Review Type
Outcome
Est. Completion Date
Completed
Public Works Review
Approved
09/09/2024
Amber Gregory
Miscellaneous
Outstanding
09/09/2024
As previously requested, the plans need cleaned up and the response letter must align with the response letter.
1. The callout for the abandoned service for lot 6 is pointing to the ROW line and not the service tap.
2. The water service to lot 8 is showing as being bored. Why would you bore the 3/4" service?
3. There is a stray callout for the 4" SDR pipe that points to nothing.
4. A random sewer line is shown parallel to the existing sewer main. Remove it or identify what it is.
5. The "replace and repair" callout on the main does not align with the response letter and verbal conversations that the service is a direct tap. Note 4 states that the tap needs confirmed yet the letter states a direct tap.
Again, please do not submit again until all comments are addressed and the plans are reviewed for quality control and alignment with the response letter.
Public Works Review
Failed
09/03/2024
Amber Gregory
Miscellaneous
Resolved
09/03/2024
Why does the long service go from 6" to 4"?
Miscellaneous
Resolved
09/03/2024
Confirm if the existing service tap identified as being replaced and repaired is a full bodied wye or a saddle tap. A full bodied wye would need sectioned out of the main and repair couplings installed. Is this the intent? If so a bypass would need to be installed for the existing sewer main.
**The connection type and a bypass pumping plan must be provided (if necessary)
Miscellaneous
Resolved
09/03/2024
Where is the existing sanitary sewer service for Lot 9 being abandon? The existing services must be shown on the plans.
Miscellaneous
Resolved
09/03/2024
provide the private sewer service easement recorded document
This will be provided once services are installed. [Amber Gregory @ 09/03/2024 11:24 AM]
Miscellaneous
Resolved
09/03/2024
Per the Muni-code, joint sewer services are not allowed. The response letter states that the 6" line is a joint service line. The service line also starts with a 4" line then turns to 6". Correction 4 states that you do not want to stub to lot 7 but drawing shows lot 7 stub and connection to joint service line. If Lot 7 does not wish to be stubbed, that is fine but there is no room on the shown plan for future connection and future connection must be accounted for.
Miscellaneous
Resolved
09/03/2024
Per the Standards, cleanouts are required any time bends are greater than 45-degrees. Add cleanouts where required.
Miscellaneous
Resolved
09/03/2024
In response t o correction 2 question - why wouldn't you use the wye if it is working? Where is the service leaking? A cap will not fix a broken wye. If the wye is leaking at the connection of the service line, the service line can be pulled out and a new service installed.
Miscellaneous
Resolved
09/03/2024
Stray callouts are located all over the document and linework is not labeled. Are you installing the 6"/4" line right at the creek bank? Please clean up the plans and make sure everything follows city standards and is consistent prior to resubmittal.
Miscellaneous
Carried Forward
09/09/2024
As previously requested, the plans need cleaned up and the response letter must align with the response letter.
1. The callout for the abandoned service for lot 6 is pointing to the ROW line and not the service tap.
2. The water service to lot 8 is showing as being bored. Why would you bore the 3/4" service?
3. There is a stray callout for the 4" SDR pipe that points to nothing.
4. A random sewer line is shown parallel to the existing sewer main. Remove it or identify what it is.
5. The "replace and repair" callout on the main does not align with the response letter and verbal conversations that the service is a direct tap. Note 4 states that the tap needs confirmed yet the letter states a direct tap.
Again, please do not submit again until all comments are addressed and the plans are reviewed for quality control and alignment with the response letter.
Public Works Review
Failed
08/27/2024
Amber Gregory
Miscellaneous
Carried Forward
09/03/2024
Why does the long service go from 6" to 4"?
Miscellaneous
Carried Forward
09/03/2024
Confirm if the existing service tap identified as being replaced and repaired is a full bodied wye or a saddle tap. A full bodied wye would need sectioned out of the main and repair couplings installed. Is this the intent? If so a bypass would need to be installed for the existing sewer main.
**The connection type and a bypass pumping plan must be provided (if necessary)
Miscellaneous
Carried Forward
09/03/2024
Where is the existing sanitary sewer service for Lot 9 being abandon? The existing services must be shown on the plans.
Miscellaneous
Resolved
08/27/2024
If sanitary sewer stubs are being created for future connection, the ends must be capped and the stubs be identified per Standards. Provide all required stub information.
Miscellaneous
Carried Forward
09/03/2024
provide the private sewer service easement recorded document
Miscellaneous
Resolved
08/27/2024
Several comments keep getting ignored with each resubmittal. Please provide a comment letter that addresses questions. How is lot 7 going to be served by sewer?
Miscellaneous
Carried Forward
09/03/2024
Per the Muni-code, joint sewer services are not allowed. The response letter states that the 6" line is a joint service line. The service line also starts with a 4" line then turns to 6". Correction 4 states that you do not want to stub to lot 7 but drawing shows lot 7 stub and connection to joint service line. If Lot 7 does not wish to be stubbed, that is fine but there is no room on the shown plan for future connection and future connection must be accounted for.
