Permit Application Status
B-21-204
In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
Engineering Review | TCO Approved | 11/24/2021 | 11/30/2021 |
Emrick Soltis, P.E., CFM
|
|||
Miscellaneous
Outstanding
11/30/2021
Failed. A completion letter submitted by the Engineer of Record prior to final inspection.
|
|||
TCO/CO/CC Approval | |||
Planning Review | TCO Approved | 11/24/2021 | 11/29/2021 |
Bob Keenan, AICP
|
|||
Miscellaneous
Outstanding
12/06/2021
TCO Approved. Need drainage easement
|
|||
TCO/CO/CC Approval | |||
Building Code Review | TCO Approved | 11/24/2021 | 11/29/2021 |
Heidi Spengler
|
|||
Building Final approved for the new lower terminal building, the boiler will be fired up later today and a mechanical final re-inspection will be done tomorrow, approved for a Certificate of Occupancy. | |||
Fire Code Review | TCO Approved | 11/24/2021 | 11/19/2021 |
Shannon Yaconiello
|
|||
Miscellaneous
Outstanding
11/19/2021
Fire needs a copy of the elevator inspection before CO sign-off.
|
|||
TCO/CO/CC Approval - Fire needs a copy of the elevator inspection before CO sign-off. | |||
Finance Department Review | TCO Approved | 11/24/2021 | 11/18/2021 |
Amy Camilletti
|
|||
TCO/CO/CC Approval The City of Steamboat Springs Finance department has approved a TEMPORARY CERTIFICATE on this project. A construction use tax reconciliation must be completed within 90 days to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department. | |||
Utilities Review - Mt. Werner | Approved | 11/24/2021 | 11/18/2021 |
Richard Buccino
|
|||
TCO/CO/CC Approval | |||
GIS Land Development Review | Approved | 11/24/2021 | 11/17/2021 |
Heidi Spengler
|
|||
Approved for CO. RCBD | |||
Building Code Review | Approved | 09/01/2021 | 08/29/2021 |
Todd Carr
|
|||
door specs provided and approved Lower terminal bridge RFI received, AOR and EOR approved existing bridge remaining with a 6"overpour | |||
Fire Code Review | Approved | 06/24/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Fire Dept sysadmin - Jun 24 2021 2:27PM - Addendum 2: Approved - Please maintain emergency access during construction work. Elevator approval is subject to final inspection. Any fire alarm work or alterations require a permit to be submitted to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms. | |||
Legacy Permitting Review | Approved | 06/21/2021 | |
SysAdmin
|
|||
VP legacy plan review: Routt Building sysadmin - Mar 16 2021 8:40AM - Plan review process started sysadmin - Mar 24 2021 1:44PM - Plan review letter sent, resubmittal needed. sysadmin - Apr 3 2021 6:06AM - Permit approved with resubmittal provided sysadmin - Apr 27 2021 11:57AM - Addendum approved with elevator increase in size, snow and electrical vaults and other minor modifications. sysadmin - Jun 21 2021 1:19PM - Addendum approved on 6/21/21 for architectural, structural, plumbing and civil drawings under building codes. | |||
Legacy Permitting Review | Approved | 06/18/2021 | |
SysAdmin
|
|||
VP legacy plan review: Mt Werner Water District sysadmin - Mar 24 2021 8:49AM - This permit does not include building demolition or water and sewer relocations. Demo permit to be under separate permit which will require engineered water and sewer plans. sysadmin - May 3 2021 10:46AM - Addendum OK. sysadmin - Jun 18 2021 11:39AM - ASI #2 OK. | |||
Planning Review | Approved w/ Conditions | 06/18/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Planning sysadmin - Mar 22 2021 11:34AM - OK per BK. Applicant must satisfy all Conditions of Approval outlined in DPA-20-08 approval letter (attached to this permit). sysadmin - Apr 26 2021 11:32AM - Addendum received 4/26/2021 approved. sysadmin - Jun 18 2021 11:39AM - Addendum received 6/18/2021 approved per BK. | |||
Engineering Review | Approved | 05/03/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Engineering Dept sysadmin - May 3 2021 9:39AM - no concerns were identified in the permit addendum from 4/23 | |||
Interim Construction Site Management | Approved | 04/02/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Construction Site Management sysadmin - Mar 23 2021 11:50AM - waiting on CSMP submittal | |||
GIS Land Development Review | Approved | 03/17/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Address | |||
