Planning Application Status
DPVC-21-16
You will only be able to view fees if you are a contact on the planning application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
Title | Location | Date | Time |
---|---|---|---|
Planning Commission, 2022-06-23, 05:00 PM | Citizens Meeting Room, Centennial Hall, 124 10th Street | 06/23/2022 | 5:00 PM |
Recommendation
Approved with Conditions
|
|||
City Council, 2022-07-05, 05:00 PM | Citizens Meeting Room, Centennial Hall, 124 10th Street | 07/05/2022 | 5:00 PM |
Resolution
Approved with Conditions
|
There are no inspections for this planning application, or you are not authorized to view them.
Condition | Status | Category |
---|---|---|
Site Posting Affidavit | Resolved | Prior to Final Review |
Planning Department
Property Posting (the sign) is required within seven days of a complete application being accepted by the Planning Department.
|
||
AO Proximity Disclosure - BP | Resolved | |
Planning Department
Prior to Building Permit issuance, the property owner shall record an airport proximity disclosure.
___
See DPVC-21-06 for doc
|
||
AO Avigation Easement - BP | Resolved | |
Planning Department
Prior to Building Permit issuance, the property owner shall record an avigation easement.
__
See DPVC-21-06 for doc
|
||
Traffic Contribution prior to BP | Resolved | Prior to Issuance of Construction Permit |
Engineering
Prior to Building Permit issuance, the developer shall pay their proportionate share of potential future roadway and/or intersection improvements at Downhill Drive at US 40 intersection, calculated at 0.62% of 8,333,132.02 or $51,665.42
___
Paid 7/20/23 Ck #128 $51,665.42
|
||
Miscellaneous Condition | Resolved | Prior to Issuance of Construction Permit |
Engineering
Civil construction plans prepared/signed/sealed by a licensed Colorado Professional Engineer are required to be submitted to the RCRBD with a Building Permit/ Grading Permit application for review and approval prior to the start of any construction.
|
||
Miscellaneous Condition | Resolved | Prior to Issuance of Construction Permit |
Engineering
Prior to approval of construction permit, owner shall receive approved CDOT access permit for intersection of Curve Court at US 40.
|
||
Critical Improvements (List) | Resolved | Prior to Issuance of Certificate of Occupancy/Completion |
Engineering
The following items are considered critical improvements and must be constructed and approved or accepted prior to issuance of a Certificate of Occupancy/Completion:
• Parking areas
• Driveways
• Road from Elk River Road to Curve Court
• Right in- Right out modifications to driveway onto Elk River Road
• Relocation of Transit Stop on Elk River Road
• Grading and drainage infrastructure
• Stormwater quality treatment facility
• Any US 40 improvements required by CDOT Access Permit
|
||
PWQ O&M prior to CO/CAC | Resolved | Prior to Issuance of CO/CC |
Engineering
Prior to Certificate of Occupancy/Completion, an Ownership and Maintenance Agreement for the Permanent Stormwater Quality Treatment Facility shall be recorded.
|
||
Record Drawings/CAD Files | Resolved | Prior to Permanent Stormwater Quality Treatment Facility Inspection |
Engineering
Record Drawings/CAD Files shall be submitted prior to Permanent Stormwater Quality Treatment Facility Inspection
|
||
Completion Letter (Private Improv.) | Resolved | Prior to Engineering Final Approval Inspection |
Engineering
Prior to Engineering Final Approval Inspection, a Completion Letter signed and sealed by a Colorado Professional Engineer (Project Engineer) shall be submitted.
|
||
Detention/Infiltration Pond State Registration | Resolved | Prior to Permanent Stormwater Quality Treatment Facility Inspection |
Engineering
Prior to Permanent Stormwater Quality Treatment Facility Inspection, documentation of state registration of detention or infilatration facility shall be submitted.
|
||
Miscellaneous Condition | Resolved | Prior to Issuance of Construction Permit |
Planning Department
A development agreement shall be recorded to document phasing prior to building permit approval.
__
Recorded at reception no. 846475.
|
||
Miscellaneous Condition | Open | Prior to Issuance of Construction Permit |
Planning Department
Prior to Building Permit issuance for Phase B, the mural on the commercial container will require approval through the Substantial Conformance process.
__
Changed from Phase A to Phase B per PL20230131
|
||
Mailing Affidavit | Resolved | |
Planning Department
Submit a signed affidavit no later than eight days prior to the required public hearing or final decision date confirming the required mailed notice has been completed in accordance with Section 703.C.2.
|
There are no related items for this planning application.