Go to Site Search

City of Steamboat Springs Web Portal

Planning Application Status

PL20220235


You will only be able to view fees if you are a contact on the planning application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PL20220235
Copper Ridge Business Park, Lot 3, Filling 4, Work/Live development
Development Plan
Development Plan - Administrative
File Closed
06/29/2022
RICHEY CONSTRUCTION INC
Administrative Development Plan application for two work/live units and associated site development.

Locations

Application Types

Development Plan - Administrative

Administrative
File Closed

Hearings

There are no hearings for this planning application.

Inspections

There are no inspections for this planning application, or you are not authorized to view them.

Conditions

Condition Status Category
Site Posting Affidavit Resolved Prior to Final Review
Planning Department
Property Posting (the sign) is required within seven days of a complete application being accepted by the Planning Department.
Mailing Affidavit Resolved Prior to Final Review
Planning Department
Submit a signed affidavit no later than eight days prior to the required public hearing or final decision date confirming the required mailed notice has been completed in accordance with Section 703.C.2.
AO Proximity Disclosure - BP Resolved Prior to Issuance of Construction Permit
Planning Department
Prior to Building Permit issuance, the property owner shall record an airport proximity disclosure.
Miscellaneous Condition Resolved Prior to Final Review
Planning Department
See informational comments from the Planning Department in Documents and Images.
Development Agreement Resolved Prior to Approval of Civil Construction Plans or Overlot Grading Plans
Planning Department
The owner shall enter into and record a Development Agreement regarding allowed uses and required parking. The agreement shall be recorded prior to Civil Construction Plan approval.
AO Avigation Easement - BP Resolved Prior to Issuance of Construction Permit
Planning Department
Prior to Building Permit issuance, the property owner shall record an avigation easement.
Critical Improvements (List) Resolved Prior to Issuance of Certificate of Occupancy/Completion
Planning Department
The following items are considered critical improvements and must be constructed and approved or accepted prior to issuance of a Certificate of Occupancy/Completion or approval of a Condo/Townhome Final Plat, whichever occurs first: • Water and Sewer infrastructure • Access drive, driveway, and parking areas • Drainage improvements • Permanent storm water quality treatment facilities • Revegetation (sidewalk removed- fee in lieu paid) [Toby Stauffer @ 07/11/2024 10:44 AM]
Miscellaneous Condition Resolved Prior to Issuance of Construction Permit
Planning Department
The owner shall pay $22,392.80 as a fee-in-lieu payment for the required sidewalk along Copper Ridge Circle. Payment of $22,392.80 shall be submitted to the City prior to issuance of any Building Permit.
Civils Required at BP Resolved Prior to Issuance of Construction Permit
Engineering
Civil construction plans prepared/signed/sealed by a licensed Colorado Professional Engineer are required to be submitted to the RCRBD with a Building Permit/Grading Permit application for review and approval prior to the start of any construction.
Executed Easements Prior to BP/GF Resolved Prior to Issuance of Construction Permit
Engineering
The owner shall provide the following recorded easements prior to issuance of a construction permit (Grade and Fill, Building):• Drainage and access easement from Public Street related to the storm water quality treatment facility.
Final Drainage Study prior to BP Resolved Prior to Issuance of Construction Permit
Engineering
Prior to any construction permit issuance, the final signed and sealed drainage study shall be submitted.
Completion Letter (Private Improv.) Resolved Prior to Engineering Final Approval Inspection
Engineering
Prior to Engineering Final Approval Inspection, a Completion Letter signed and sealed by a Colorado Professional Engineer (Project Engineer) shall be uploaded to the applicable building permit condition.
Record Drawings/CAD Files Resolved Prior to Issuance of CO/CC
Engineering
Record Drawings/CAD Files including drainage, PWQTF(s), and sidewalks shall be submitted prior to CO.

Related Permit & Planning Applications

There are no related items for this planning application.

Documents & Images

Date Uploaded File Type Name
Letter ADMINISTRATIVE APPROVAL LETTER.PDF
Letter NOTICE OF COMPLETE APPLICATION.PDF
Letter NOTICE OF FINAL DECISION.PDF
Letter NOTICE OF INCOMPLETE APPLICATION.PDF
Letter SURROUNDING PROPERTY OWNER NOTIFICATION.PDF
06/29/2022 Form FIRE FLOW REQUIREMENT WORKSHEET - 6_28_22 (1)
06/29/2022 Other Lot 4 Copper Ridge Business Park Checklist use
07/07/2022 Other Lot 4 CR Checklist Signed by Owner
07/07/2022 Receipt Receipt for transaction:2022-000972
07/07/2022 PL20220235.SPOList
07/28/2022 DRTMemo_PlanningInformationalComments.1716CRSpur
07/28/2022 Letter DRT Review Comments (Generate/Send DRT Review Comments Notice)
07/28/2022 Letter Property Record Card - R8167846 (Received)
07/28/2022 Study Web Soil Survey (Received)
07/28/2022 Study Preconsultation Approval Letter - Traffic (Not Required)
07/28/2022 Narrative 1647-007 FIRE Lot 3 Copper Ridge Work Live (Received)
07/28/2022 Study FIRMETTE_f5d053c9-bcc8-45b9-83cf-7361109de8a4 (Received)
08/29/2022 FPSE DRT Response August 2022 DP
09/21/2022 Letter DRT Review Comments (Generate/Send DRT Review Comments Notice)
09/21/2022 Narrative 1647-007 Lot 3 Copper Ridge Narrative DP0 (Received)
09/21/2022 Letter 1647-007 Engineers Cost Estimate_SIDEWALK - Fee In Lieu (Received)
10/03/2022 1647-007 Engineers Cost Estimate_SIDEWALK FEE IN LIEU
10/03/2022 FPSE DRT Response 10-3-2022 DP
10/04/2022 PL20220235DevelopmentAgreement_10.04.22
10/14/2022 Letter DRT Review Comments (Generate/Send DRT Review Comments Notice)
10/14/2022 Plans 1647-007 C1 Lot 3 Copper Ridge Work Live COV (Received)
10/14/2022 Plans 1647-007 C2 Lot 3 Copper Ridge Work Live EXC1 (Received)
10/14/2022 Plans 1647-007 C3 Lot 3 Copper Ridge Work Live SP3 (Received)
10/14/2022 Plans 1647-007 C4 Lot 3 Copper Ridge Work Live GD0 (Received)
10/14/2022 Plans 1647-007 C4 Lot 3 Copper Ridge Work Live GD (Received)
10/14/2022 Plans 1647-007 C3 Lot 3 Copper Ridge Work Live SP4 (Received)
10/14/2022 Plans 1647-007 C5 Lot 3 Copper Ridge Work Live LT0 (Received)
11/04/2022 Plans 21160 Richey Live Work REV1 STAMPED 10_18_22 (Received)
11/04/2022 Study 1647-007 Lot 3 Copper Ridge Live Work Drainage Letter w Attachments - Oct 2022 flat (Received)
11/14/2022 DevelopmentAgreementFinal
06/12/2023 Drainage Easement Lot 3 Copper Ridge
06/13/2023 ReceptionNumbers

Contact Us

  1. 115 10th Street

  2. Steamboat Springs, CO 80487

  3. Phone:  970-879-2060

  4. Hours

  5. Mon-Thurs: 7:30am-5:30pm

  6. Friday: 7:30am-11:30am

Government Websites by CivicPlus®