Summary

SPRSF241798
New Single Family Dwelling
Permit(s) Issued
MCENTEE GROUP, LLC
New
R-3 - Residential, one- and two-family
UNIT B of New construction of heavy timber duplex with conventional stick built garage. 3016 SF, 4 Bed/435 Bath with 681 SF attached Garage SPRSF241394: UNIT A: 200 Sundance Ct (all fees, valuation and reviews on this permit) SPRSF241798: UNIT B: 202 Sundance Ct
11/15/2024
11/15/2024

Locations

Property
142800020

Address
202 SUNDANCE CT

Permits

Permit Number: SPRSF241798-BD1

Building
Issued

Reviews

Review Type Outcome Est. Completion Date Completed
COO Review - Building Code Approved 01/26/2026 01/16/2026
COO Review - Finance Department TCO Approved 01/06/2026 01/06/2026
COO Review - Building Code TCO Approved 01/13/2026 01/06/2026
COO Review - Planning Approved 01/07/2026 12/30/2025
COO Review - Building Code Failed 12/30/2025 12/30/2025
COO Review - Planning Failed 01/06/2026 12/29/2025
COO Review - Engineering (SF/DU) TCO Approved 01/06/2026 12/29/2025
COO Review - Fire Code Approved 01/06/2026 12/29/2025
Building Code Review Approved 08/28/2025 08/25/2025
Building Code Review Approved 03/10/2025 03/03/2025
Building Code Review Approved 12/10/2024 12/04/2024
Utilities Review - City Approved 11/13/2024 11/14/2024
Planning Review Approved 11/13/2024 11/13/2024
Construction Site Management Review Approved 11/13/2024 11/08/2024
Building Code Review Approved 11/13/2024 11/06/2024
Utilities Review - City Failed 10/30/2024 10/31/2024
Construction Site Management Review Failed 10/30/2024 10/31/2024
Planning Review Failed 10/30/2024 10/30/2024
Building Code Review Failed 10/30/2024 10/24/2024
Planning Review Failed 09/26/2024 10/02/2024
Construction Site Management Review Failed 09/25/2024 09/27/2024
Utilities Review - City Failed 09/26/2024 09/27/2024
GIS Land Development Review Approved 09/26/2024 09/26/2024
Fire Code Review Approved 09/26/2024 09/26/2024
External Agencies Review Approved 09/26/2024 09/26/2024
Building Code Review Failed 09/26/2024 09/25/2024
Electrical Review Approved 09/26/2024 09/20/2024
Finance Department Review Approved 09/26/2024 09/12/2024

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Rough Site Inspection Pending
Scott Slamal
Final Site Inspection Pending
Scott Slamal
Corrections:


Miscellaneous
Outstanding
03/20/2026
Road base shouldering required where damaged along Sundance Ct approximately 50' up and down from the driveway access. City requires 18" of road base from edge of pavement. This will also need to be applied along Steamboat Blvd where the temporary access was used.

Miscellaneous
Outstanding
03/20/2026
All disturbed soils must be stabilized with native seed mix and biodegradable erosion control blankets including the drainage ditch on Sundance.

Miscellaneous
Outstanding
03/20/2026
The temporary construction access off Steamboat Blvd must be removed and the area regraded to its original condition, stabilized with native seed and biodegradable erosion control blankets.

