- Home
- City of Steamboat Springs Web Portal
City of Steamboat Springs Web Portal
Permit Application Status
TB-21-834
| Review Type | Outcome | Est. Completion Date | Completed |
|---|---|---|---|
| COO Review - Finance Department | Approved | 01/11/2024 | 01/04/2024 |
| COO Review - Building Code | Approved | 01/02/2024 | 12/22/2023 |
| COO Review - Building Code | TCO Approved | 10/25/2023 | 10/27/2023 |
| COO Review - Engineering (SF/DU) | TCO Approved | 10/13/2023 | 10/16/2023 |
| COO Review - Building Code | Failed | 10/13/2023 | 10/13/2023 |
| COO Review - Utilities - Mt. Werner | Approved | 10/13/2023 | 10/13/2023 |
| COO Review - GIS Land Development | Approved | 10/13/2023 | 10/13/2023 |
| COO Review - Planning | Failed | 10/13/2023 | 10/12/2023 |
| COO Review - Finance Department | TCO Approved | 10/13/2023 | 10/09/2023 |
| Building Code Review | Approved | 05/01/2023 | 04/25/2023 |
| Building Code Review | Approved | 11/15/2022 | 11/10/2022 |
| Utilities Review - Mt. Werner | Approved | 08/31/2021 | 09/23/2021 |
| Engineering Review | Approved | 08/24/2021 | |
| Building Code Review | Approved | 08/31/2021 | 08/24/2021 |
| Planning Review | Approved w/ Conditions | 08/04/2021 | |
| External Agencies Review | Approved w/ Conditions | 08/04/2021 | |
| External Agencies Review | Approved | 07/19/2021 | |
| Fire Code Review | Approved | 07/16/2021 | |
| GIS Land Development Review | Approved | 07/15/2021 | |
| Finance Department Review | Approved | 07/13/2021 |
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Footing Inspection | Passed | 1/11/2022 | 1/12/2022 | 01/13/2022 |
| Jeff Yeiser | ||||
| Foundation Inspection | Partial Pass | 2/4/2022 | 2/7/2022 | 02/07/2022 |
| Ron Norton | ||||
| Foundation Inspection | Partial Pass | 2/10/2022 | 2/11/2022 | 02/11/2022 |
| Ron Norton | ||||
| Foundation Inspection | Partial Pass | 3/25/2022 (Afternoon) | 3/28/2022 | 03/28/2022 |
| Ron Norton | ||||
| Foundation Drain Inspection | Partial Pass | 6/3/2022 | 6/3/2022 | 06/03/2022 |
| Ron Norton | ||||
| Foundation Drain Inspection | Partial Pass | 6/10/2022 | 6/10/2022 | 06/10/2022 |
| Ron Norton | ||||
| Foundation Drain Inspection | Partial Pass | 8/12/2022 | 8/12/2022 | 08/12/2022 |
| Ron Norton | ||||
| Framing Inspection | Partial Pass | 11/14/2022 | 11/14/2022 | 11/14/2022 |
| Ron Norton | ||||
| Foundation Drain Inspection | Passed | 11/14/2022 | 11/14/2022 | 11/14/2022 |
| Ron Norton | ||||
| Foundation Inspection | Passed | 11/14/2022 | 11/14/2022 | 11/14/2022 |
| Ron Norton | ||||
| Framing Inspection | Partial Pass | 1/25/2023 | 1/25/2023 | 01/25/2023 |
| Ron Norton | ||||
| Framing Inspection | Partial Pass | 1/26/2023 | 1/26/2023 | 01/26/2023 |
| Ron Norton | ||||
| Framing Inspection | Partial Pass | 4/13/2023 | 4/13/2023 | 04/13/2023 |
| Todd Carr | ||||
| Insulation Inspection | Failed | 4/18/2023 | 04/18/2023 | |
| Todd Carr | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
04/18/2023
We cannot approve the insulation until we receive an addendum that recognizes and shows the exact R-value of the core bond foam that has been installed on all exterior walls, include all wall types in the addendum, so basement concrete walls, stick framed walls over the concrete wall on the inside, and all stick framed walls above grade, please make sure draw up all wall assemblies that have changed so we have something to review in the office and in the field to approve the changes. The sauna room must be included as well, as this is 100% core bond for roof and walls, so include this in the addendum with listed R-values based on R-7 per inch of core bond. Call back for a reinspection after the addendum is reviewed and approved.
