
06/22/2023
provide lengths between fittings and bend sizes
|
|||
See Document Markups
Carried Forward
06/22/2023
bend?
|
|||
Miscellaneous
Carried Forward
06/22/2023
Identify the number of hose bibs that will be attached to each building.
|
|||
Miscellaneous
Carried Forward
06/22/2023
Identify the square footage, if any, associated with the building.
|
|||
Applicant is seeking Foundation Only Approval with this review if bull BP is not approvable. | |||
Engineering Review | Failed | 05/30/2023 | 06/06/2023 |
Emrick Soltis, P.E., CFM
|
|||
Miscellaneous
Carried Forward
06/22/2023
See Planning comments.
|
|||
Applicant is seeking Foundation Only Approval with this review if bull BP is not approvable. | |||
Planning Review | Failed | 05/30/2023 | 05/30/2023 |
Kelly Douglas, AICP
|
|||
Miscellaneous
Carried Forward
06/22/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
Prior to Building Permit issuance, the developer shall pay their proportionate share of potential future roadway and/or intersection improvements at Downhill Drive at US 40 intersection, calculated at 0.62% of 8,333,132.02 or $51,665.42
|
|||
Miscellaneous
Carried Forward
06/22/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
A development agreement shall be recorded to document phasing prior to building permit approval.
|
|||
Miscellaneous
Carried Forward
06/22/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
Prior to Building Permit issuance for Phase A, the mural on the commercial container will require approval through the Substantial Conformance process.
|
|||
Miscellaneous
Carried Forward
06/22/2023
The plans for this permit (SPRMU230307) are not consistent with the phasing plan approved with DPVC-21-16. Substantial Conformance is required in order to amend the phasing plan.
___
Approval of Substantial Conformance application PL20230131 is required prior to approval.
|
|||
Existing Grade
Carried Forward
06/22/2023
Please add and label existing grade to all elevations in order to confirm compliance with overall height and average plate height standards.
|
|||
Applicant is seeking Foundation Only Approval with this review if bull BP is not approvable. | |||
Building Code Review | Failed | 05/30/2023 | 05/26/2023 |
Ted Allen
|
|||
Miscellaneous
Carried Forward
06/22/2023
Following is a list of items, found during a cursory review that will need to be addressed prior to re-submitting the plans for review. Complications relating to delegated design are not uncommon, though they often surface much later in the project during the inspection phase, or plan review stage following the time of inspections and concrete has been cast which can be an inopportune time. These complications often relate to misunderstandings of roles and responsibilities, whether contractual or design related. Effective implementation of delegated design in a project needs to be carefully coordinated during the Foundation Only approval of construction documents to avoid potential pitfalls and ensure a successfully completed project. Please read Foundation Only Policy and make sure these concerns have been addressed prior to signing and resubmitting for a Foundation Only Permit. These items and any subsequent review questions will need to be addressed prior to the Foundation Only Permit being issued:
1. Submittal documents consisting of statement of special inspections, reports and other data shown on Sheet S0003 designates the portions of the work that require special inspection and indicates the duties of the special inspectors. Include the following in statement of special inspections and responsibilities:
a. The geotechnical report suggests contacting NWCC to coordinate with the micropile contractor, the foundation design and layout was provided without any mention of product or contractor. As a minimum, three (3) test piles shall be advanced at each building site so that a pre-production pull test may be conducted. The person or firm responsible for providing micropiles shall submit final shop drawings, stamped and signed as requested and approved by the Engineer of Record (EOR).
b. Provide frequency of testing per notes of the shop drawing submittal above.
c. Provide amount of time the reports and inspections for Phase I are to be submitted to the building department.
d. Otherwise note acceptance of the condition placed on the permit that may appear as a Stop Work Order allowing the permit to be issued that requires Final Micropile Special Inspection Report to be submitted to RCRBD prior to release for inspection of grade beams.
These items and any subsequent review questions will need to be addressed prior to the Building Permit being issued:
2. Looking at Tables 601 and Reference of Type VA Primary Structural Frame on Sheet G0003 appears to reflect Type IIIB where exterior bearing walls are 2-Hour. There are also references for FRT wood throughout the plans. Please verify type of construction and note the differences when designing with Type VA and furnish all required fire assemblies. OUTSTANDING: See Item 6 below for comments.
