Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
COO Review - Building Code | Approved | 03/17/2025 | 03/17/2025 |
Malea Michael-Ferrier
|
|||
COO Review - Finance Department | Approved | 03/11/2025 | 03/04/2025 |
Sondra Spratta
|
|||
COO Review - Engineering (SF/DU) | Approved | 02/19/2025 | 02/27/2025 |
Scott Slamal
|
|||
Approval based on receipt and execution of Revegetation Agreement. [Scott Slamal @ 02/27/2025 4:40 PM] | |||
COO Review - Fire Code | Approved | 02/18/2025 | 02/25/2025 |
Shannon Yaconiello
|
|||
CO Approved. [Shannon Yaconiello @ 02/25/2025 11:05 AM] | |||
COO Review - Building Code | TCO Approved | 02/18/2025 | 02/18/2025 |
Malea Michael-Ferrier
|
|||
CO Review | |||
COO Review - Finance Department | TCO Approved | 02/18/2025 | 02/11/2025 |
Sondra Spratta
|
|||
CO Review | |||
Planning Review | Approved | 06/27/2024 | 06/28/2024 |
Darby Kenyon
|
|||
Addendum submitted on 06/19/2024 Review notes: structural addendum OK. | |||
Building Code Review | Approved | 06/27/2024 | 06/27/2024 |
Ted Allen
|
|||
Addendum submitted on 06/19/2024 No narrative however Structural uploaded has changed to dropped deck beams and deleted a few details on S2. | |||
Planning Review | Approved | 09/27/2023 | 09/22/2023 |
Darby Kenyon
|
|||
Updated Planning Review: The proposed development meets the overall building height and average plate height requirements. The planning review correction can be resolved, and the planning review can be approved. -DK | |||
Planning Review | Failed | 09/07/2023 | 09/08/2023 |
Darby Kenyon
|
|||
Label Plate
Resolved
09/22/2023
Overall height and average plate height: Please label the existing grade on the Architectural Planset drawing, A2.0 + A2.1. The overall height and the average plate height is measured from the existing grade.
Resolved 9/22 Elevation plans updated. DK
|
|||
ADDENDUM: See Barnett Residence Narrative This planning review is in correspond with the most recent planset submission and does not reference previous submission plansets. Lot coverage and FAR OK. Patio and deck OK. Setbacks OK. Informational comment: When final light fixtures are selected, applicant should refer to CDC Section 405 Exterior Lighting Standards (specifically 405.D.2) to ensure code compliance and avoid any code enforcement cases. | |||
Building Code Review | Approved | 09/07/2023 | 09/06/2023 |
Ted Allen
|
|||
ADDENDUM: See Barnett Residence Narrative | |||
Utilities Review - Mt. Werner | Approved | 09/07/2023 | 09/05/2023 |
Frank Alfone
|
|||
ADDENDUM: See Barnett Residence Narrative | |||
Utilities Review - Mt. Werner | Approved | 08/29/2022 | 09/06/2022 |
Richard Buccino
|
|||
Building Code Review | Approved | 08/29/2022 | 08/24/2022 |
Ted Allen
|
|||
Miscellaneous
Carried Forward
08/24/2022
Retaining walls shall be designed to ensure stability against overturning, sliding, excessive foundation
pressure and water uplift. Retaining walls shall be designed for a safety factor of 1.5 against lateral sliding and
overturning. Provide engineered design of retaining wall shown in plan framing the exterior stairs in Site Plan
and Sheet A02.00 and in elevation on Sheet A03.00 of approximately 10-feet. The engineer in responsible
charge of the design shall verify in writing if special inspection is required by IBC Section 1704 to include
retaining walls, specifically MSE as applicable. The inspection program shall designate the portions of the
work that require special inspection and the name or names of the individuals or firms who are to perform the
special inspections, and indicate the duties of the special inspectors. Special inspectors shall be employed by
the owner, the architect or engineer responsible for the design, or an agent of the owner, but NOT by the
contractor or any other person responsible for the work. Provide the name or names of the individuals or firms
who are to perform the special inspections. Carl Warnke-Engineering Designworks
|
|||
Miscellaneous
Carried Forward
08/24/2022
Provide details of what appears as a fireplace labelled in rec room as FP and also one shown in Section
B/A04.00 in the living room above. Include the type of fuel as we need type of fuel used by fireplace (FP) to
finish plan review. Fireplace shall be gas, all with tight-fitting doors and outside combustion air.- Zero Clearance Gas Fireplace.
