Staff cannot approve an unknown (field determined) location for the bike rack via this proposal. The note should be eliminated and the bike rack left in place (until such time as a new location is determined), or the new location should be determined at this time for approval.
Addendum to civil plans (CIVIL PLAN Revisions - 2075 Walton Creek - Dated 2026_03_25) see narrative for the detailed changes.
Engineering Review
Approved
04/02/2026
04/02/2026
Emrick Soltis, P.E., CFM
Addendum to civil plans (CIVIL PLAN Revisions - 2075 Walton Creek - Dated 2026_03_25) see narrative for the detailed changes.
Fire Code Review
Approved
04/02/2026
04/01/2026
Charles Brookshire
Addendum to civil plans (CIVIL PLAN Revisions - 2075 Walton Creek - Dated 2026_03_25) see narrative for the detailed changes. Full Permit. NB [Charles Brookshire @ 04/01/2026 8:09 AM]
Construction Site Management Review
Approved
04/02/2026
03/31/2026
Scott Slamal
Addendum to civil plans (CIVIL PLAN Revisions - 2075 Walton Creek - Dated 2026_03_25) see narrative for the detailed changes.
Utilities Review - Mt. Werner
Approved
04/02/2026
03/30/2026
Beau Cahill
Addendum to civil plans (CIVIL PLAN Revisions - 2075 Walton Creek - Dated 2026_03_25) see narrative for the detailed changes.
Building Code Review
Approved
04/02/2026
03/26/2026
Todd Carr
Addendum to civil plans (CIVIL PLAN Revisions - 2075 Walton Creek - Dated 2026_03_25) see narrative for the detailed changes.
Plans reviewed, new proposed boulder walls are less than 4 in height and therefore exempt from a permit, no other changes on the civil plans apply to the Building code, pavers being added compared to concrete will be subject to ADA surface requirments.
Electrical Review
Approved
02/13/2026
02/11/2026
Tom Cook
Electrical plans for large service.
Planning Review
Approved
01/20/2026
01/20/2026
Jeremy Brown
Miscellaneous
Resolved
01/20/2026
Provide revised glazing calculations for all facades. Planning will not be able to approve reductions in glazing without additional public hearing review. It would appear that while most windows stay the same, there are some select windows that have visible small reductions and the garage doors that eliminate glazing panes.
Miscellaneous
Resolved
01/20/2026
South Elevations on both buildings may not "end" the stone veneer as proposed without returning to an inside corner CDC 437.I.1.b
1.12.26- Resubmittal of Architectural from previously failed addendum review. See attached narrative.
Substantial conformance reviewed through this application. [Jeremy Brown @ 01/20/2026 7:08 PM]
Utilities Review - Mt. Werner
Approved
11/19/2025
11/18/2025
Beau Cahill
ADDENDUM 11.11.25- see attached narrative.
Planning Review
Failed
11/19/2025
11/18/2025
Jeremy Brown
Miscellaneous
Carried Forward
01/12/2026
Provide revised glazing calculations for all facades. Planning will not be able to approve reductions in glazing without additional public hearing review. It would appear that while most windows stay the same, there are some select windows that have visible small reductions and the garage doors that eliminate glazing panes.
Miscellaneous
Carried Forward
01/12/2026
South Elevations on both buildings may not "end" the stone veneer as proposed without returning to an inside corner CDC 437.I.1.b
ADDENDUM 11.11.25- see attached narrative.
Building Code Review
Approved
11/19/2025
11/18/2025
Ted Allen
ADDENDUM 11.11.25- see attached narrative.
Fire Code Review
Approved
11/19/2025
11/13/2025
Charles Brookshire
ADDENDUM 11.11.25- see attached narrative.
Full Permit. NB [Charles Brookshire @ 11/13/2025 7:48 PM]
Utilities Review - Mt. Werner
Approved
07/21/2025
07/17/2025
Beau Cahill
Addendum ASI #01 and new civil, utility and site plan.
Planning Review
Approved
07/21/2025
07/15/2025
Jeremy Brown
Addendum ASI #01 and new civil, utility and site plan.
Building Code Review
Approved
07/21/2025
07/15/2025
Ted Allen
Addendum ASI #01 and new civil, utility and site plan.
Construction Site Management Review
Failed
07/21/2025
07/14/2025
Scott Slamal
Miscellaneous
Resolved
11/11/2025
Show that for commercial, industrial, and multifamily sites, aggregate tracking pads shall be constructed of three-inch to eight-inch angular aggregate. If using FODs mats, a minimum of two mats are required and need to be installed per the manufactures specifications.