Legacy Permitting Review | Approved | 03/16/2021 | |
SysAdmin
|
|||
VP legacy plan review: Routt Electrical Plan Review sysadmin - Mar 16 2021 11:09AM - Electric plans approved. | |||
Utilities Review - City | Complete | 03/16/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Water & Sewer | |||
External Agencies Review | Complete | 03/16/2021 | |
SysAdmin
|
|||
VP legacy plan review: YVEA | |||
External Agencies Review | Complete | 03/16/2021 | |
SysAdmin
|
|||
VP legacy plan review: Atmos Energy | |||
Finance Department Review | Approved | 03/16/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Finance Dept sysadmin - Mar 16 2021 1:07PM - City of Steamboat Springs Finance has approved City tax & permit fees of $204,022.50 on this permit. This is the City’s portion, made payable to the City of Steamboat Springs and submitted to the Routt County Regional Building Department. At the end of the project, City of Steamboat Springs Finance requires a construction use tax reconciliation be completed to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/approval with the Routt County Building Department. |
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Foundation Inspection | Complete | 07/06/2021 | ||
SysAdmin | ||||
Footing Inspection | Complete | 07/07/2021 | ||
SysAdmin | ||||
Foundation Inspection | Failed | 07/07/2021 | ||
SysAdmin | ||||
Foundation Inspection | Complete | 07/12/2021 | ||
SysAdmin | ||||
Footing Inspection | Complete | 07/16/2021 | ||
SysAdmin | ||||
Foundation Inspection | Failed | 07/20/2021 | ||
SysAdmin | ||||
Foundation Inspection | Complete | 07/21/2021 | ||
SysAdmin | ||||
Foundation Inspection | Complete | 07/27/2021 | ||
SysAdmin | ||||
Foundation Drain Inspection | Complete | 07/30/2021 | ||
SysAdmin | ||||
Footing Inspection | Complete | 07/30/2021 | ||
SysAdmin | ||||
Foundation Inspection | Complete | 08/03/2021 | ||
SysAdmin | ||||
Footing Inspection | Complete | 08/09/2021 | ||
SysAdmin | ||||
Insulation Inspection | Partial Pass | 9/8/2021 | 9/8/2021 | 09/08/2021 |
Don Marchbanks | ||||
Framing Inspection | Partial Pass | 9/7/2021 | 9/7/2021 | 09/08/2021 |
Don Marchbanks | ||||
Insulation Inspection | Partial Pass | 9/9/2021 | 9/9/2021 | 09/09/2021 |
Don Marchbanks | ||||
Framing Inspection | Partial Pass | 9/9/2021 | 9/9/2021 | 09/09/2021 |
Don Marchbanks | ||||
Foundation Inspection | Partial Pass | 9/10/2021 | 9/10/2021 | 09/10/2021 |
Don Marchbanks | ||||
Foundation Drain Inspection | Partial Pass | 9/10/2021 | 9/13/2021 | 09/13/2021 |
Don Marchbanks | ||||
Foundation Inspection | Partial Pass | 9/15/2021 | 9/15/2021 | 09/15/2021 |
Don Marchbanks | ||||
Foundation Inspection | Partial Pass | 9/23/2021 | 9/23/2021 | 09/23/2021 |
Don Marchbanks | ||||
Foundation Inspection | Partial Pass | 10/29/2021 | 10/29/2021 | 10/29/2021 |
Todd Carr | ||||
Roofing Inspection | Failed | 11/3/2021 | 11/3/2021 | 11/03/2021 |
Todd Carr | ||||
Corrections:
Miscellaneous
Carried Forward
11/03/2021
Roofing inspection of elevator/boiler room, membrane is fully installed except the boiler vent is not installed yet call back for that once installed. Also you must install the scupper per the plans as the secondary drain, currently we have only the primary roof drain but no secondary.
|
||||
Building Final Inspection | Passed | 11/17/2021 | 11/17/2021 | 11/17/2021 |
Todd Carr |
Condition | Status | Category |
---|---|---|
Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
Building Department
spray applied fire resistant special inspection received, and elevator permit from NWCOO
|
||
Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
Finance
Use Tax Reconciliation
--------------------------------------
Consent agreement executed due July 31, 2023
|
||
Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
Planning Department
Prior to project completion or Certificate of Occupancy, the applicant shall record a drainage easement to cover the water quality treatment facility and access to it from the public street.
|
Reference Number | Status | Type |
---|---|---|
E-21-361 | Closed | Electrical |
P-21-281 | Closed | Plumbing |
SPRMH210052 | Closed | Mechanical |
SPREL210062 | Closed | Electrical |
SPRPL210106 | Canceled | Plumbing |