|
|||
Construction Stormwater Review | Approved | 08/09/2022 | 08/19/2022 |
Scott Slamal
|
|||
Utilities Review - Mt. Werner | Failed | 08/09/2022 | 08/11/2022 |
Malea Michael-Ferrier
|
|||
PIF Fees sent to Beau at Vaussa 8-3-22. | |||
Planning Review | Approved | 08/09/2022 | 08/08/2022 |
Kelly Douglas, AICP
|
|||
Average plate height ok, overall height ok. KD | |||
Building Code Review | Failed | 08/09/2022 | 08/03/2022 |
Ted Allen
|
|||
Miscellaneous
Carried Forward
08/19/2022
Retaining walls shall be designed to ensure stability against overturning, sliding, excessive foundation
pressure and water uplift. Retaining walls shall be designed for a safety factor of 1.5 against lateral sliding and
overturning. Provide engineered design of retaining wall shown in plan framing the exterior stairs in Site Plan
and Sheet A02.00 and in elevation on Sheet A03.00 of approximately 10-feet. The engineer in responsible
charge of the design shall verify in writing if special inspection is required by IBC Section 1704 to include
retaining walls, specifically MSE as applicable. The inspection program shall designate the portions of the
work that require special inspection and the name or names of the individuals or firms who are to perform the
special inspections, and indicate the duties of the special inspectors. Special inspectors shall be employed by
the owner, the architect or engineer responsible for the design, or an agent of the owner, but NOT by the
contractor or any other person responsible for the work. Provide the name or names of the individuals or firms
who are to perform the special inspections.
|
|||
Miscellaneous
Carried Forward
08/19/2022
Provide details of what appears as a fireplace labelled in rec room as FP and also one shown in Section
B/A04.00 in the living room above. Include the type of fuel as we need type of fuel used by fireplace (FP) to
finish plan review. See our website for Indoor Wood Burning and Pellet Stove Fireplace Permits and Policies.
|
|||
External Agencies Review | Approved | 06/27/2022 | 06/28/2022 |
Malea Michael-Ferrier
|
|||
ATMOS ATMOS ENERGY CORPORATION 2# Systems will not be allowed unless proof of an appliance requiring a MINUMUM of over 7" W.C. is provided to Atmos Energy Corporation personnel for review. Meter location must be approved by an Atmos Energy Corporation employee during a mandatory site visit to be scheduled after foundation is in place. Meters will not be allowed under a shedding roofline or where overhanging snow is a danger to the meter set. Any work performed in utility easements must be approved by Atmos Energy Corp | |||
Building Code Review | Failed | 06/27/2022 | 06/24/2022 |
Ted Allen
|
|||
Miscellaneous
Carried Forward
08/01/2022
Retaining walls shall be designed to ensure stability against overturning, sliding, excessive foundation pressure and water uplift. Retaining walls shall be designed for a safety factor of 1.5 against lateral sliding and overturning. Provide engineered design of retaining wall shown in plan framing the exterior stairs in Site Plan and Sheet A02.00 and in elevation on Sheet A03.00 of approximately 10-feet. The engineer in responsible charge of the design shall verify in writing if special inspection is required by IBC Section 1704 to include retaining walls, specifically MSE as applicable. The inspection program shall designate the portions of the work that require special inspection and the name or names of the individuals or firms who are to perform the special inspections, and indicate the duties of the special inspectors. Special inspectors shall be employed by the owner, the architect or engineer responsible for the design, or an agent of the owner, but NOT by the contractor or any other person responsible for the work. Provide the name or names of the individuals or firms who are to perform the special inspections.
