Summary

SPRSW240383
Construction Stormwater
Permit(s) Issued
SERAC PINE GROVE STEAMBOAT LAND OWNER LLC
New
This project consists of the ground-up construction of a four-story hotel and associated site improvements.
04/23/2024
05/13/2024
11/09/2024

Locations

Property
217100003

Address
1750 CENTRAL PARK DR

Permits

Permit Number: SPRSW240383-SW1

Construction Stormwater
Issued

Permit Number: SPRSW240383-LD1

Land Disturbance
Expired

Reviews

Review Type Outcome Est. Completion Date Completed
Construction Stormwater Review Approved 05/14/2024 05/13/2024
Construction Stormwater Review Failed 05/14/2024 05/06/2024
Construction Stormwater Review Failed 05/14/2024 04/29/2024

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Interim Construction Stormwater Pending
Scott Slamal
Final Construction Stormwater Pending
Scott Slamal
45 Day Inspection Pending 5/3/2026
Scott Slamal
Corrections:


Trash
Outstanding
03/16/2026
Trash must be picked up throughout site in the snow storage piles in detention ponds, and on the south and west side of the hotel.

Perimeter Control Measures
Outstanding
03/16/2026
Sediment barriers must be installed at the edge of pavement at the north detention pond where erosion had occurred on the slope of the pond.

Inlet Protection
Outstanding
03/16/2026
Inlet protection measures were damaged and must be replaced along Central Park Dr., Snap Dragon, and within the hotel parking lot.

Sediment Discharges
Outstanding
03/16/2026
Heavy sediment accumulation in the curb line along Snap Dragon needs to be cleaned out and the inlet protection replaced.

Temporary soil stabilization
Outstanding
03/16/2026
The damaged erosion control blankets on the south side of the hotel need to be maintained or reinstalled.

Sediment Discharges
Outstanding
03/16/2026
The hose placed at the storm inlet adjacent to the foundation for the grills/pool used to dewater the foundation is an illicit discharge violation and must be removed.

Perimeter Control Measures
Outstanding
03/16/2026
Perimeter control measures must be installed around the soil stock pile at the northeast corner of the property.

Material Spills and Leaks
Outstanding
03/16/2026
Materials from drywall and mortar mixing were noted on the ground and need to be cleaned up immediately.

Perimeter Control Measures
Outstanding
03/16/2026
The straw wattle check dams in the north swale on the property line need to be replaced immediately.

45 Day Inspection Pending 5/5/2026
Scott Slamal
45 Day Inspection Not Ready 6/27/2024 06/24/2024
Scott Slamal
45 Day Inspection Passed 7/12/2024 07/12/2024
Scott Slamal
45 Day Inspection Passed 8/21/2024 08/26/2024
Scott Slamal
45 Day Inspection Failed 11/18/2024 10/04/2024
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
10/04/2024
Cleanup, spilled cement wash out as noted during inspection.

Miscellaneous
Carried Forward
10/04/2024
Continue keeping up with sweeping Central Park dr.

45 Day Inspection Failed 12/8/2024 10/24/2024
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
10/24/2024
Cleanup, spilled cement wash out as noted during inspection.

Miscellaneous
Carried Forward
10/24/2024
Continue keeping up with sweeping Central Park dr.

45 Day Inspection Failed 5/16/2025 04/01/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
04/01/2025
Anchor Porta potty.

Miscellaneous
Carried Forward
04/01/2025
Reinstall inlet filter fabric at corner of Snapdragon and Central Park.

Miscellaneous
Carried Forward
04/01/2025
Continue to pick up trash as needed.

45 Day Inspection Failed 6/21/2025 05/07/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
05/07/2025
Further install erosion control blankets at Northwest sediment basin.

Miscellaneous
Carried Forward
05/07/2025
Install aggregate material at corner of entrance to prevent tracking.

Miscellaneous
Carried Forward
05/07/2025
Continue to pick up trash as needed.

45 Day Inspection Failed 8/9/2025 06/25/2025
Scott Slamal
Corrections:


Miscellaneous
Resolved
06/25/2025
Further install erosion control blankets at Northwest sediment basin.

Miscellaneous
Resolved
06/25/2025
Install aggregate material at corner of entrance to prevent tracking.

Miscellaneous
Carried Forward
06/25/2025
Continue to pick up trash as needed.

45 Day Inspection Failed 9/19/2025 08/05/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
08/05/2025
Continue to pick up trash as needed.