3. Also, the code analysis references COMcheck but was not submitted. RESOLVED: Note Reduced Air Infiltration requires blower door testing. I have set conditions for deferred truss submittal and blower door test to be completed. Truss drawings shall be submitted after they have been reviewed and approved prior to installation and inspections.
4. Re: Partition Type N on Sheet A1000:
a. Fire-resistance ratings, STCs, FSTCs, and IICs are the results of tests conducted on systems composed of specific materials put together in a specified manner. Many UL listed assemblies are “Proprietary,” meaning that very specific brand name products must be used in the construction of the assemblies. Provide copies of fire-resistive assemblies to include testing of the desired STC rating. RESOLVED
b. Many of these systems have furring channels or multiple layers required for fire or sound. Check to see that all materials required in the assembly are represented in the drawings and verify the assemblies apply to the structural members specified on the structural plans. For example, when not specified as a component of a fire-resistance rated wall or partition system, how are wood structural panels permitted to be added to one or both sides? Provide general explanatory notes added to drawings. OUTSTANDING: See plans for 2SW2 and Detail 10/S0060 and General Explanatory Note 22 of GA-600-2009 Fire Resistive Design Manual.
c. Unless otherwise specified, the face layers of all systems shall have joints taped and fastener heads treated. Base layers in multi-layer systems shall not be required to have joints or fasteners taped. Note where the gypsum board extends above the ceiling to floor/roof deck requires joints to be taped and fasteners need to be covered unless an exception is provided. Where required the plans shall show fire-resistance rated partitions extending above the ceiling, not as depicted in Details 9/A0900, 11/A0901, 1/A0910, 2/A0910, Partition Type N on Sheet A1000. RESOLVED
5. While subject to compliance under Chapter 11 of the IBC, any development with seven or more units is subject to Title 9 Article 5 of The Colorado Revised Statutes amended and signed into law on April 29, 2003. Provide narrative to include details of compliance and schedule if dispersed throughout later phases of construction. RESOLVED
6. Provide details of all required fire-resistive construction with complete assemblies to include fire walls, party walls, rated floor and roof ceilings, fire partition and penetrations of wall or floor-ceiling assemblies required to protect penetrations in fire-resistance-rated assemblies in accordance with IBC Section 714. Include STC ratings between all units and public spaces. OUTSTANDING: An example of a typical building of Type VA construction is a wood frame building in which the interior and exterior load-bearing walls, floors, roofs [those members that are less than 20 feet (6096 mm) to the lowest member] and all structural members are protected to provide a minimum 1-hour fire-resistance rating. See General Explanatory Note 11 of GA-600-2009 Fire Resistive Design Manual for the addition of excessive insulation.
7. While the calculations submitted include several notes regarding items to check and some with references to corrections made to the plans, there appear to be several items of concern as follows:
a. Solid sawn header RISA analyzed would fail. RESOLVED
b. Interior 2x4 bearing wall analyzed by Forte would fail by 8%. This may not seem to be much, however, considering the members appear to have been designed with a duration factor of 1.15. For our area use a duration factor of 1.0 (not reduced). RESOLVED
c. Several shear walls analyzes by Tekla failed due to excessive deflection and several other shear wall segments were not analyzed due to aspect ratio exceeding maximum allowable. RESOLVED
d. RCRBD finds the labelling of shear walls on the floor and roof plan to be inconsistent with the calculations and hold down callouts when referencing anchor bolts in concrete. RESOLVED
|
|||
Applicant is seeking Foundation Only Approval with this review if bull BP is not approvable. | |||
Fire Code Review | Approved | 04/27/2023 | 04/28/2023 |
Matt Workman
|
|||
Conditionally Approved –NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms MW | |||
Utilities Review - City | Failed | 04/27/2023 | 04/28/2023 |
Amber Gregory
|
|||
See Document Markups
Carried Forward
05/22/2023
5'- min separation required
|
|||
See Document Markups
Carried Forward
05/22/2023
10' min sep.
|
|||
See Document Markups
Carried Forward
05/22/2023
5' separation
|
|||
See Document Markups
Carried Forward
05/22/2023
relocate the irrigation line from the blowoff
|
|||
See Document Markups
Carried Forward
05/22/2023
svs cannot be right at bend/deflection
|
|||
See Document Markups
Carried Forward
05/22/2023
5-feet of separation is required between taps- apply to all locations
|
|||
See Document Markups
Carried Forward
05/22/2023
provide lengths of new 4" pipe between fittings. How large is the deflection?