|
|||
Miscellaneous
Carried Forward
08/01/2022
Provide complete details and dimensions of all stairs to include rise and run of rectangular treads or winders or combination thereof from one landing to another such as the exterior stair referenced above to include handrails, guards at open sides of stairways.
|
|||
Miscellaneous
Carried Forward
08/01/2022
The adopted codes in Routt County are the 2018 ICC model codes to include APPENDIX F
RADON CONTROL METHODS. Required on all New Single Family home, Passive Radon Gas Controls are required. The components of a passive submembrane depressurization system shall be installed during construction.
|
|||
Miscellaneous
Carried Forward
08/01/2022
Call-out the continuous insulation shown on the sections on Sheet A04.02 for walls at slab. The value as shown in table on Sheet A0.00 calls for a minimum of R-10 insulation from the top of the slab downward 48" without gaps. Please show this along with brick veneer without gaps to protect the insulation’s thermal performance on the plans.
|
|||
Miscellaneous
Carried Forward
08/01/2022
Provide details of what appears as a fireplace labelled in rec room as FP and also one shown in Section B/A04.00 in the living room above. Include the type of fuel as we need type of fuel used by fireplace (FP) to finish plan review. See our website for Indoor Wood Burning and Pellet Stove Fireplace Permits and Policies.
|
|||
Miscellaneous
Carried Forward
08/01/2022
Informational: I have set conditions for deferred heat load calculations, and blower door test to be completed.
|
|||
Construction Stormwater Review | Failed | 06/06/2022 | 06/22/2022 |
Scott Slamal
|
|||
Miscellaneous
Carried Forward
08/01/2022
City Construction Stormwater Permit required for projects in Eagle Vista. Complete permit and Small Site SWMP.
https://steamboatsprings.net/354/Engineering-Documents
|
|||
Planning Review | Failed | 06/27/2022 | 06/20/2022 |
Kelly Douglas, AICP
|
|||
Miscellaneous
Carried Forward
08/01/2022
Please add existing grade to all elevations and sections in order to confirm compliance with RN-2 overall height and average plate height.
|
|||
Miscellaneous
Carried Forward
08/01/2022
Please label the the uppermost wall plate of the exterior wall that bears the building’s highest roof structure on all elevations in order to confirm compliance with RN-2 average plate height.
|
|||
Setbacks ok per reception no. 795570, lot coverage ok, | |||
GIS Land Development Review | Approved | 06/27/2022 | 06/20/2022 |
Colten Yoast
|
|||
Fire Code Review | Approved | 06/27/2022 | 06/15/2022 |
Mike Middleton
|
|||
Finance Department Review | Approved | 06/27/2022 | 06/13/2022 |
Amy Camilletti
|
|||
City of Steamboat Springs Finance has approved City permit fees and taxes on this building permit. This is the City's portion, payable to the City of Steamboat Springs and submitted via the Routt County Regional Building Department or City View online portal. At the end of the project, the City of Steamboat Springs Finance requires a construction use tax reconciliation to be completed to be compliant with the City of Steamboat Springs Municipal Code AND before signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department. | |||
Utilities Review - Mt. Werner | Failed | 06/27/2022 | 06/13/2022 |
Richard Buccino
|
|||
Miscellaneous
Carried Forward
08/01/2022
Water and Sewer fees send to beau@vaussa.com on 6-13-22.
|
|||
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Foundation Drain Inspection | Partial Pass | 10/20/2022 | ||
Ron Norton | ||||
Foundation Drain Inspection | Partial Pass | 11/10/2022 | 11/10/2022 | 11/10/2022 |
Ron Norton | ||||
Structural Inspection | Stop Work | 8/31/2023 | 8/31/2023 | 08/31/2023 |
Todd Carr | ||||
Corrections:
Building Department Corrections to be Completed
Outstanding
08/31/2023
The Building Department (Todd Carr) and City Engineering (Scott Slamal) performed a site inspection today based on complaints and concerns about Public Safety from the property owners to the north ease directly adjacent to this project, concerns related to over-excavation along the property line. This project has not had a Legal Contractor of Record since 04/28/2023, the Building Department received an email from the owners representative and owner stating to remove Vaussa Construction on 04/28/2023 and for us to add Salt Box Construction, however we have never received notification from Salt Box accepting legal responsibilities as the contractor, therefore this permit should have been Revoked on 04/28/2023. At this time the permit has been revoked until such a time a Contractor who is certified in Routt County takes on legal responsibility for the project.