Miscellaneous
Resolved
11/11/2025
Wire backed silt fence required on down gradient limits of disturbance.
Miscellaneous
Resolved
11/11/2025
Recommend constructing detention pond during initial grading to serve as a sedimentation basin for the duration of the project. The basin should be constructed with a temporary perforated vertical outlet pipe. Scott can email recommended details.
Addendum ASI #01 and new civil, utility and site plan.
Utilities Review - Mt. Werner
Approved
04/01/2025
06/03/2025
Beau Cahill
Miscellaneous
Resolved
06/03/2025
Plant investment fees must be paid in full prior to permit approval. I have reached out to applicant representatives for information needed to finalize fees but have not received a response.
Update - applicant has finalized fees - approved permit with condition holding issuance of permit until fees are paid in full. [bcahill @ 06/03/2025 10:23 AM]
Building Code Review
Approved
04/01/2025
06/02/2025
Todd Carr
Miscellaneous
Resolved
06/02/2025
There appears to be two (2) copies of Architectural plan sheet G0002 submitted to Routt County Regional Building Department (RCRBD) for review, one signed and sealed and the second unsigned. There are references to International Building Code 2012, Louisiana State Codes and ICC/ANSI 117.1 – 2003 under General Note 1 that shall be coordinated with Sheet G0003 and updated to ANSI 117.1-2017. Also, the Fair Housing Act Design and Construction Requirements has guidelines for meeting each of 7 requirements of the Act. These requirements are: accessible building entrance on an accessible route; accessible and useable public and common use areas; useable doors; accessible route into and through the covered dwelling unit; light switches, electrical outlets, thermostats, and other environmental controls in accessible locations; reinforced walls for grab bars; “adaptable” dwelling unit requirements were carried forward with the FHA requirements reflected in the Type B units Option A and B bathrooms. The specifics of these requirements are not beyond the scope of construction documents to include electrical plans and all of the Type B components throughout visitable ground floor as applicable.
Miscellaneous
Resolved
06/02/2025
Construction documents shall indicate the solar-ready zone per RS402.2 and also designate the EV ready space per RV502.3 and unless HVAC is electric similar consideration (as applicable) from location of the panel to Electric receptacle or junction box within 3 feet of the combustion equipment or appliances that meets the requirements of Section RE302.5, electrical service panel to accommodate future electric equipment and reserved physical space for circuit breakers in the main panel that are properly labeled.
Corrections have been made, permit is now approved.
Utilities Review - Mt. Werner
Failed
05/15/2025
05/15/2025
Beau Cahill
Miscellaneous
Carried Forward
06/02/2025
Plant investment fees must be paid in full prior to permit approval. I have reached out to applicant representatives for information needed to finalize fees but have not received a response.
Miscellaneous
Resolved
05/15/2025
Request for water and sewer services form (appendix H) must be signed by project owners and returned to MWW prior to permit approval. Form can be downloaded from mwwater.com; additionally form will be sent to applicant along with finalized plant investment fees.
Miscellaneous
Resolved
05/15/2025
Informational Comment:
A license agreement for storm water infrastructure proposed to be constructed within existing sanitary sewer easement will need to be executed with the District prior to any issuance of occupancy
Plant Investment Fees outstanding
Engineering Review
Approved
05/15/2025
05/14/2025
Makenzie Carroll
See Document Markups
Resolved
05/13/2025
(C1): Lighting Plan?
See Document Markups
Resolved
05/13/2025
(C2): May 1.
See Document Markups
Resolved
05/13/2025
(C4): Property boundary?
See Document Markups
Resolved
05/13/2025
(C4): What is going on here?
See Document Markups
Resolved
05/13/2025
(C4): Provide railing detail.
See Document Markups
Resolved
05/13/2025
(C4): Provide valley pan detail.
See Document Markups
Resolved
05/14/2025
(C4): Provide handrail detail.
See Document Markups
Resolved
05/13/2025
(C6): Roof Drain?
See Document Markups
Resolved
05/13/2025
(C6): Flared end sections required.
See Document Markups
Resolved
05/13/2025
(C6): Flared end sections required
See Document Markups
Resolved
05/13/2025
(C8): Provide detail for 4' diameter manhole.
See Document Markups
Resolved
05/13/2025
(C9): Provide detail for 4' diameter manhole.