|
|||
See Document Markups
Carried Forward
05/22/2023
provide lengths between fittings and bend sizes
|
|||
See Document Markups
Carried Forward
05/22/2023
bend?
|
|||
Building Code Review | Failed | 04/27/2023 | 04/27/2023 |
Ted Allen
|
|||
Miscellaneous
Carried Forward
05/22/2023
Following is a list of items, found during a cursory review that will need to be addressed prior to re-submitting the plans for review. Please be aware that this is not a complete plan review. These items and any subsequent review questions will need to be addressed prior to the Building Permit being issued:
1. While the geotechnical report suggests contacting NWCC to coordinate with the micropile contractor, the foundation design and layout was provided without any mention of product or contractor. As a minimum, three (3) test piles shall be advanced at each building site so that a pre-production pull test may be conducted. The person or firm responsible for providing micropiles shall submit final shop drawings, stamped and signed as requested and approved by the Engineer of Record (EOR).
2. Submittal documents consisting of statement of special inspections, reports and other data shown on Sheet S0003 designates the portions of the work that require special inspection and indicates the duties of the special inspectors. Include the following in statement of special inspections and responsibilities:
a. Provide documentation of the name of individual or firm that is responsible for testing and special inspection(s) of micropiles.
b. Provide frequency of testing per notes of the shop drawing submittal above.
c. Provide amount of time the reports and inspections for Phase I are to be submitted to the building department.
d. Also note the condition placed on the permit that requires Final Micropile Special Inspection Report to be submitted to RCRBD prior to inspection of grade beams.
3. Looking at Tables 601 and Reference of Type VA Primary Structural Frame on Sheet G0003 appears to reflect Type IIIB where exterior bearing walls are 2-Hour. There are also references for FRT wood throughout the plans. Please verify type of construction and note the differences when designing with Type VA and furnish all required fire assemblies.
4. Also, the code analysis references COMcheck but was not submitted.
5. Re: Partition Type N on Sheet A1000:
a. Fire-resistance ratings, STCs, FSTCs, and IICs are the results of tests conducted on systems composed of specific materials put together in a specified manner. Many UL listed assemblies are “Proprietary,” meaning that very specific brand name products must be used in the construction of the assemblies. Provide copies of fire-resistive assemblies to include testing of the desired STC rating.
b. Many of these systems have furring channels or multiple layers required for fire or sound. Check to see that all materials required in the assembly are represented in the drawings and verify the assemblies apply to the structural members specified on the structural plans. For example, when not specified as a component of a fire-resistance rated wall or partition system, how are wood structural panels permitted to be added to one or both sides? Provide general explanatory notes added to drawings.
c. Unless otherwise specified, the face layers of all systems shall have joints taped and fastener heads treated. Base layers in multi-layer systems shall not be required to have joints or fasteners taped. Note where the gypsum board extends above the ceiling to floor/roof deck requires joints to be taped and fasteners need to be covered unless an exception is provided. Where required the plans shall show fire-resistance rated partitions extending above the ceiling, not as depicted in Details 9/A0900, 11/A0901, 1/A0910, 2/A0910, Partition Type N on Sheet A1000,
6. While subject to compliance under Chapter 11 of the IBC, any development with seven or more units is subject to Title 9 Article 5 of The Colorado Revised Statutes amended and signed into law on April 29, 2003. Provide narrative to include details of compliance and schedule if dispersed throughout later phases of construction.
7. Provide details of all required fire-resistive construction with complete assemblies to include fire walls, party walls, rated floor and roof ceilings, fire partition and penetrations of wall or floor-ceiling assemblies required to protect penetrations in fire-resistance-rated assemblies in accordance with IBC Section 714. Include STC ratings between all units and public spaces.
8. While the calculations submitted include several notes regarding items to check and some with references to corrections made to the plans, there appear to be several items of concern as follows:
a. Solid sawn header RISA analyzed would fail.
b. Interior 2x4 bearing wall analyzed by Forte would fail by 8%. This may not seem to be much, however, considering the members appear to have been designed with a duration factor of 1.15. For our area use a duration factor of 1.0 (not reduced).
c. Several shear walls analyzes by Tekla failed due to excessive deflection and several other shear wall segments were not analyzed due to aspect ratio exceeding maximum allowable.
d. RCRBD finds the labelling of shear walls on the floor and roof plan to be inconsistent with the calculations and hold down callouts when referencing anchor bolts in concrete.
