Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
COO Review - Engineering | Approved | 08/02/2023 | 07/31/2023 |
Emrick Soltis, P.E., CFM
|
|||
COO Review - Building Code | Approved | 07/26/2023 | 07/26/2023 |
Heidi Spengler
|
|||
All building complete. | |||
COO Review - Fire Code | Approved | 02/28/2023 | 02/21/2023 |
Shannon Yaconiello
|
|||
CC Approved - SY | |||
COO Review - Fire Code | TCO Approved | 12/13/2022 | 12/07/2022 |
Doug Shaffer
|
|||
COO Review - Planning | Approved | 12/13/2022 | 12/06/2022 |
Bob Keenan, AICP
|
|||
COO Review - Building Code | TCO Approved | 12/13/2022 | 12/06/2022 |
Heidi Spengler
|
|||
TCO approved for the building department. | |||
COO Review - Building Code | Failed | 11/22/2022 | 11/28/2022 |
Heidi Spengler
|
|||
TCO not approved please see inspection report. | |||
COO Review - Finance Department | TCO Approved | 11/22/2022 | 11/16/2022 |
Amy Camilletti
|
|||
5/31/23 City Finance approves a TCO extension to 4/30/23 [Amy Camilletti @ 02/21/2023 9:59 AM] The City of Steamboat Springs Finance department has approved a TEMPORARY CERTIFICATE (TCO/TCC) on this project. A construction use tax reconciliation is required within 90 days to be compliant with the City of Steamboat Springs Municipal Code AND before signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department. This information is sent to the email listed in City View. Please forward this information to the appropriate person to get this completed timely. | |||
COO Review - Fire Code | TCO Approved | 11/18/2022 | 11/10/2022 |
Shannon Yaconiello
|
|||
TCO Approved for the Basement Level only - SY 11/10/22 | |||
Building Code Review | Approved | 08/15/2022 | 08/15/2022 |
Todd Carr
|
|||
Addendum 8.5.22 approved. | |||
Building Code Review | Approved | 08/11/2022 | 08/05/2022 |
Todd Carr
|
|||
Addendum: Revised MEP drawings based on field demolition work. Scope of M&P revisions includes changes to floor drains and plumbing work at basement and revisions to the HVAC units and ducting on all levels. Electrical Revisions include updated panels, power plans and lighting. MEP's have been reviewed and approved. | |||
Planning Review | Approved | 05/27/2022 | 05/31/2022 |
Bob Keenan, AICP
|
|||
Miscellaneous
Outstanding
05/26/2022
Cannot approve until applicant receives approval of a Development Plan. Applicant to provide approved color modifications as made through DP proccess.
|
|||
Planning Review | Failed | 05/24/2022 | 05/25/2022 |
Bob Keenan, AICP
|
|||
Miscellaneous
Carried Forward
05/26/2022
Cannot approve until applicant receives approval of a Development Plan. Applicant to provide approved color modifications as made through DP proccess.