Miscellaneous
Carried Forward
08/05/2025
The Eco concrete washout pan was more than three quarters full and need to be emptied.

Miscellaneous
Carried Forward
08/05/2025
Sediment controls were needed at each of the stormwater pond outlets.

Miscellaneous
Carried Forward
08/05/2025
Rock socks or other measures were needed to contain the soil pile at Snap Dragon and Central Park Dr.

45 Day Inspection Failed 11/8/2025 09/23/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
09/24/2025
Some trash was noted and needs to be picked up daily and disposed of properly.

Miscellaneous
Carried Forward
09/24/2025
Control measures were not adequate to prevent sediment discharges from the site. Significant erosion was noted on the slopes of both stormwater facilities and sediment controls were not installed at each of the stormwater facility outlets.

Miscellaneous
Carried Forward
09/24/2025
The silt fence at the northern stormwater facility was down and needing to be replaced.

Miscellaneous
Carried Forward
09/24/2025
Sediment control measures were not installed behind the containers of the south stormwater facility where significant erosion was occurring.

Miscellaneous
Carried Forward
09/24/2025
Concrete waste was noted on the ground in the north stormwater facility with no containment.

Miscellaneous
Carried Forward
09/24/2025
The straw wattle below the silt fence at the north corner of the site needs to be mucked out or replaced.

Interim Construction Stormwater Failed 10/3/2025 10/07/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
10/07/2025
Install inlet protection at the southwest inlet at Snapdragon Wy and Central Park Dr.

Miscellaneous
Carried Forward
10/07/2025
Continue to pick up trash daily.

Miscellaneous
Carried Forward
10/07/2025
Install vehicle tracking controls at the south boundary where vehicles/equipment are accessing the site.

Miscellaneous
Carried Forward
10/07/2025
Install straw wattles in south detention pond along concrete trickle channel.

45 Day Inspection Failed 12/21/2025 11/04/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
11/06/2025
Control measures were not installed at the south stormwater facility outlet or along the edge of the trickle channel to prevent sediment discharges from the site. A Notice of Violation was sent on September 24, 2025 for the same violation where sediment was actively discharging from both stormwater facilities. The next significant stormwater management violation as determined by the city stormwater inspector will result in a Summons into the City of Steamboat Springs Municipal Court and criminal penalties as set forth in Section 1-15 of the Municipal Code. A person convicted of a violation is subject to potential penalties not to exceed $2,650.00 per offense. Each day the violation continues is a separate offense.

Miscellaneous
Carried Forward
11/06/2025
Trash was observed in locations around the site and must be picked up daily.

Miscellaneous
Carried Forward
11/06/2025
Sediment controls were not installed around stockpiles on Snapdragon Wy or at the stockpile located at the northeast corner of the site.

Miscellaneous
Carried Forward
11/06/2025
The dirt accumulation on Pinegrove Rd along the east boundary needs to be swept and removed.

45 Day Inspection Partial Pass 12/18/2025 12/17/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
12/17/2025
Control measures were not installed at the south stormwater facility outlet or along the edge of the trickle channel to prevent sediment discharges from the site. A Notice of Violation was sent on September 24, 2025 for the same violation where sediment was actively discharging from both stormwater facilities. The next significant stormwater management violation as determined by the city stormwater inspector will result in a Summons into the City of Steamboat Springs Municipal Court and criminal penalties as set forth in Section 1-15 of the Municipal Code. A person convicted of a violation is subject to potential penalties not to exceed $2,650.00 per offense. Each day the violation continues is a separate offense.

Miscellaneous
Carried Forward
12/17/2025
Trash was observed in locations around the site and must be picked up daily.

Miscellaneous
Carried Forward
12/17/2025
Sediment controls were not installed around stockpiles on Snapdragon Wy or at the stockpile located at the northeast corner of the site.

Miscellaneous
Carried Forward
12/17/2025
The dirt accumulation on Pinegrove Rd along the east boundary needs to be swept and removed.

45 Day Inspection Failed 1/31/2026 02/04/2026
Scott Slamal
Corrections:


Miscellaneous
Resolved
02/05/2026
Control measures were not installed at the south stormwater facility outlet or along the edge of the trickle channel to prevent sediment discharges from the site. A Notice of Violation was sent on September 24, 2025 for the same violation where sediment was actively discharging from both stormwater facilities. The next significant stormwater management violation as determined by the city stormwater inspector will result in a Summons into the City of Steamboat Springs Municipal Court and criminal penalties as set forth in Section 1-15 of the Municipal Code. A person convicted of a violation is subject to potential penalties not to exceed $2,650.00 per offense. Each day the violation continues is a separate offense.