Informational: RCRBD places condition on inspections provided for foundation inspection that shall not be conducted until copies of special inspections to include Miocropile Final Report is submitted to RCRBD and approved. RCRBD does not accept any responsibility for any condition that was not known at the time of this report. We reserve the right to amend this report if additional information is received.
|
|||
Engineering Review | Failed | 04/27/2023 | 04/27/2023 |
Emrick Soltis, P.E., CFM
|
|||
Miscellaneous
Carried Forward
05/22/2023
See Planning comments.
|
|||
External Agencies Review | Approved | 04/27/2023 | 04/27/2023 |
Malea Michael-Ferrier
|
|||
GIS Land Development Review | Approved | 04/27/2023 | 04/26/2023 |
Colten Yoast
|
|||
I do not believe that the current addresses are reflected in this permit. Please update the addresses. | |||
Planning Review | Failed | 04/27/2023 | 04/25/2023 |
Kelly Douglas, AICP
|
|||
Miscellaneous
Carried Forward
05/22/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
Prior to Building Permit issuance, the developer shall pay their proportionate share of potential future roadway and/or intersection improvements at Downhill Drive at US 40 intersection, calculated at 0.62% of 8,333,132.02 or $51,665.42
|
|||
Miscellaneous
Carried Forward
05/22/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
A development agreement shall be recorded to document phasing prior to building permit approval.
|
|||
Miscellaneous
Carried Forward
05/22/2023
There is an outstanding DPVC-21-16 condition of approval required to be addressed prior to building permit approval:
Prior to Building Permit issuance for Phase A, the mural on the commercial container will require approval through the Substantial Conformance process.
|
|||
Miscellaneous
Carried Forward
05/22/2023
The plans for this permit (SPRMU230307) are not consistent with the phasing plan approved with DPVC-21-16. Substantial Conformance is required in order to amend the phasing plan.
|
|||
Existing Grade
Carried Forward
05/22/2023
Please add and label existing grade to all elevations in order to confirm compliance with overall height and average plate height standards.
|
|||
Construction Site Management Review | Approved | 04/27/2023 | 04/25/2023 |
Scott Slamal
|
|||
Electrical Review | Approved | 04/27/2023 | 04/24/2023 |
Tom Cook
|
|||
Final approval subject to field inspection | |||
Finance Department Review | Approved | 04/27/2023 | 04/11/2023 |
Sondra Spratta
|
|||
Other multi-unit buildings are being assessed commercial permit review. |
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Final Construction Site Management | Pending | |||
Scott Slamal | ||||
Shower Pan | Pending | |||
Building Final Inspection | Pending | |||
Foundation Inspection | Partial Pass | 10/25/2023 | 10/25/2023 | 10/25/2023 |
Ron Norton | ||||
Footing Inspection | Partial Pass | 10/26/2023 | 10/26/2023 | 10/26/2023 |
Ron Norton | ||||
Footing Inspection | Partial Pass | 10/30/2023 | 10/30/2023 | 10/30/2023 |
Ron Norton | ||||
Footing Inspection | Partial Pass | 10/31/2023 | 10/31/2023 | 10/31/2023 |
Ron Norton | ||||
Footing Inspection | Passed | 11/1/2023 | 11/1/2023 | 11/01/2023 |
Ron Norton | ||||
Foundation Inspection | Partial Pass | 2/23/2024 | 2/23/2024 | 02/23/2024 |
Silas Ebbert | ||||
Foundation/Under Slab Insulation | Not Ready | 2/23/2024 | 2/23/2024 | 02/23/2024 |
Silas Ebbert | ||||
Foundation Inspection | Partial Pass | 2/26/2024 | 2/26/2024 | 02/26/2024 |
Silas Ebbert | ||||
Foundation Inspection | Partial Pass | 2/29/2024 | 2/29/2024 | 02/29/2024 |
Silas Ebbert | ||||
Foundation/Under Slab Insulation | Passed | 3/7/2024 | 3/7/2024 | 03/07/2024 |
Ron Norton | ||||
Foundation Inspection | Partial Pass | 3/7/2024 | 3/7/2024 | 03/07/2024 |
Ron Norton | ||||
Foundation Inspection | Partial Pass | 3/11/2024 | 3/11/2024 | 03/11/2024 |
Silas Ebbert | ||||
Foundation Inspection | Partial Pass | 3/12/2024 | 3/12/2024 | 03/12/2024 |
Silas Ebbert | ||||
Radon Piping | Passed | 3/13/2024 | 3/13/2024 | 03/13/2024 |
