Permit Application Status
B-21-632
In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
COO Review - Fire Code | Approved | 04/24/2023 | 06/20/2023 |
Doug Shaffer
|
|||
Fire sprinkler in small mech room mentioned in TCO is completed. | |||
COO Review - Building Code | Approved | 04/24/2023 | 04/17/2023 |
Todd Carr
|
|||
COO Review - Building Code | Failed | 03/15/2023 | 03/15/2023 |
Heidi Spengler
|
|||
Need to pass all final inspections. Certificate of completion not approved. | |||
Fire Code Review | TCO Approved | 11/17/2021 | 12/07/2021 |
Doug Shaffer
|
|||
Miscellaneous
Outstanding
12/07/2021
Miscellaneous Corrections Failed CO due to small mech/elect. room at north end of locker room in bldg. C needs fire sprinkler coverage fixed.
|
|||
TCO/CO/CC Approval Failed CO due to small mech/elect. room at north end of locker room in bldg. C needs fire sprinkler coverage fixed. | |||
Building Code Review | TCO Approved | 11/17/2021 | 11/17/2021 |
Heidi Spengler
|
|||
Needs final building inspection. | |||
Finance Department Review | TCO Approved | 11/17/2021 | 11/16/2021 |
Amy Camilletti
|
|||
TCO/CO/CC Approval The City of Steamboat Springs Finance department has approved a TEMPORARY CERTIFICATE on this project. A construction use tax reconciliation must be completed within 90 days to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department. | |||
Utilities Review - Mt. Werner | Approved | 11/17/2021 | 11/11/2021 |
Richard Buccino
|
|||
TCO/CO/CC Approval | |||
Planning Review | Approved | 11/17/2021 | 11/10/2021 |
Michael Fitz
|
|||
TCO/CO/CC Approval | |||
GIS Land Development Review | Approved | 11/17/2021 | 11/09/2021 |
Heidi Spengler
|
|||
Approved for CC. RCBD | |||
Fire Code Review | Approved | 07/14/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Fire Dept sysadmin - Jul 14 2021 10:06AM - 6/25/21 Conditionally approved- pending resubmittal of site plan with access width, grade, turning radius, turnaround, and turnouts meeting Fire Dept. access requirements or if unable to meet requirements submittal of fire sprinkler and monitored fire alarm plans and permits. No inspections past foundation until the above is resolved.) www.steamboatsprings.net for details. sysadmin - Jul 14 2021 10:06AM - 7/9/21 The drawings with the fire truck movements are acceptable for our purposes. The Fire Marshal has asked that the GC add those drawing to the plans that you submitted. | |||
Legacy Permitting Review | Approved | 07/13/2021 | |
SysAdmin
|
|||
VP legacy plan review: Mt Werner Water District sysadmin - Jul 6 2021 1:56PM - Sarah with Gensler working on PIF Qty take-off. | |||
Legacy Permitting Review | Approved | 07/06/2021 | |
SysAdmin
|
|||
VP legacy plan review: Routt Electrical Plan Review | |||
Legacy Permitting Review | Approved | 06/29/2021 | |
SysAdmin
|
|||
VP legacy plan review: Routt Building sysadmin - Jun 15 2021 11:15AM - Plan review process started sysadmin - Jun 29 2021 2:21PM - permit approved subject to deferrred submittals | |||
Planning Review | Approved | 06/24/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Planning sysadmin - Jun 24 2021 11:20AM - OK per BK | |||
GIS Land Development Review | Approved | 06/17/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Address | |||
Finance Department Review | Approved | 06/15/2021 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Finance Dept sysadmin - Jun 15 2021 11:23AM - City of Steamboat Springs Finance has approved City tax & permit fees of $63,208.69 on this permit. This is the City’s portion, made payable to the City of Steamboat Springs and submitted to the Routt County Regional Building Department. At the end of the project, City of Steamboat Springs Finance requires a construction use tax reconciliation be completed to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/approval with the Routt County Building Department. |
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Framing Inspection | Partial Pass | 9/13/2021 | 9/13/2021 | 09/13/2021 |
Don Marchbanks | ||||
Framing Inspection | Partial Pass | 9/20/2021 | 9/20/2021 | 09/20/2021 |
Todd Carr | ||||
Framing Inspection | Partial Pass | 9/27/2021 | 9/27/2021 | 09/27/2021 |
Silas Ebbert | ||||
Framing Inspection | Partial Pass | 10/7/2021 | 10/7/2021 | 10/07/2021 |
Don Marchbanks | ||||
Framing Inspection | Partial Pass | 10/13/2021 | 10/13/2021 | 10/13/2021 |
Don Marchbanks | ||||
Building Final Inspection | Partial Pass | 11/5/2021 | 11/5/2021 | 11/05/2021 |
Todd Carr | ||||
Building Final Inspection | Partial Pass | 12/7/2021 | 12/7/2021 | 12/07/2021 |
Todd Carr | ||||
Corrections:
Miscellaneous
Carried Forward
12/07/2021
Below Conditions left to complete prior to full CO approval, all spaces approved for TCO.