|
|||
Building Code Review | Approved | 05/24/2022 | 05/24/2022 |
Todd Carr
|
|||
Miscellaneous
Resolved
05/24/2022
Review started, however AOR has called this a TYPE II B building, however permits SB-01-620 and S-97-229 call this a Type III construction under the UBC, today this is a Type IIIB under the I-Codes
|
|||
Resubmittal provided, Architect has corrected type of construction and worked with the structural engineer to identify one load bearing exterior wall, per Type IIIB construction this wall is now a 2-hour UL listed assembly on the plans, permit approved. | |||
Construction Site Management Review | Approved | 05/24/2022 | 05/23/2022 |
Scott Slamal
|
|||
Fire Code Review | Approved | 05/24/2022 | 05/20/2022 |
Mike Middleton
|
|||
Conditionally approved- Any fire alarm / sprinkler work requires plans and a permit to be submitted to Fire Prevention. Visit www.steamboatsprings.net | |||
Building Code Review | Failed | 05/24/2022 | 05/19/2022 |
Todd Carr
|
|||
Miscellaneous
Carried Forward
05/24/2022
Review started, however AOR has called this a TYPE II B building, however permits SB-01-620 and S-97-229 call this a Type III construction under the UBC, today this is a Type IIIB under the I-Codes
|
|||
Review started, however AOR has called this a TYPE II B building, however permits SB-01-620 and S-97-229 call this a Type III construction under the UBC, today this is a Type IIIB under the I-Codes | |||
Finance Department Review | Approved | 05/24/2022 | 05/17/2022 |
Amy Camilletti
|
|||
City of Steamboat Springs Finance has approved City permit fees and taxes on this building permit. This is the City's portion, payable to the City of Steamboat Springs and submitted via the Routt County Regional Building Department or City View online portal. At the end of the project, the City of Steamboat Springs Finance requires a construction use tax reconciliation to be completed to be compliant with the City of Steamboat Springs Municipal Code AND before signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department. | |||
Utilities Review - Mt. Werner | Approved | 05/24/2022 | 05/11/2022 |
Richard Buccino
|
|||
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Framing Inspection | Not Ready | 8/10/2022 | 8/11/2022 | 08/11/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 8/15/2022 (Morning) | 8/15/2022 | 08/15/2022 |
Ron Norton | ||||
Insulation Inspection | Partial Pass | 8/23/2022 | 8/24/2022 | 08/24/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 8/23/2022 | 8/24/2022 | 08/24/2022 |
Ron Norton | ||||
Insulation Inspection | Partial Pass | 8/31/2022 (11:00 to 12:00) | 9/1/2022 | 09/01/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 8/31/2022 | 9/1/2022 | 09/01/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 9/22/2022 | 09/22/2022 | |
Ron Norton | ||||
Insulation Inspection | Partial Pass | 9/28/2022 | 9/29/2022 | 09/29/2022 |
Ron Norton | ||||
Framing Inspection | Partial Pass | 9/28/2022 | 9/29/2022 | 09/29/2022 |
Ron Norton | ||||
Insulation Inspection | Failed | 10/6/2022 | 10/06/2022 | |
Todd Carr | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
10/06/2022
Building Department Corrections to be Completed:
Insulation must be cut properly around all boxes in the wall, currently insulation is not installed behind boxes, nor cut around them, it's shoved in tight and compressed as well, please thin insulation and cut it to fit properly around all boxes. Also you must fill all cavities or gaps between old studs as well.
|
||||
Framing Inspection | Partial Pass | 10/6/2022 | 10/06/2022 | |
Todd Carr | ||||
Insulation Inspection | Partial Pass | 10/11/2022 | 10/12/2022 | 10/12/2022 |
Ron Norton | ||||
Corrections:
Building Department Corrections to be Completed
Carried Forward
10/12/2022
Building Department Corrections to be Completed:
Insulation must be cut properly around all boxes in the wall, currently insulation is not installed behind boxes, nor cut around them, it's shoved in tight and compressed as well, please thin insulation and cut it to fit properly around all boxes. Also you must fill all cavities or gaps between old studs as well.
|
||||
Framing Inspection | Passed | 11/10/2022 | 11/14/2022 | 10/12/2022 |
Ron Norton | ||||
Drywall Inspection | Partial Pass | 10/11/2022 | 10/12/2022 | 10/12/2022 |
Ron Norton | ||||
Drywall Inspection | Partial Pass | 10/17/2022 | 10/18/2022 | 10/18/2022 |
Todd Carr | ||||
Insulation Inspection | Passed | 11/3/2022 | 11/4/2022 | 11/04/2022 |
Ron Norton | ||||
Corrections:
Building Department Corrections to be Completed
Outstanding
10/12/2022
Building Department Corrections to be Completed:
Insulation must be cut properly around all boxes in the wall, currently insulation is not installed behind boxes, nor cut around them, it's shoved in tight and compressed as well, please thin insulation and cut it to fit properly around all boxes. Also you must fill all cavities or gaps between old studs as well.