See Document Markups
Resolved
05/13/2025
(C4): Detectable Warning Plates Required. Please also provide detail
See Document Markups
Resolved
05/13/2025
(C4): Detectable warnings required.
Construction Site Management Review
Approved
05/15/2025
05/12/2025
Scott Slamal
Miscellaneous
Outstanding
05/08/2025
Show that for commercial, industrial, and multifamily sites, aggregate tracking pads shall be constructed of three-inch to eight-inch angular aggregate. If using FODs mats, a minimum of two mats are required and need to be installed per the manufactures specifications.
Miscellaneous
Outstanding
05/08/2025
Wire backed silt fence required on down gradient limits of disturbance.
Miscellaneous
Outstanding
05/08/2025
Recommend constructing detention pond during initial grading to serve as a sedimentation basin for the duration of the project. The basin should be constructed with a temporary perforated vertical outlet pipe. Scott can email recommended details.
Building Code Review
Failed
05/15/2025
05/12/2025
Ted Allen
Miscellaneous
Carried Forward
06/02/2025
There appears to be two (2) copies of Architectural plan sheet G0002 submitted to Routt County Regional Building Department (RCRBD) for review, one signed and sealed and the second unsigned. There are references to International Building Code 2012, Louisiana State Codes and ICC/ANSI 117.1 – 2003 under General Note 1 that shall be coordinated with Sheet G0003 and updated to ANSI 117.1-2017. Also, the Fair Housing Act Design and Construction Requirements has guidelines for meeting each of 7 requirements of the Act. These requirements are: accessible building entrance on an accessible route; accessible and useable public and common use areas; useable doors; accessible route into and through the covered dwelling unit; light switches, electrical outlets, thermostats, and other environmental controls in accessible locations; reinforced walls for grab bars; “adaptable” dwelling unit requirements were carried forward with the FHA requirements reflected in the Type B units Option A and B bathrooms. The specifics of these requirements are not beyond the scope of construction documents to include electrical plans and all of the Type B components throughout visitable ground floor as applicable.
Miscellaneous
Resolved
05/12/2025
The fire-resistance-rated wall or assembly separating townhouse units shall be continuous from the foundation to the underside of the roof sheathing. Please correct and resubmit Detail 12/A0800 showing continuity of 2-Hour WP 4232 walls rated for exposure from both sides with gypsum wallboard continuous to the underside of the roof sheathing per IRC Section R302.2.3 and either parapets for townhouses or exception per IRC Section R302.2.4
Miscellaneous
Resolved
05/12/2025
The Exterior Wall and Roof Types on Sheet A1000 references COMcheck but was not submitted and REScheck is required for insulation and fenestration requirements for this project. IECC Chapter 3 covers general regulations for energy conservation features of buildings. Detail 5/A0800 shall show insulation from the top of the slab downward 48" without gaps, a 45 degree taper is allowed at top of slab.
With this energy information extending to Details 9/A0800 provided above, where insulation is extended above grade and exposed to the elements include a rigid, opaque and weather-resistant protective covering to prevent the degradation of the insulation’s thermal performance and extends 6-inches below grade per IECC R303.2.1 and on above where the detail shows floor shall also be packed of 2x framed wall value – Typical at floors.
Miscellaneous
Resolved
05/12/2025
Plaster (stucco) with its shared properties of thin veneer (adhered masonry veneer), water-resistive barriers shall comply with one of the applicable requirements in R703.7.3.1 Dry Climates. The water-resistive barrier shall be two layers of 10-minute Grade D paper or have a water resistance equal to or greater than two layers of a water-resistive barrier complying with ASTM E2556, Type I. The individual layers shall be installed independently such that each layer provides a separate continuous plane (where VAPOR BARRIER, BUILDING PAPER &
PERMALATH UNDERLAYMENTS are shown). Flashing installed in accordance with Section R703.4 and intended to drain to the water-resistive barrier, weep screed shall be directed between the layers. The weep screed shall be placed not less than 4 inches (102 mm) above the earth or 2 inches (51 mm) above paved areas and shall be of a type that will allow trapped water to drain to the exterior of the building.
Miscellaneous
Carried Forward
06/02/2025
Construction documents shall indicate the solar-ready zone per RS402.2 and also designate the EV ready space per RV502.3 and unless HVAC is electric similar consideration (as applicable) from location of the panel to Electric receptacle or junction box within 3 feet of the combustion equipment or appliances that meets the requirements of Section RE302.5, electrical service panel to accommodate future electric equipment and reserved physical space for circuit breakers in the main panel that are properly labeled.