|
||||
| Rough Site Inspection | Failed | 04/18/2023 | ||
| Scott Slamal | ||||
|
Corrections:
Miscellaneous
Carried Forward
04/18/2023
Clean up all trash in front of property and in surrounding snow storage piles. Especially micro bits of insulation board.
|
||||
| Insulation Inspection | Passed | 4/26/2023 | 4/26/2023 | 04/26/2023 |
| Ron Norton | ||||
|
Corrections:
Building Department Corrections to be Completed
Outstanding
04/18/2023
We cannot approve the insulation until we receive an addendum that recognizes and shows the exact R-value of the core bond foam that has been installed on all exterior walls, include all wall types in the addendum, so basement concrete walls, stick framed walls over the concrete wall on the inside, and all stick framed walls above grade, please make sure draw up all wall assemblies that have changed so we have something to review in the office and in the field to approve the changes. The sauna room must be included as well, as this is 100% core bond for roof and walls, so include this in the addendum with listed R-values based on R-7 per inch of core bond. Call back for a reinspection after the addendum is reviewed and approved.
|
||||
| Drywall Inspection | Not Ready | 10/4/2023 | 10/4/2023 | 10/04/2023 |
| Jeff Yeiser | ||||
| Building Final Inspection | Failed | 10/6/2023 | 10/6/2023 | 10/06/2023 |
| Todd Carr | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
10/06/2023
Building Department Corrections:
1. The handrail going downstairs is a type II handrail, currenlty review the section below as it requires the grasable finger area to begin within 3/4" of the tallest portion of the handrail, in this case that is the top of the this rectangular handrail.
Type II. Handrails with a perimeter greater than 61/4 inches (160 mm) shall have a graspable finger recess area on both sides of the profile. The finger recess shall begin within 3/4 inch (19 mm) measured vertically from the tallest portion of the profile and have a depth of not less than 5/16 inch (8 mm) within 7/8 inch (22 mm) below the widest portion of the profile. This required depth shall continue for not less than 3/8 inch (10 mm) to a level that is not less than 13/4 inches (45 mm) below the tallest portion of the profile. The width of the handrail above the recess shall be not less than 11/4 inches (32 mm) and not more than 23/4 inches (70 mm). Edges shall have a radius of not less than 0.01 inch (0.25 mm).
2. The stairs going upstairs has two issues, the first flight of stairs are not 36" wide and they must be 36" wide. The stairs also have no handrail, so review the section for handrails and install a handrail that meets code.
3. The basement hallway at the bottom of the stairs does not meet code, we are supposed to maintain 36" wide in hallways, from the tread nosing to the bump out wall we are around 33".
4. Basement mechanical room: Please call back once boiler is running as it's primary heat.
5. Kitchen sink is not working.
6. Exposed foam in upstairs must be covered.
7. Finish all siding on exterior.
8. The smoke detectors in upstairs landing and bedroom do not meet code for proper location with respect to ceiling, they must be within 1 foot of top of ceiling when wall mounted.
|
||||
| Drywall Inspection | Violation Present | 10/06/2023 | ||
| Heidi Spengler | ||||
| Building Final Inspection | Partial Pass | 10/18/2023 | 10/18/2023 | 10/18/2023 |
| Ron Norton | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
10/18/2023
Building Department Corrections:
1. The handrail going downstairs is a type II handrail, currenlty review the section below as it requires the grasable finger area to begin within 3/4" of the tallest portion of the handrail, in this case that is the top of the this rectangular handrail.
Type II. Handrails with a perimeter greater than 61/4 inches (160 mm) shall have a graspable finger recess area on both sides of the profile. The finger recess shall begin within 3/4 inch (19 mm) measured vertically from the tallest portion of the profile and have a depth of not less than 5/16 inch (8 mm) within 7/8 inch (22 mm) below the widest portion of the profile. This required depth shall continue for not less than 3/8 inch (10 mm) to a level that is not less than 13/4 inches (45 mm) below the tallest portion of the profile. The width of the handrail above the recess shall be not less than 11/4 inches (32 mm) and not more than 23/4 inches (70 mm). Edges shall have a radius of not less than 0.01 inch (0.25 mm).