The Building Department is placing a Stop Work on the project at this time until the following items are resolved and corrected, once all work has been completed per the corrections listed below we can allow work to continue with the footings and foundation. At this time only excavation work may proceed and stabilization and safety work.
1. Must have a Certified Residential Contractor accept responsibility for the project, and email the building department to accept responsibility.
2. The excavation cut has crossed the physical property line toward the back of the property close to where the dumpster sit's on the neighboring property, it has broken off a piece of the asphalt driveway in this location, it also has caused the existing blacktop driveway to buckle and crack and deflect a little towards the property under construction. Additionally the safety fence is not installed anymore along this cut, but rather laying on the ground offering no fall protection to the excavation cut performed on this property. We are requiring you to work with our Contractors, and ensure the excavation work is completed and corrected in accordance with OSHA regulations and stabilized to ensure the neighboring property is not compromised further or a collapse of the cut were to take place. The neighboring property has a lot of vehicles the enter and exit this driveway, along with a trash truck that would pick up the dumpster, it's the Owners/Contractors responsibility to ensure safety is met and excavation work is done in accordance with OSHA regulations. We are requesting you work quickly to resolve the current conditions on the site, and request you contact the property owner adjacent to this site to gain permission if you have not already to perform safety work on their property to install a proper fence or barricade to protect against fall protection. Additionally it appears you have pulled out a black 4" conduit that may have either electrical or technology cabling inside of it, this must be placed back into the cut when you perform proper backfill and compaction work. Additionally you will need to restore the damaged asphalt driveway prior to obtaining a TCO on your project, but as soon as practical after all backfill work has been completed after the foundation walls have been poured.
Please contact Scott Slamal and Todd Carr for a re-inspection after the safety measures and stabilization work have been completed, so we can perform a site visit and provide approval for footing and foundation work to continue.
|
||||
Structural Inspection | Passed | 09/20/2023 | ||
Todd Carr | ||||
Footing Inspection | Partial Pass | 10/3/2023 | 10/3/2023 | 10/03/2023 |
Jeff Yeiser | ||||
Foundation Inspection | Partial Pass | 10/13/2023 | 10/13/2023 | 10/13/2023 |
Todd Carr | ||||
Foundation Inspection | Passed | 10/24/2023 | 10/24/2023 | 10/24/2023 |
Todd Carr | ||||
Foundation Drain Inspection | Passed | 10/24/2023 | 10/24/2023 | 10/24/2023 |
Jeff Yeiser | ||||
Insulation Inspection | Partial Pass | 11/13/2023 | 11/13/2023 | 11/13/2023 |
Ron Norton | ||||
Roofing Inspection | Not Ready | 2/12/2024 | 2/12/2024 | 02/12/2024 |
Ron Norton | ||||
Roofing Inspection | Failed | 2/12/2024 | 2/13/2024 | 02/13/2024 |
Ron Norton | ||||
Roofing Inspection | Not Ready | 2/14/2024 | 2/14/2024 | 02/14/2024 |
Ron Norton | ||||
Roofing Inspection | Passed | 2/14/2024 | 02/14/2024 | |
Ron Norton | ||||
Framing Inspection | Partial Pass | 5/2/2024 | 5/2/2024 | 05/02/2024 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 6/21/2024 | 6/21/2024 | 06/21/2024 |
Jeff Yeiser | ||||
Insulation Inspection | Passed | 7/19/2024 (Morning) | 7/22/2024 | 07/22/2024 |
Jeff Yeiser | ||||
Drywall Inspection | Partial Pass | 7/25/2024 | 7/26/2024 | 07/26/2024 |
Heidi Spengler | ||||
Shower Pan | Partial Pass | 10/1/2024 | 10/2/2024 | 10/02/2024 |
Ron Norton | ||||
Shower Pan | Passed | 10/18/2024 | 10/18/2024 | |
Ron Norton | ||||
Building Final Inspection | Failed | 2/10/2025 | 2/10/2025 | 02/10/2025 |
Ron Norton | ||||
Building Final Inspection | Partial Pass | 2/13/2025 | 2/13/2025 | 02/13/2025 |
Ron Norton | ||||
Building Final Inspection | Passed | 3/14/2025 | 3/14/2025 | 03/14/2025 |
Ron Norton |
Condition | Status | Category |
---|---|---|
Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
Sales Tax Department
Use Tax Reconciliation City of Steamboat Springs Finance has approved City permit fees and taxes on this building permit. This is the City's portion, payable to the City of Steamboat Springs and submitted via the Routt County Regional Building Department or City View online portal.