1. 3rd and 4th Floor Building A: All work completed except minor work related to interior doors, door hardware, must re-install exit door hardware to north side interior exit stairs and remove paint over door rating labels. Water Heater needs to be connected to outlet or junction box by the water heater to avoid the cord stretching over the door. Missing drinking fountain, and missing permanent exterior door and entryway. Building C has work left for permanent fixtures and lockers to be installed. Building F is approved except for floor drain inside of water heater room, this needs to be sealed around the floor drain. Must receive final As-Built plans for the mechanical work related to the commercial laundry room, for dryer exhaust configuration and make-up air to this room, the plans do not match the installation, have Mechanical Engineer review the dryer exhaust lines, draw up plans to match the work, and show where the dampers are installed which are gravity dampers inside the room, show insulation on dryer exhaust, then currently we have non-conditions make-up air coming into the room all the time through a wall louver, please have the Mechanical Engineer review this louver in the mechanical code and energy code. Include diagrams of how the dryer terminates outside with elbows pointing exhaust downward towards louvers, with distances above louvers.
|
||||
Framing Inspection | Partial Pass | 12/10/2021 | 12/10/2021 | 12/10/2021 |
Todd Carr | ||||
Building Final Inspection | Not Ready | 12/20/2021 | 12/20/2021 | 12/20/2021 |
Todd Carr | ||||
Corrections:
Miscellaneous
Carried Forward
12/20/2021
Below Conditions left to complete prior to full CO approval, all spaces approved for TCO.
1. 3rd and 4th Floor Building A: All work completed except minor work related to interior doors, door hardware, must re-install exit door hardware to north side interior exit stairs and remove paint over door rating labels. Water Heater needs to be connected to outlet or junction box by the water heater to avoid the cord stretching over the door. Missing drinking fountain, and missing permanent exterior door and entryway. Building C has work left for permanent fixtures and lockers to be installed. Building F is approved except for floor drain inside of water heater room, this needs to be sealed around the floor drain. Must receive final As-Built plans for the mechanical work related to the commercial laundry room, for dryer exhaust configuration and make-up air to this room, the plans do not match the installation, have Mechanical Engineer review the dryer exhaust lines, draw up plans to match the work, and show where the dampers are installed which are gravity dampers inside the room, show insulation on dryer exhaust, then currently we have non-conditions make-up air coming into the room all the time through a wall louver, please have the Mechanical Engineer review this louver in the mechanical code and energy code. Include diagrams of how the dryer terminates outside with elbows pointing exhaust downward towards louvers, with distances above louvers.
|
||||
Building Final Inspection | Failed | 3/7/2023 | 3/7/2023 | 03/08/2023 |
Todd Carr | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
03/08/2023
Areas in the parking garage that need fire caulk have been emailed to Alec, above the AC unit platform on far south end of garage, then above overhead door that enters the Sheraton we have gas lines penetrating that need fire caulk.
|
||||
Building Final Inspection | Passed | 4/17/2023 | 4/17/2023 | 04/17/2023 |
Todd Carr | ||||
Corrections:
Building Department Corrections to be Completed
Resolved
04/17/2023
Areas in the parking garage that need fire caulk have been emailed to Alec, above the AC unit platform on far south end of garage, then above overhead door that enters the Sheraton we have gas lines penetrating that need fire caulk.
|
Condition | Status | Category |
---|---|---|
Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
Finance
Consent agreement executed due July 31, 2023
|
||
Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
Building Department
Below Conditions left to complete prior to full CO approval, all spaces approved for TCO.
1. 3rd and 4th Floor Building A: All work completed except minor work related to interior doors, door hardware, must re-install exit door hardware to north side interior exit stairs and remove paint over door rating labels. Water Heater needs to be connected to outlet or junction box by the water heater to avoid the cord stretching over the door. Missing drinking fountain, and missing permanent exterior door and entryway. Building C has work left for permanent fixtures and lockers to be installed. Building F is approved except for floor drain inside of water heater room, this needs to be sealed around the floor drain. Must receive final As-Built plans for the mechanical work related to the commercial laundry room, for dryer exhaust configuration and make-up air to this room, the plans do not match the installation, have Mechanical Engineer review the dryer exhaust lines, draw up plans to match the work, and show where the dampers are installed which are gravity dampers inside the room, show insulation on dryer exhaust, then currently we have non-conditions make-up air coming into the room all the time through a wall louver, please have the Mechanical Engineer review this louver in the mechanical code and energy code. Include diagrams of how the dryer terminates outside with elbows pointing exhaust downward towards louvers, with distances above louvers.
|
Reference Number | Status | Type |
---|---|---|
SPREL210168 | Closed | Electrical |
SPRMH210323 | Closed | Mechanical |
SPRPL210327 | Closed | Plumbing |