Silas Ebbert | ||||
Foundation Inspection | Partial Pass | 3/20/2024 | 3/20/2024 | 03/20/2024 |
Silas Ebbert | ||||
Foundation Water Proofing | Partial Pass | 3/21/2024 | 3/21/2024 | 03/21/2024 |
Silas Ebbert | ||||
Foundation Inspection | Partial Pass | 3/22/2024 | 3/22/2024 | 03/22/2024 |
Silas Ebbert | ||||
Foundation Inspection | Partial Pass | 3/28/2024 | 3/28/2024 | 03/28/2024 |
Silas Ebbert | ||||
Foundation Inspection | Passed | 4/1/2024 | 4/1/2024 | 04/01/2024 |
Silas Ebbert | ||||
Structural Inspection | Partial Pass | 7/11/2024 | 7/16/2024 | 07/17/2024 |
Silas Ebbert | ||||
Framing Inspection | Failed | 10/16/2024 | 10/16/2024 | 10/16/2024 |
Silas Ebbert | ||||
Framing Inspection | Not Ready | 10/28/2024 | 10/28/2024 | 10/28/2024 |
Silas Ebbert | ||||
Framing Inspection | Partial Pass | 1/16/2025 | 1/16/2025 | 01/16/2025 |
Silas Ebbert | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
01/16/2025
Building Department Corrections to be Completed
1. Need to install a couple more stud shoes in units 1 and 2 in bearing walls
2. Add H2.5 clips to balcony rafters to plate connection over garage door
3. Unit 1 third floor landing window needs to be tempered
4. Need to get engineers RFI responses in stamped letter
5. Add A35 slips to all shear wall rim to plate connections
6. Add squash blocking in rim joists where needed
|
||||
Structural Inspection | Not Ready | 1/16/2025 | 1/16/2025 | 01/16/2025 |
Silas Ebbert | ||||
Framing Inspection | Partial Pass | 1/22/2025 | 1/22/2025 | 01/22/2025 |
Silas Ebbert | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
01/22/2025
Building Department Corrections to be Completed
1. Need to install a couple more stud shoes in units 1 and 2 in bearing walls
2. Add H2.5 clips to balcony rafters to plate connection over garage door
3. Unit 1 third floor landing window needs to be tempered
4. Need to get engineers RFI responses in stamped letter
5. Add A35 slips to all shear wall rim to plate connections
6. Add squash blocking in rim joists where needed
|
||||
Building Department Corrections to be Completed
Carried Forward
01/22/2025
1. Unit 1 third floor landing window needs to be tempered
2. Add stud shoes in garage middle bearing wall
3. Fire caulk all penetrations in top and bottom plates and through penetrations between units
|
||||
Structural Inspection | Not Ready | 1/22/2025 | 1/22/2025 | 01/22/2025 |
Silas Ebbert | ||||
Framing Inspection | Partial Pass | 1/23/2025 | 1/23/2025 | 01/23/2025 |
Ron Norton | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
01/23/2025
Building Department Corrections to be Completed
1. Need to install a couple more stud shoes in units 1 and 2 in bearing walls
2. Add H2.5 clips to balcony rafters to plate connection over garage door
3. Unit 1 third floor landing window needs to be tempered
4. Need to get engineers RFI responses in stamped letter
5. Add A35 slips to all shear wall rim to plate connections
6. Add squash blocking in rim joists where needed
|
||||
Building Department Corrections to be Completed
Carried Forward
01/23/2025
1. Unit 1 third floor landing window needs to be tempered
2. Add stud shoes in garage middle bearing wall
3. Fire caulk all penetrations in top and bottom plates and through penetrations between units
|
||||
Structural Inspection | Not Ready | 1/27/2025 | 1/27/2025 | 01/27/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 1/29/2025 | 1/29/2025 | 01/29/2025 |
Silas Ebbert | ||||
Structural Inspection | Passed | 1/29/2025 | 1/29/2025 | 01/29/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/3/2025 | 2/3/2025 | 02/03/2025 |
Silas Ebbert | ||||
Insulation Inspection | Passed | 2/7/2025 | 2/7/2025 | 02/07/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/7/2025 | 2/7/2025 | 02/07/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/11/2025 | 2/11/2025 | 02/11/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/13/2025 | 2/13/2025 | 02/13/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/14/2025 | 2/14/2025 | 02/14/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/18/2025 | 2/18/2025 | 02/18/2025 |