Miscellaneous
Resolved
02/05/2026
Trash was observed in locations around the site and must be picked up daily.

Miscellaneous
Resolved
02/05/2026
Sediment controls were not installed around stockpiles on Snapdragon Wy or at the stockpile located at the northeast corner of the site.

Miscellaneous
Resolved
02/05/2026
The dirt accumulation on Pinegrove Rd along the east boundary needs to be swept and removed.

Miscellaneous
Carried Forward
02/05/2026
Pickup up building material trash from snow storage piles and around the roll off dumpsters.

45 Day Inspection Failed 4/30/2026 03/13/2026
Scott Slamal
Corrections:


Miscellaneous
Resolved
03/16/2026
Pickup up building material trash from snow storage piles and around the roll off dumpsters.

Trash
Carried Forward
03/16/2026
Trash must be picked up throughout site in the snow storage piles in detention ponds, and on the south and west side of the hotel.

Perimeter Control Measures
Carried Forward
03/16/2026
Sediment barriers must be installed at the edge of pavement at the north detention pond where erosion had occurred on the slope of the pond.

Inlet Protection
Carried Forward
03/16/2026
Inlet protection measures were damaged and must be replaced along Central Park Dr., Snap Dragon, and within the hotel parking lot.

Sediment Discharges
Carried Forward
03/16/2026
Heavy sediment accumulation in the curb line along Snap Dragon needs to be cleaned out and the inlet protection replaced.

Temporary soil stabilization
Carried Forward
03/16/2026
The damaged erosion control blankets on the south side of the hotel need to be maintained or reinstalled.

Sediment Discharges
Carried Forward
03/16/2026
The hose placed at the storm inlet adjacent to the foundation for the grills/pool used to dewater the foundation is an illicit discharge violation and must be removed.

Perimeter Control Measures
Carried Forward
03/16/2026
Perimeter control measures must be installed around the soil stock pile at the northeast corner of the property.

Material Spills and Leaks
Carried Forward
03/16/2026
Materials from drywall and mortar mixing were noted on the ground and need to be cleaned up immediately.

Perimeter Control Measures
Carried Forward
03/16/2026
The straw wattle check dams in the north swale on the property line need to be replaced immediately.

Interim Construction Stormwater Failed 3/24/2026 3/24/2026 03/26/2026
Scott Slamal
Corrections:


Perimeter Control Measures
Carried Forward
03/26/2026
1. Additional sediment barriers must be installed at the edge of pavement at the north detention pond where erosion is occurring on the slope of the pond. 2. Wattles were not installed per specifications. 3. Additional rocks needed at both outlet structures to prevent sediment discharging. 4. Sediment needs to be removed from the concrete trickle channels in both detention ponds. 5. Spill clean up material were needing to be applied with fuel spills were noted at the portable fuel tank.

Conditions

There are no conditions for this engineering permit application, or you are not authorized to view them.