Planning Review
Approved
04/18/2025
04/24/2025
Jeremy Brown
Engineering Review
Failed
04/18/2025
04/22/2025
Makenzie Carroll
See Document Markups
Carried Forward
05/08/2025
(C1): Lighting Plan?
See Document Markups
Carried Forward
05/08/2025
(C2): May 1.
See Document Markups
Carried Forward
05/08/2025
(C4): Property boundary?
See Document Markups
Carried Forward
05/08/2025
(C4): What is going on here?
See Document Markups
Carried Forward
05/08/2025
(C4): Provide railing detail.
See Document Markups
Carried Forward
05/08/2025
(C4): Provide valley pan detail.
See Document Markups
Carried Forward
05/08/2025
(C4): Provide handrail detail.
See Document Markups
Carried Forward
05/08/2025
(C6): Roof Drain?
See Document Markups
Carried Forward
05/08/2025
(C6): Flared end sections required.
See Document Markups
Carried Forward
05/08/2025
(C6): Flared end sections required
See Document Markups
Carried Forward
05/08/2025
(C8): Provide detail for 4' diameter manhole.
See Document Markups
Carried Forward
05/08/2025
(C9): Provide detail for 4' diameter manhole.
See Document Markups
Carried Forward
05/08/2025
(C4): Detectable Warning Plates Required. Please also provide detail
See Document Markups
Carried Forward
05/08/2025
(C4): Detectable warnings required.
GIS Land Development Review
Approved
04/18/2025
04/21/2025
Colten Yoast
External Agencies Review
Approved
04/18/2025
04/18/2025
Tammy Green
YVEA - inspections@yvea.com
Please go to YVEA's website and fill out all the steps.
https://www.yvea.com/new-commercial-construction/
Any questions please reach out to Emma 970-871-2242
Construction Site Management Review
Failed
04/18/2025
04/18/2025
Scott Slamal
Miscellaneous
Carried Forward
05/08/2025
Show that for commercial, industrial, and multifamily sites, aggregate tracking pads shall be constructed of three-inch to eight-inch angular aggregate. If using FODs mats, a minimum of two mats are required and need to be installed per the manufactures specifications.
Miscellaneous
Carried Forward
05/08/2025
Wire backed silt fence required on down gradient limits of disturbance.
Miscellaneous
Carried Forward
05/08/2025
Recommend constructing detention pond during initial grading to serve as a sedimentation basin for the duration of the project. The basin should be constructed with a temporary perforated vertical outlet pipe. Scott can email recommended details.
Utilities Review - Mt. Werner
Failed
04/18/2025
04/18/2025
Catherine Smith
Miscellaneous
Carried Forward
05/08/2025
Plant investment fees must be paid in full prior to permit approval. I have reached out to applicant representatives for information needed to finalize fees but have not received a response.
Miscellaneous
Carried Forward
05/08/2025
Request for water and sewer services form (appendix H) must be signed by project owners and returned to MWW prior to permit approval. Form can be downloaded from mwwater.com; additionally form will be sent to applicant along with finalized plant investment fees.
Miscellaneous
Carried Forward
05/08/2025
Informational Comment:
A license agreement for storm water infrastructure proposed to be constructed within existing sanitary sewer easement will need to be executed with the District prior to any issuance of occupancy
Building Code Review
Failed
04/18/2025
04/14/2025
Ted Allen
Miscellaneous
Carried Forward
05/08/2025
Architectural plans prepared under the direct supervision of the registered design professional and submitted to Routt County Regional Building Department (RCRBD) for review shall be have date plans were prepared under the direct supervision of the registered design professional and stamped in accordance with Colorado State Law.
Miscellaneous
Carried Forward
05/08/2025
The fire-resistance-rated wall or assembly separating townhouse units shall be continuous from the foundation to the underside of the roof sheathing. Please correct and resubmit Detail 12/A0800 showing continuity of 2-Hour WP 4232 walls rated for exposure from both sides with gypsum wallboard continuous to the underside of the roof sheathing per IRC Section R302.2.3 and either parapets for townhouses or exception per IRC Section R302.2.4
Miscellaneous
Carried Forward
05/08/2025
The Exterior Wall and Roof Types on Sheet A1000 references COMcheck but was not submitted and REScheck is required for insulation and fenestration requirements for this project. IECC Chapter 3 covers general regulations for energy conservation features of buildings. Detail 5/A0800 shall show insulation from the top of the slab downward 48" without gaps, a 45 degree taper is allowed at top of slab.