Footing Inspection Partial Pass 12/6/2024 12/6/2024 12/06/2024
Ron Norton
Foundation Inspection Partial Pass 12/20/2024 (Afternoon) 12/27/2024 12/27/2024
Ron Norton
Foundation Inspection Partial Pass 12/27/2024 12/30/2024 12/30/2024
Ron Norton
Foundation Drain Inspection Partial Pass 1/30/2025 1/31/2025 01/31/2025
Ron Norton
Framing Inspection Partial Pass 2/18/2025 2/19/2025 02/19/2025
Ron Norton
Footing Inspection Partial Pass 02/25/2025
Ron Norton
Foundation Water Proofing Not Ready 2/25/2025 2/25/2025 02/25/2025
Ron Norton
Foundation Inspection Partial Pass 2/28/2025 2/28/2025 02/28/2025
Silas Ebbert
Foundation Drain Inspection Partial Pass 3/4/2025 3/4/2025 03/04/2025
Ron Norton
Wall/Roof Sheeting Passed 3/27/2025 3/27/2025 03/27/2025
Silas Ebbert
Footing Inspection Partial Pass 3/31/2025 3/31/2025 03/31/2025
Ron Norton
Foundation Inspection Partial Pass 3/31/2025 3/31/2025 03/31/2025
Ron Norton
Framing Inspection Partial Pass 05/05/2025
Ron Norton
Radon Piping Partial Pass 6/9/2025 6/9/2025 06/09/2025
Ron Norton
Foundation Inspection Partial Pass 7/2/2025 7/2/2025 07/02/2025
Ron Norton
Framing Inspection Partial Pass 8/11/2025 8/11/2025 08/11/2025
Ron Norton
Insulation Inspection Passed 8/21/2025 8/21/2025 08/21/2025
Ron Norton
Sewer Service Inspection Passed 8/20/2025 8/20/2025 09/05/2025
Baseline Inspectors
Shower Pan Passed 9/11/2025 09/11/2025
Todd Carr
Water Service Inspection Passed 9/25/2025 9/25/2025 09/25/2025
Baseline Inspectors
Building Final Inspection Passed 12/29/2025 12/29/2025 12/29/2025
Jeff Yeiser
Final Site Inspection Failed 3/18/2026 3/18/2026 03/20/2026
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
03/20/2026
Road base shouldering required where damaged along Sundance Ct approximately 50' up and down from the driveway access. City requires 18" of road base from edge of pavement. This will also need to be applied along Steamboat Blvd where the temporary access was used.

Miscellaneous
Carried Forward
03/20/2026
All disturbed soils must be stabilized with native seed mix and biodegradable erosion control blankets including the drainage ditch on Sundance.

Miscellaneous
Carried Forward
03/20/2026
The temporary construction access off Steamboat Blvd must be removed and the area regraded to its original condition, stabilized with native seed and biodegradable erosion control blankets.

Conditions

Condition Status Category
Use Tax Reconciliation Open Prior to Issuance of CO/CC
Finance
Use Tax Reconciliation
Building Department Conditions to be Completed Resolved Prior to Full Building Permit Issuance
Building Department
Malea to create permit for unit 2 of duplex.
Miscellaneous Conditions Resolved
Fire Prevention
Any fire alarm/sprinkler work will require a permit/plans to be submitted to Fire Prevention. See www.steamboatsprings.net, Fire and EMS Services, Fire Prevention, Downloadable Permits and Forms. NB [Charles Brookshire @ 09/26/2024 3:48 PM]
Final Fire Inspection Required Resolved Prior to Issuance of TCO/CO/CC
Fire Prevention
Fire needs to be involved with TCO/CO/CC sign-off in case there is an alarm or sprinkler permit. [Shannon Yaconiello @ 09/26/2024 4:08 PM]
Engineering Sf/Du CO Review Open Prior to Issuance of CO/CC
Engineering
At the time of project completion, request the Final Site Inspection from the Department of Public Works Engineering Div. to ensure the project has been built in accordance with the approved plans. [Scott Slamal @ 09/27/2024 2:22 PM]
Blower Door Test Results Resolved Prior to Certificate of Occupancy/Completion
Building Department
Blower Door Test Results Reviewed and resolved. [Malea Michael-Ferrier @ 01/16/2026 1:35 PM]
Heat Loss Calculations Deferred Submittal Resolved Prior to Mechanical Permit Issuance for Heat
Building Department
Heat Load Calculations must be submitted, Reviewed and approved prior to any heating equipment being installed. Reviewed and resolved. [Malea Michael-Ferrier @ 01/05/2026 3:03 PM]
Engineering Sf/Du CO Review Open Prior to Issuance of CO/CC
Engineering
The temporary construction access that has been used off Steamboat Blvd must be removed, regraded to its original condition and stabilized with native seed and biodegradable erosion control blankets prior to CO approval. [Scott Slamal @ 03/20/2026 1:34 PM]
FLC Submittal Resolved Prior to Rough Site Inspection
Planning Department
Foundation location certificate shall be provided FLC Review complete.
SFR/Dup Planning CO Review Resolved Prior to Issuance of TCO/CO/CC
Planning Department
Prior to issuance of a Certificate of Occupancy, the Department of Planning and Community Development may conduct an onsite inspection to ensure the project has been built in accordance with the approved plans and the Community Development Code. In the event the planning department deems an inspection necessary, a planning representative will contact the applicant. The applicant need not call for inspections. The inspection may include but is not limited to general site planning and grading, outdoor lighting, parking, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.