2. The stairs going upstairs has two issues, the first flight of stairs are not 36" wide and they must be 36" wide. The stairs also have no handrail, so review the section for handrails and install a handrail that meets code.
3. The basement hallway at the bottom of the stairs does not meet code, we are supposed to maintain 36" wide in hallways, from the tread nosing to the bump out wall we are around 33".
4. Basement mechanical room: Please call back once boiler is running as it's primary heat.
5. Kitchen sink is not working.
6. Exposed foam in upstairs must be covered.
7. Finish all siding on exterior.
8. The smoke detectors in upstairs landing and bedroom do not meet code for proper location with respect to ceiling, they must be within 1 foot of top of ceiling when wall mounted.
|
||||
| Final Site Inspection | Passed | 10/30/2023 | ||
| Greg Gunn | ||||
| Final Right of Way | Passed | 10/30/2023 | ||
| Greg Gunn | ||||
|
Corrections:
Miscellaneous
Carried Forward
10/17/2023
10/16/23: TCO approved. Prior to CO:
Site grading complete in compliance with approved plan.
Roadway shoulder restored with road base.
Roadside ditch restored and revegetated.
Disturbed areas revegetated - sod, seed and straw or landscaping complete.
|
||||
| Building Final Inspection | Passed | 12/22/2023 | 12/22/2023 | |
| Heidi Spengler | ||||
|
Corrections:
Building Department Corrections to be Completed
Resolved
12/22/2023
Building Department Corrections:
1. The handrail going downstairs is a type II handrail, currenlty review the section below as it requires the grasable finger area to begin within 3/4" of the tallest portion of the handrail, in this case that is the top of the this rectangular handrail.
Type II. Handrails with a perimeter greater than 61/4 inches (160 mm) shall have a graspable finger recess area on both sides of the profile. The finger recess shall begin within 3/4 inch (19 mm) measured vertically from the tallest portion of the profile and have a depth of not less than 5/16 inch (8 mm) within 7/8 inch (22 mm) below the widest portion of the profile. This required depth shall continue for not less than 3/8 inch (10 mm) to a level that is not less than 13/4 inches (45 mm) below the tallest portion of the profile. The width of the handrail above the recess shall be not less than 11/4 inches (32 mm) and not more than 23/4 inches (70 mm). Edges shall have a radius of not less than 0.01 inch (0.25 mm).
2. The stairs going upstairs has two issues, the first flight of stairs are not 36" wide and they must be 36" wide. The stairs also have no handrail, so review the section for handrails and install a handrail that meets code.
3. The basement hallway at the bottom of the stairs does not meet code, we are supposed to maintain 36" wide in hallways, from the tread nosing to the bump out wall we are around 33".
4. Basement mechanical room: Please call back once boiler is running as it's primary heat.
5. Kitchen sink is not working.
6. Exposed foam in upstairs must be covered.
7. Finish all siding on exterior.
8. The smoke detectors in upstairs landing and bedroom do not meet code for proper location with respect to ceiling, they must be within 1 foot of top of ceiling when wall mounted.
|
||||
| Condition | Status | Category |
|---|---|---|
| Blower Door Test Results | Resolved | Prior to Certificate of Occupancy/Completion |
|
Building Department
Blower Door Test Results
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
|
Finance
At the end of the project, City of Steamboat Springs Finance requires a construction use tax reconciliation be completed to be compliant with the City of Steamboat Springs Municipal Code AND prior to signoff for the FINAL certificate of occupancy/completion with the Routt County Building Department.
|
||
| Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
|
Sales Tax Department
Use Tax Reconciliation
|
||
| FLC Submittal | Resolved | Prior to Rough Site Inspection |
|
Planning Department
Foundation location certificate shall be provided
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
|
Engineering
10/16/23: TCO approved. Prior to CO:
Site grading complete in compliance with approved plan.
Roadway shoulder restored with road base.
Roadside ditch restored and revegetated.
Disturbed areas revegetated - sod, seed and straw or landscaping complete.
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Issuance of CO/CC |
|
Building Department
Building Department Conditions to be Completed
Need 1 additional receptacle is needed between kitchen sink and range for final.
|
||
| Reference Number | Status | Type |
|---|---|---|
| SPRMH221672 | Closed | Mechanical |
| SPRPL230298 | Closed | Plumbing |
| SPRMH230371 | Closed | Mechanical |
| SPREL231143 | Closed | Electrical |
Powered by CityView