Miscellaneous
Carried Forward
09/03/2024
Per the Standards, cleanouts are required any time bends are greater than 45-degrees. Add cleanouts where required.
Miscellaneous
Carried Forward
09/03/2024
In response t o correction 2 question - why wouldn't you use the wye if it is working? Where is the service leaking? A cap will not fix a broken wye. If the wye is leaking at the connection of the service line, the service line can be pulled out and a new service installed.
Miscellaneous
Carried Forward
09/03/2024
Stray callouts are located all over the document and linework is not labeled. Are you installing the 6"/4" line right at the creek bank? Please clean up the plans and make sure everything follows city standards and is consistent prior to resubmittal.
Public Works Review
Failed
08/23/2024
Amber Gregory
Miscellaneous
Carried Forward
08/27/2024
Why does the long service go from 6" to 4"?
Miscellaneous
Carried Forward
08/27/2024
Confirm if the existing service tap identified as being replaced and repaired is a full bodied wye or a saddle tap. A full bodied wye would need sectioned out of the main and repair couplings installed. Is this the intent? If so a bypass would need to be installed for the existing sewer main.
Miscellaneous
Carried Forward
08/27/2024
Where is the existing sanitary sewer service for Lot 9 being abandon? The existing services must be shown on the plans.
Miscellaneous
Carried Forward
08/27/2024
If sanitary sewer stubs are being created for future connection, the ends must be capped and the stubs be identified per Standards. Provide all required stub information.
Miscellaneous
Carried Forward
08/27/2024
provide the private sewer service easement recorded document
Miscellaneous
Carried Forward
08/27/2024
Several comments keep getting ignored with each resubmittal. Please provide a comment letter that addresses questions. How is lot 7 going to be served by sewer?
Utilities Review - City
Failed
08/21/2024
Amber Gregory
Public Works Review
Failed
08/20/2024
08/20/2024
Amber Gregory
Miscellaneous
Resolved
08/21/2024
All bends must be shown. The cleanout at Lot 6, Block 12 must also have a bend
Miscellaneous
Resolved
08/20/2024
Lengths between fittings, min. grade, min. depth, must be shown on the plans.
Miscellaneous
Resolved
08/20/2024
cleanouts are required when bends are greater than 45-degrees whether it be a singular or aggregate bend configuration. Add cleanouts.
Miscellaneous
Carried Forward
08/23/2024
Why does the long service go from 6" to 4"?
Miscellaneous
Carried Forward
08/23/2024
Confirm if the existing service tap identified as being replaced and repaired is a full bodied wye or a saddle tap. A full bodied wye would need sectioned out of the main and repair couplings installed. Is this the intent? If so a bypass would need to be installed for the existing sewer main.
Miscellaneous
Carried Forward
08/23/2024
Where is the existing sanitary sewer service for Lot 9 being abandon? The existing services must be shown on the plans.
Miscellaneous
Resolved
08/21/2024
Callouts are cut off in the viewport for the water service. Correct.
Miscellaneous
Carried Forward
08/23/2024
If sanitary sewer stubs are being created for future connection, the ends must be capped and the stubs be identified per Standards. Provide all required stub information.
Miscellaneous
Carried Forward
08/23/2024
provide the private sewer service easement recorded document
Public Works Review
Failed
08/09/2024
Amber Gregory
Miscellaneous
Carried Forward
08/14/2024
All bends must be shown. The cleanout at Lot 6, Block 12 must also have a bend
Miscellaneous
Carried Forward
08/14/2024
Lengths between fittings, min. grade, min. depth, must be shown on the plans.
Miscellaneous
Carried Forward
08/14/2024
cleanouts are required when bends are greater than 45-degrees whether it be a singular or aggregate bend configuration. Add cleanouts.
Miscellaneous
Carried Forward
08/14/2024
Why does the long service go from 6" to 4"?
Miscellaneous
Carried Forward
08/14/2024
Confirm if the existing service tap identified as being replaced and repaired is a full bodied wye or a saddle tap. A full bodied wye would need sectioned out of the main and repair couplings installed. Is this the intent? If so a bypass would need to be installed for the existing sewer main.
Miscellaneous
Carried Forward
08/14/2024
Where is the existing sanitary sewer service for Lot 9 being abandon? The existing services must be shown on the plans.
Miscellaneous
Carried Forward
08/14/2024
Callouts are cut off in the viewport for the water service. Correct.
Miscellaneous
Carried Forward
08/14/2024
If sanitary sewer stubs are being created for future connection, the ends must be capped and the stubs be identified per Standards. Provide all required stub information.
There are no inspections for this engineering permit application, or you are not authorized to view them.
There are no conditions for this engineering permit application, or you are not authorized to view them.
There are no related items for this engineering permit application.