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images

Date Uploaded File Type Name
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT0.PDF
Report INSPECTION REPORT1.PDF
Report INSPECTION REPORT2.PDF
Report INSPECTION REPORT3.PDF
Report INSPECTION REPORT4.PDF
Report INSPECTION REPORT5.PDF
Report INSPECTION REPORT6.PDF
Report INSPECTION REPORT7.PDF
Permit PERMIT - DETAILED CONSTRUCTION STORMWATER.PDF
04/29/2024 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
05/06/2024 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
07/12/2024 IMG_0212
07/12/2024 IMG_0218
07/12/2024 IMG_0213
07/12/2024 IMG_0215
07/12/2024 IMG_0216
07/12/2024 IMG_0217
08/26/2024 IMG_0385
08/26/2024 IMG_0382
08/26/2024 IMG_0388
08/26/2024 IMG_0387
08/26/2024 IMG_0384
08/26/2024 IMG_0383
08/26/2024 IMG_0386
10/04/2024 IMG_0686
10/04/2024 IMG_0685
10/04/2024 IMG_0689
10/04/2024 IMG_0687
10/04/2024 IMG_0684
10/24/2024 NOV tracking
10/24/2024 NOV tracking 0
10/24/2024 NOV tracking 1
12/02/2024 Photograph Tracking 11/22/24
04/01/2025 IMG_0999
04/01/2025 IMG_0996
04/01/2025 IMG_1003
04/01/2025 IMG_0997
04/01/2025 IMG_0998
04/01/2025 IMG_1004
04/01/2025 IMG_1001
05/07/2025 IMG_1319
05/07/2025 IMG_1314
05/07/2025 IMG_1315
05/07/2025 IMG_1313
05/07/2025 IMG_1312
05/07/2025 IMG_1317
05/07/2025 IMG_1316
05/07/2025 IMG_1318
05/07/2025 IMG_1310
05/07/2025 IMG_1311
05/07/2025 IMG_1309
06/25/2025 IMG_1537
06/25/2025 IMG_1539
06/25/2025 IMG_1538
06/25/2025 IMG_1540
06/25/2025 IMG_1542
06/25/2025 IMG_1544
08/05/2025 IMG_1704
08/05/2025 IMG_1714
08/05/2025 IMG_1705
08/05/2025 IMG_1707
08/05/2025 IMG_1710
08/05/2025 IMG_1715
08/05/2025 IMG_1716
08/05/2025 IMG_1706
08/05/2025 IMG_1711
08/05/2025 IMG_1708
08/05/2025 IMG_1713
09/23/2025 IMG_1913
09/23/2025 IMG_1912
09/23/2025 IMG_1914
09/23/2025 IMG_1911
09/23/2025 IMG_1910
09/23/2025 IMG_1909
09/23/2025 IMG_1907
09/23/2025 IMG_1905
09/23/2025 IMG_1915
10/07/2025 IMG_2010
10/07/2025 IMG_2001
10/07/2025 IMG_2002
10/07/2025 IMG_2008
10/07/2025 IMG_2007
10/07/2025 IMG_2006
10/07/2025 IMG_2005
10/07/2025 IMG_2004
10/07/2025 IMG_1999
10/07/2025 IMG_2009
10/07/2025 IMG_2003
11/06/2025 IMG_2226
11/06/2025 IMG_2240
11/06/2025 IMG_2228
11/06/2025 IMG_2237
11/06/2025 IMG_2238
11/06/2025 IMG_2243
11/06/2025 IMG_2229
11/06/2025 IMG_2234
11/06/2025 IMG_2233
11/06/2025 IMG_2232
11/06/2025 IMG_2235
11/06/2025 IMG_2242
11/06/2025 IMG_2227
11/06/2025 IMG_2231
11/06/2025 IMG_2230
11/06/2025 IMG_2236
11/06/2025 IMG_2241
03/16/2026 IMG_2436
03/16/2026 IMG_2435
03/16/2026 IMG_2434
03/16/2026 IMG_2437
03/16/2026 IMG_2432
03/16/2026 IMG_2419
03/16/2026 IMG_2433
03/16/2026 IMG_2403
03/16/2026 IMG_2428
03/16/2026 IMG_2431
03/16/2026 IMG_2425
03/16/2026 IMG_2415
03/16/2026 IMG_2412
03/16/2026 IMG_2408
03/16/2026 IMG_2429
03/16/2026 IMG_2427
03/16/2026 IMG_2424
03/16/2026 IMG_2423
03/16/2026 IMG_2421
03/16/2026 IMG_2417
03/16/2026 IMG_2406
03/16/2026 IMG_2407
03/16/2026 IMG_2426
03/16/2026 IMG_2422
03/16/2026 IMG_2420
03/16/2026 IMG_2416
03/16/2026 IMG_2414
03/16/2026 IMG_2413
03/16/2026 IMG_2411
03/16/2026 IMG_2410
03/16/2026 IMG_2409
03/16/2026 IMG_2404
03/16/2026 IMG_2401
03/16/2026 IMG_2430
03/16/2026 IMG_2405
03/26/2026 IMG_2514
03/26/2026 IMG_2512
03/26/2026 IMG_2509
03/26/2026 IMG_2508
03/26/2026 IMG_2518
03/26/2026 IMG_2517
03/26/2026 IMG_2515
03/26/2026 IMG_2513
03/26/2026 IMG_2511
03/26/2026 IMG_2510
03/26/2026 IMG_2516

Contact Us

  1. 115 10th Street

  2. Steamboat Springs, CO 80487

  3. Phone:  970-879-2060

  4. Hours

  5. Mon-Thurs: 7:30am-5:30pm

  6. Friday: 7:30am-11:30am

Government Websites by CivicPlus®