With this energy information extending to Details 9/A0800 provided above, where insulation is extended above grade and exposed to the elements include a rigid, opaque and weather-resistant protective covering to prevent the degradation of the insulation’s thermal performance and extends 6-inches below grade per IECC R303.2.1 and on above where the detail shows floor shall also be packed of 2x framed wall value – Typical at floors.
Miscellaneous
Carried Forward
05/08/2025
Plaster (stucco) with its shared properties of thin veneer (adhered masonry veneer), water-resistive barriers shall comply with one of the applicable requirements in R703.7.3.1 Dry Climates. The water-resistive barrier shall be two layers of 10-minute Grade D paper or have a water resistance equal to or greater than two layers of a water-resistive barrier complying with ASTM E2556, Type I. The individual layers shall be installed independently such that each layer provides a separate continuous plane (where VAPOR BARRIER, BUILDING PAPER &
PERMALATH UNDERLAYMENTS are shown). Flashing installed in accordance with Section R703.4 and intended to drain to the water-resistive barrier, weep screed shall be directed between the layers. The weep screed shall be placed not less than 4 inches (102 mm) above the earth or 2 inches (51 mm) above paved areas and shall be of a type that will allow trapped water to drain to the exterior of the building.
Miscellaneous
Carried Forward
05/08/2025
Construction documents shall also indicate the solar-ready zone per RS402.2 and also designate the EV ready space per RV502.3 and indicate the locations of raceway and/or conduit and the termination points serving them and shall indicate at least one potential pathway for routing of conduit and/or raceway from the solar-ready zone to the electrical service panel and shall be labeled as “Potential Pathway” on the construction documents.
Electrical Review
Approved
04/18/2025
04/14/2025
Tom Cook
If service is 400 amps or over engineered one-line drawings prior to rough inspection
Fire Code Review
Approved
04/18/2025
04/10/2025
Shannon Yaconiello
Conditionally Approved –NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms. [Nick Brookshire @ 04/10/2025 3:27 PM]
Finance Department Review
Approved
04/18/2025
04/01/2025
Denitsa Yaneva
Inspection
Outcome
Requested
Scheduled
Date Inspected
Water Service Inspection
Pending
Amber Gregory
Sewer Service Inspection
Pending
Amber Gregory
Interim Construction Site Management
Pending
Scott Slamal
Roofing Inspection
Pending
Insulation Inspection
Pending
Final Planning Department Site Improvement
Pending
Final Construction Site Management
Pending
Scott Slamal
Building Final Inspection
Pending
Structural Inspection
Pending
Lath/Veneer Inspection
Pending
Shower Pan
Pending
Foundation Inspection
Pending
Footing Inspection
Pending
Framing Inspection
Pending
Drywall Inspection
Pending
Wall/Roof Sheeting
Pending
Footing Inspection
Partial Pass
7/16/2025
7/16/2025
07/16/2025
Ron Norton
Foundation Drain Inspection
Partial Pass
7/25/2025
7/25/2025
07/25/2025
Todd Carr
Foundation Inspection
Not Ready
7/29/2025
7/29/2025
07/29/2025
Ron Norton
Footing Inspection
Partial Pass
9/5/2025
9/5/2025
09/08/2025
Jeff Yeiser
Foundation Inspection
Partial Pass
9/16/2025
9/16/2025
09/16/2025
Jeff Yeiser
Footing Inspection
Partial Pass
9/30/2025
9/30/2025
09/30/2025
Jeff Yeiser
Radon Piping
Passed
10/3/2025
10/3/2025
10/03/2025
Jeff Yeiser
Foundation/Under Slab Insulation
Passed
10/6/2025
10/6/2025
10/06/2025
Jeff Yeiser
Foundation Water Proofing
Passed
10/2/2025
11/12/2025
11/12/2025
Jeff Yeiser
Foundation Drain Inspection
Passed
9/30/2025
11/12/2025
11/12/2025
Jeff Yeiser
Framing Inspection
Not Ready
2/12/2026
2/12/2026
02/12/2026
Jeff Yeiser
Drywall Inspection
Partial Pass
2/12/2026
2/12/2026
02/12/2026
Jeff Yeiser
Wall/Roof Sheeting
Not Ready
3/17/2026
3/17/2026
03/17/2026
Ron Norton
Wall/Roof Sheeting
Partial Pass
3/24/2026
3/25/2026
03/25/2026
Ron Norton
Condition
Status
Category
Building Department Conditions to be Completed
Resolved
Prior to Full Building Permit Issuance
Building Department
Building Department will change the Application Type of this permit to Single Family Residence and create seven additional permits, one for each unit. [Malea Michael-Ferrier @ 03/26/2025 7:29 AM] See Todd Carr before making changes and creating new permits, to discuss civil plans on large projects like this.