At the end of the project, the City of Steamboat Springs Finance requires a construction use tax reconciliation to be completed to be compliant with the City of Steamboat Springs Municipal Code AND before signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department.
|
||
Miscellaneous Conditions | Resolved | |
Fire Prevention
Full Permit - Any fire alarm/sprinkler work will require permit/plans to be submitted by sub-contractor to Fire Prevention.
|
||
Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
Fire Prevention
Fire needs to be involved with TCO/CO/CC sign-off in case there is an alarm or sprinkler permit.
|
||
FLC Submittal | Resolved | Prior to Rough Site Inspection |
Planning Department
Foundation location certificate shall be provided
FLC review OK.
|
||
SFR/Dup Planning CO Review | Resolved | Prior to Issuance of TCO/CO/CC |
Planning Department
At the time of project completion, request certificate of occupancy inspections from the Department of Planning and Community Development to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, outdoor lighting, parking, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
|
||
Blower Door Test Results | Resolved | Prior to Certificate of Occupancy/Completion |
Building Department
Blower Door Test Results
|
||
Heat Loss Calculations Deferred Submittal | Resolved | Prior to Mechanical Permit Issuance for Heat |
Building Department
Heat Load Calculations must be submitted, Reviewed and approved prior to any heating equipment being installed.
|
||
Special Inspections Deffered Submittal | Resolved | Prior to Final Building Inspection |
Building Department
Special Inspection Reports shall be submitted immediately upon conclusion of the special inspections regardless if it passed or failed and prior to any work being done beyond this point if it failed..The name or names of the individuals or firms who are to perform the special inspections of boulder retaining walls is Carl Warnke-Engineering Designworks.
|
||
Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
Mount Werner Water & Sanitation
Further inspection by MWW required before any issuance of occupancy can be issued. Water service line does not meet MWW material spec; applicant must confirm service line material and install tracer wire if serve line material is anything other than type k copper.
Jim with Saltbox confirmed via phone that the transition to poly pipe occurs right at the house. [bcahill @ 01/16/2025 1:14 PM]
|
||
Building Department Conditions to be Completed | Resolved | Prior to Issuance of CO/CC |
Building Department
Building Department Conditions to be Completed:
Completed patio
Complete upper cabinets and add grille to ERV supply above cabinet.
|
||
Engineering Sf/Du CO Review | Resolved | Prior to Issuance of TCO/CO/CC |
Engineering
At the time of project completion, request the Final Site Inspection from the Department of Public Works Engineering Div. to ensure the project has been built in accordance with the approved plans.
|
Reference Number | Status | Type |
---|---|---|
SPREL231489 | Closed | Electrical |
SPRPL231578 | Closed | Plumbing |
SPRMH231639 | Closed | Mechanical |
SPRMH240368 | Closed | Mechanical |
SPRMH240892 | Closed | Mechanical |