|
||||
Building Final Inspection | Failed | 11/14/2022 (Morning) | 11/15/2022 | 11/15/2022 |
Todd Carr | ||||
Building Final Inspection | Failed | 11/22/2022 | 11/22/2022 | 11/22/2022 |
Todd Carr | ||||
Building Final Inspection | Partial Pass | 12/6/2022 | 12/06/2022 | |
Ron Norton | ||||
Building Final Inspection | Passed | 7/18/2023 | 7/19/2023 | 07/19/2023 |
Todd Carr |
Condition | Status | Category |
---|---|---|
Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
Sales Tax Department
City Finance approves a TCO extension to 4/30/23 [Amy Camilletti @ 02/21/2023 9:59 AM] Use Tax ReconciliationThe City of Steamboat Springs Finance department has approved a TEMPORARY CERTIFICATE (TCO/TCC) on this project. A construction use tax reconciliation is required within 90 days to be compliant with the City of Steamboat Springs Municipal Code AND before signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department.
This information is sent to the email listed in City View. Please forward this information to the appropriate person to get this completed timely.
|
||
Miscellaneous Conditions | Resolved | Prior to Full Building Permit Issuance |
Fire Prevention
Final Permit - Any fire alarm / sprinkler work requires plans and a permit to be submitted to Fire Prevention. Visit www.steamboatsprings.net
|
||
Miscellaneous Conditions | Resolved | Prior to Issuance of TCO/CO/CC |
Fire Prevention
Fire needs to be involved with CC sign-off in case there is an alarm or sprinkler permit.
|
||
Building Department Conditions to be Completed | Resolved | Prior to Issuance of TCO/CO/CC |
Building Department
Building Department Conditions to be Completed: FRTW plywood to be installed in exterior load bearing 2-hour wall
|
||
MF/Com/I Planning CO Review | Resolved | Prior to Issuance of TCO/CO/CC |
Planning Department
At the time of project completion, request certificate of occupancy inspections from the Department of Planning and Community Development to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, landscaping and revegetation, outdoor lighting, parking and parking lot striping, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
|
||
Building Department Conditions to be Completed | Resolved | Prior to Issuance of TCO/CO/CC |
Building Department
Through review of the addendum submitted for MEP's, we need the Architect of Record or EOR to review penetrations shown possibly going through a Fire Wall to the adjacent parking structure on Sheet P.200 for the 2 1/2" Water Line, and the 1 1/2" CW Line from the mechanical room, then on Sheet M100 it shows 2 - 2 1/2" HWS lines going through this wall potentially as well. Please review and respond if these are truly penetrations through the wall in the basement, or under the slab, if they are wall penetration then review 2018 IBC Section 714 Penetrations, but specifically 714.4.1 Through Penetrations. Upon review provide me back a response by either stating which exception you meet under 714.4.1 or provide me back the Fire Assembly that will be installed in necessary, prior to calling for inspections.
|
||
Special Inspections Deffered Submittal | Resolved | Prior to Final Building Inspection |
Building Department
Special Inspection Reports shall be submitted immediately upon conclusion of the special inspections regardless if it passed or failed and prior to any work being done beyond this point if it failed.
|
||
Building Department Conditions to be Completed | Resolved | Prior to Issuance of CO/CC |
Building Department
Building Department Conditions to be Completed:
1-Complete RTU
|
||
Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
Fire Prevention
12/21/2022
Miscellaneous Conditions, must have one speaker strobe that is not lighting on second level and one strobe not lighting on second level replaced prior to CO.
|
Reference Number | Status | Type |
---|---|---|
SPRPL220977 | Closed | Plumbing |
SPREL221026 | Closed | Electrical |
SPRMH221444 | Closed | Mechanical |