Ron Norton | ||||
Drywall Inspection | Partial Pass | 2/20/2025 | 2/20/2025 | 02/20/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/21/2025 | 2/21/2025 | 02/21/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/24/2025 | 2/24/2025 | 02/24/2025 |
Silas Ebbert | ||||
Drywall Inspection | Partial Pass | 2/27/2025 | 2/27/2025 | 02/27/2025 |
Silas Ebbert | ||||
Lath/Veneer Inspection | Passed | 3/6/2025 | 3/6/2025 | 03/06/2025 |
Silas Ebbert | ||||
Drywall Inspection | Passed | 3/11/2025 | 3/11/2025 | 03/11/2025 |
Silas Ebbert | ||||
Wall/Roof Sheeting | Passed | 3/13/2025 | 3/13/2025 | 03/13/2025 |
Silas Ebbert | ||||
Framing Inspection | Partial Pass | 3/24/2025 | 3/24/2025 | 03/24/2025 |
Silas Ebbert | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
03/24/2025
Building Department Corrections to be Completed
1. Need to install a couple more stud shoes in units 1 and 2 in bearing walls
2. Add H2.5 clips to balcony rafters to plate connection over garage door
3. Unit 1 third floor landing window needs to be tempered
4. Need to get engineers RFI responses in stamped letter
5. Add A35 slips to all shear wall rim to plate connections
6. Add squash blocking in rim joists where needed
|
||||
Building Department Corrections to be Completed
Carried Forward
03/24/2025
1. Unit 1 third floor landing window needs to be tempered
2. Add stud shoes in garage middle bearing wall
3. Fire caulk all penetrations in top and bottom plates and through penetrations between units
|
||||
Drywall Inspection | Passed | 4/16/2025 | 4/16/2025 | 04/16/2025 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 4/17/2025 | 4/17/2025 | 04/17/2025 |
Jeff Yeiser | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
04/17/2025
Building Department Corrections to be Completed
1. Need to install a couple more stud shoes in units 1 and 2 in bearing walls
2. Add H2.5 clips to balcony rafters to plate connection over garage door
3. Unit 1 third floor landing window needs to be tempered
4. Need to get engineers RFI responses in stamped letter
5. Add A35 slips to all shear wall rim to plate connections
6. Add squash blocking in rim joists where needed
|
||||
Building Department Corrections to be Completed
Carried Forward
04/17/2025
1. Unit 1 third floor landing window needs to be tempered
2. Add stud shoes in garage middle bearing wall
3. Fire caulk all penetrations in top and bottom plates and through penetrations between units
|
||||
Drywall Inspection | Partial Pass | 4/16/2025 | 4/17/2025 | 04/17/2025 |
Jeff Yeiser | ||||
Drywall Inspection | Passed | 4/24/2025 | 4/24/2025 | 04/24/2025 |
Silas Ebbert | ||||
Framing Inspection | Passed | 4/28/2025 | 4/28/2025 | 04/28/2025 |
Silas Ebbert | ||||
Corrections:
Building Department Corrections to be Completed
Resolved
04/28/2025
Building Department Corrections to be Completed
1. Need to install a couple more stud shoes in units 1 and 2 in bearing walls
2. Add H2.5 clips to balcony rafters to plate connection over garage door
3. Unit 1 third floor landing window needs to be tempered
4. Need to get engineers RFI responses in stamped letter
5. Add A35 slips to all shear wall rim to plate connections
6. Add squash blocking in rim joists where needed
|
||||
Building Department Corrections to be Completed
Resolved
04/28/2025
1. Unit 1 third floor landing window needs to be tempered
2. Add stud shoes in garage middle bearing wall
3. Fire caulk all penetrations in top and bottom plates and through penetrations between units
|
||||
Building Final Inspection | Not Ready | 6/6/2025 | 6/9/2025 | 06/09/2025 |
Jeff Yeiser | ||||
Building Final Inspection | Partial Pass | 6/11/2025 | 6/11/2025 | 06/11/2025 |
Silas Ebbert |
Condition | Status | Category |
---|---|---|
Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
Finance
Use Tax Reconciliation
|
||
Vested Approval Conditions | Resolved | |
Planning Department
Compliance with DPVC-21-16 conditions of approval required.