Related Permit & Planning Applications

Reference Number Status Type
SPRPL250611 Closed Plumbing
SPRPL250715 Closed Plumbing
SPREL250988 Closed Electrical
SPRMH251252 Closed Mechanical

Documents & Images

Date Uploaded File Type Name
Report
Report
Report
Report
Report
Plans ALPHA FIREPLACE.PDF.PDF
Plans ARCHITECTURAL-10_18_2024 SEAD REDLINES.PDF (RECEIVED) (STAMPED).PDF
Plans C3 - SITE PLAN.PDF (RECEIVED) (STAMPED).PDF
Plans C5 - UTILITY PLAN (RECEIVED) (STAMPED).PDF
Plans C6 - CSMP (STAMPED).PDF.PDF
Letter CERTIFICATE OF TEMPORARY OCCUPANCY.PDF
Letter CERTIFICATE OF TEMPORARY OCCUPANCY0.PDF
Plans CIVIL PLAN SET REVISED 10-16-2024 (STAMPED).PDF
Plans GARAGEWINDOWNARRATIVE_STEAMBOATDUPLEX_24043.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Permit PERMIT - DETAILED.PDF
11/15/2024 Plans Structural Drawings (Stamped) (3)
12/04/2024 24042_Footing Letter (Stamped)
12/04/2024 Letter 24042_Foundation Changes Letter (1) (Stamped)
03/03/2025 Plans New Header Letter 02.27.2025 (Stamped)
08/25/2025 Plans Fire seperation detail 20250821 (Stamped)
08/25/2025 24042_Fire Separation (Stamped)
08/25/2025 202 Sundance Ct Insulation certs
11/26/2025 IMG_2326
11/26/2025 IMG_2328
11/26/2025 IMG_2327
11/26/2025 IMG_2325
12/30/2025 Lot 20 Mtn View FLC-ILC
01/05/2026 Manual J (Steamboat)
01/05/2026 Manual S
01/05/2026 Radiant Layout (Steamboat)
01/05/2026 Radiant Report (Steamboat)
01/05/2026 200 Sundance CT Insulation certs
01/05/2026 Final Order Window Rushmore Quote Report- Customer 7168504
01/05/2026 Final Order Windows Steamboat Quote Report- Customer 7168498 (1)
01/16/2026 Report 2021 IECC Air-leakage Test - 202 Sundance Ct-2
03/20/2026 IMG_0318
03/20/2026 IMG_0313
03/20/2026 IMG_0316
03/20/2026 IMG_0321
03/20/2026 IMG_0317
03/20/2026 IMG_0312
03/20/2026 IMG_0311
03/20/2026 IMG_0323
03/20/2026 IMG_0319
03/20/2026 IMG_0315
03/20/2026 IMG_0320
03/20/2026 IMG_0314