Blower Door Test Results
Open
Prior to Certificate of Occupancy/Completion
Building Department
Blower Door Test Results [Todd Carr @ 03/27/2025 7:12 AM]
Heat Loss Calculations Deferred Submittal
Open
Prior to Mechanical Permit Issuance for Heat
Building Department
Heat Load Calculations must be submitted, Reviewed and approved prior to any heating equipment being installed. [Todd Carr @ 03/27/2025 7:13 AM]
Use Tax Reconciliation
Open
Prior to Issuance of CO/CC
Finance
Use Tax Reconciliation
Miscellaneous Conditions
Resolved
Prior to Rough Building Wall Inspections
Fire Prevention
1/6/26 Full Permit - Kevin Kopasz, GC emailed: As discussed, Terrain at Walton Creek consists of a 3-unit building, and a 5-unit building. All units are three story or less IRC single family town homes, which fall under the RCRBD code adoption not requiring Fire Sprinkler Systems and Monitored Fire Alarm Systems. We are not planning to install Fire Sprinkler Systems on this project, and we will be providing live voltage combo smoke/CO detectors within each unit. The design documents were originally submitted noting the units were to have Fire Sprinkler Systems installed, which the design team has since revised with recent resubmittals issued to RCRBD. [Mike Middleton @ 01/06/2026 4:41 PM]
Conditionally Approved –NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms NB [Nick Brookshire @ 04/10/2025 3:27 PM]
Final Fire Inspection Required
Resolved
Prior to Issuance of TCO/CO/CC
Fire Prevention
Final Fire Alarm and Sprinkler Inspections Required. [Shannon Yaconiello @ 04/10/2025 3:28 PM] No sprinkler or alarm system. [Mike Middleton @ 01/08/2026 11:01 AM]
Miscellaneous Conditions
Resolved
Prior to Rough Building Wall Inspections
Building Department
If service is 400 amps or over engineered one-line drawings prior to rough inspection
Received and approved by Tom Cook. Resolved. [Malea Michael-Ferrier @ 02/11/2026 8:26 AM]
Truss Drawings Deferred Submittal
Resolved
Prior to Issuance of TCO/CO/CC
Building Department
Truss drawings (include truss layout plan) shall be submitted, reviewed and approved prior to installation and inspections.
Received, reviewed and resolved. [Malea Michael-Ferrier @ 02/11/2026 1:26 PM]
MF/Com/I Planning CO Review
Open
Prior to Issuance of TCO/CO/CC
Planning Department
At the time an applicant requests a “Final Building Inspection”, prior to issuance of a Certificate of Occupancy/Completion, the Department of Planning and Community Development will contact the applicant to inspect the site to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, outdoor lighting, parking, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
Vested Approval Conditions
Open
Prior to Issuance of CO/CC
Planning Department
Compliance with XXXX conditions of approval required.
FLC Submittal
Open
Prior to Rough Site Inspection
Planning Department
Foundation location certificate shall be provided
Miscellaneous Conditions
Resolved
Prior to Full Building Permit Issuance
Planning Department
Project must receive substantial conformance approval from planning prior to full building permit issuance.
Miscellaneous Conditions
Open
Prior to Issuance of TCO/CO/CC
Mount Werner Water & Sanitation
Water and sewer infrastructure must be installed, observed and tested per MWW Rules, Regs, Specifications and license agreement for detention pond within sewer easement must be executed prior to any issuance of occupancy.
Engineering Com/Ind/MF CO Review
Open
Prior to Issuance of TCO/CO/CC
Engineering
At the time of project completion, an Improvement Summary Letter or Completion Letter signed and sealed by the Engineer of Record shall be uploaded to the associated building permit in CityView Portal against the applicable condition. Upon receipt of the letter, Engineering will review and perform a Final Site Inspection for the TCO/CO request.
Miscellaneous Conditions
Resolved
Prior to Full Building Permit Issuance
Mount Werner Water & Sanitation
Payment of Plant Investment Fees to Mount Werner Water must be satisfied prior to permit issuance.