|
||
MF/Com/I Planning CO Review | Open | Prior to Issuance of CO/CC |
Planning Department
At the time of project completion, request certificate of occupancy inspections from the Department of Planning and Community Development to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, landscaping and revegetation, outdoor lighting, parking and parking lot striping, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
_
Planning TCO inspection 6/11/25. Critical improvements ok. Landscaping incomplete. TCO ok. [Kelly Douglas @ 06/12/2025 8:07 AM]
|
||
Miscellaneous Conditions | Resolved | Prior to Rough Building Wall Inspections |
Fire Prevention
Conditionally Approved –NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms MW
|
||
Final Fire Inspection Required | Open | Prior to Issuance of TCO/CO/CC |
Fire Prevention
Final Fire Alarm & Sprinkler Inspections Required
|
||
Blower Door Test Results | Open | Prior to Certificate of Occupancy/Completion |
Building Department
Efficiency Package Reduced Air Infiltration Option requires Blower Door Test Results
|
||
Building Department Conditions to be Completed | Resolved | Prior to Footing/Foundation Inspection |
Building Department
Building Department Conditions placed on the permit that may appear as a Stop Work Order allowing the permit to be issued that requires Final Micropile Special Inspection Report to be submitted to RCRBD prior to release for inspection of grade beams.
|
||
Truss Drawings Deferred Submittal | Resolved | Prior to Issuance of TCO/CO/CC |
Building Department
Truss drawings shall be submitted, reviewed and approved prior to installation and inspections.
|
||
Building Department Conditions to be Completed | Resolved | Prior to Rough Building Wall Inspections |
Building Department
Building Department Conditions to be Completed prior to proceeding beyond the F/O Phase and Final Building Permit Phase:
Provide details of all required fire-resistive construction with complete assemblies to include fire walls, party walls, rated floor and roof ceilings, fire partition and penetrations of wall or floor-ceiling assemblies required to protect penetrations in fire-resistance-rated assemblies in accordance with IBC Section 714. Include STC ratings between all units and public spaces. OUTSTANDING: An example of a typical building of Type VA construction is a wood frame building in which the interior and exterior load-bearing walls, floors, roofs [those members that are less than 20 feet (6096 mm) to the lowest member] and all structural members are protected to provide a minimum 1-hour fire-resistance rating. See General Explanatory Note 11 of GA-600-2009 Fire Resistive Design Manual for the addition of excessive insulation.OUTSTANDING Only two items that appear in the plans with a rating: M30 Fire Test U305 (garage separation) and N60S per GA FILE NO. WP 3242 (walls separating dwelling units in the same building shall be constructed as fire partitions). While there do not appear to be any fire walls or party walls, rated floor and roof ceilings are required due to building of Type VA construction. All structural walls (exterior and interior as referenced in Section 704.10), floor construction and associated secondary members (including decks, cantilevers and floor rim boards), roofs and metal canopies shall be rated as per fire-rated assemblies attached to plans. Please include assembly notes for additional layers of gyp board due to excessive insulation or additional nail/screw length due to structural sheathing.
|
||
Miscellaneous Conditions | Open | Prior to Issuance of TCO/CO/CC |
Public Works - Water and Sewer
Trees must be placed a minimum 5-feet from the proposed 1.5" irrigation service. Verification the trees are not installed within 5' of the service must be provided
|
||
Miscellaneous Conditions | Open | Prior to Issuance of TCO/CO/CC |
GIS
Make sure correct addresses are associated with permit prior to issuance of TCO/CO [Malea Michael-Ferrier @ 04/24/2025 3:42 PM]
|
||
Miscellaneous Conditions | Open | Prior to Issuance of TCO/CO/CC |
Public Works - Water and Sewer
All City water and sewer tap fees must be paid prior to issuance of TCO/CO
|
||
Building Department Conditions to be Completed | Open | Prior to Issuance of CO/CC |
Building Department
Unit 1867 only approved for TCO
[Heidi Spengler @ 06/11/2025 1:53 PM]
|
Reference Number | Status | Type |
---|---|---|
SPRPL231627 | Permit(s) Issued | Plumbing |
SPRMH231629 | Permit(s) Issued | Mechanical |
SPREL231812 | Permit(s) Issued | Electrical |