Permit Application Status
SPRPO251164
| Date Returned | Name |
|---|---|
| POOL (STAMPED).PDF |
| Review Type | Outcome | Est. Completion Date | Completed |
|---|---|---|---|
| Building Code Review | Approved | 09/04/2025 | 08/28/2025 |
| Engineering Review | Approved | 08/15/2025 | 08/14/2025 |
| Building Code Review | Failed | 08/15/2025 | 08/14/2025 |
| GIS Land Development Review | Approved | 08/15/2025 | 08/13/2025 |
| Fire Code Review | Approved | 08/15/2025 | 08/12/2025 |
| Electrical Review | Approved | 08/15/2025 | 08/11/2025 |
| Planning Review | Approved | 08/15/2025 | 08/05/2025 |
| Finance Department Review | Approved | 08/15/2025 | 08/04/2025 |
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Plumbing Final Inspection | Pending | |||
| Foundation Water Proofing | Pending | |||
| Structural Inspection | Pending | |||
| Building Final Inspection | Pending | |||
| Framing Inspection | Pending | |||
| Footing Inspection | Pending | |||
| Plumbing Rough-in Inspection | Pending | |||
|
Corrections:
Building Department Corrections to be Completed
Outstanding
09/29/2025
Do Not Pour Concrete in Spas or Pool Foundation Walls until you have passed an inspection by Routt County, we will need to inspect all rebar, foam board, and proper clearances from rebar to forms, rebard to pool piping distances which is 1 1/2" and pool piping to form distances which we assume is also 1 1/2", and ensure rebar is proper size and spacing as well.
|
||||
| Foundation Inspection | Pending | |||
|
Corrections:
Building Department Corrections to be Completed
Outstanding
11/10/2025
Building Department Corrections to be Completed: Do Not Pour Concrete in Spas or Pool Foundation Walls until you have passed an inspection by Routt County, we will need to inspect all rebar, foam board, and proper clearances from rebar to forms, rebard to pool piping distances which is 1 1/2" and pool piping to form distances which we assume is also 1 1/2", and ensure rebar is proper size and spacing as well.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 9/19/2025 | 9/19/2025 | 09/19/2025 |
| Todd Carr | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
09/19/2025
Do Not Pour Concrete in Spas or Pool Foundation Walls until you have passed an inspection by Routt County, we will need to inspect all rebar, foam board, and proper clearances from rebar to forms, rebard to pool piping distances which is 1 1/2" and pool piping to form distances which we assume is also 1 1/2", and ensure rebar is proper size and spacing as well.
|
||||
| Foundation Inspection | Failed | 09/19/2025 | ||
| Todd Carr | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
09/19/2025
Building Department Corrections to be Completed: Do Not Pour Concrete in Spas or Pool Foundation Walls until you have passed an inspection by Routt County, we will need to inspect all rebar, foam board, and proper clearances from rebar to forms, rebard to pool piping distances which is 1 1/2" and pool piping to form distances which we assume is also 1 1/2", and ensure rebar is proper size and spacing as well.
|
||||
| Plumbing Rough-in Inspection | Not Ready | 9/19/2025 | 9/22/2025 | 09/22/2025 |
| Silas Ebbert | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
09/22/2025
Do Not Pour Concrete in Spas or Pool Foundation Walls until you have passed an inspection by Routt County, we will need to inspect all rebar, foam board, and proper clearances from rebar to forms, rebard to pool piping distances which is 1 1/2" and pool piping to form distances which we assume is also 1 1/2", and ensure rebar is proper size and spacing as well.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 9/26/2025 | 9/29/2025 | 09/29/2025 |
| Ron Norton | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
09/29/2025
Do Not Pour Concrete in Spas or Pool Foundation Walls until you have passed an inspection by Routt County, we will need to inspect all rebar, foam board, and proper clearances from rebar to forms, rebard to pool piping distances which is 1 1/2" and pool piping to form distances which we assume is also 1 1/2", and ensure rebar is proper size and spacing as well.
|
||||
| Foundation Inspection | Not Ready | 11/6/2025 | 11/10/2025 | 11/10/2025 |
| Todd Carr | ||||
|
Corrections:
Building Department Corrections to be Completed
Carried Forward
11/10/2025
Building Department Corrections to be Completed: Do Not Pour Concrete in Spas or Pool Foundation Walls until you have passed an inspection by Routt County, we will need to inspect all rebar, foam board, and proper clearances from rebar to forms, rebard to pool piping distances which is 1 1/2" and pool piping to form distances which we assume is also 1 1/2", and ensure rebar is proper size and spacing as well.
|
||||
| Condition | Status | Category |
|---|---|---|
| Miscellaneous Conditions | Open | Prior to Issuance of TCO/CO/CC |
|
Environmental Health Pool/Spa pre-operational inspection required. Assure all permits, including building, electrical, plumbing and mechanical, tied to the
swimming pool project have been finalized. Certified Pool Operator must be present during this inspection to verify chemical quality. All provisions of DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT Water Quality Control Division SWIMMING POOLS AND MINERAL BATHS 5 CCR 1003-5 must be met. Contact rmelzer@co.routt.co.us or call (970) 870-5588 to schedule.
|
||
| Use Tax Reconciliation | Open | Prior to Issuance of CO/CC |
|
Finance
Use Tax Recon work must be completed with City Finance: Contact the city directly for more information @ constructionusetax@steamboatsprings.net
|
||
| MF/Com/I Planning CO Review | Open | Prior to Issuance of TCO/CO/CC |
|
Planning Department
At the time an applicant requests a “Final Building Inspection”, prior to issuance of a Certificate of Occupancy/Completion, the Department of Planning and Community Development will contact the applicant to inspect the site to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, outdoor lighting, parking, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
|
||
| Reference Number | Status | Type |
|---|---|---|
| SPRNR240188 | Permit(s) Issued | New Commercial Building |
| SPREL240810 | Permit(s) Issued | Electrical |
| SPRPL241239 | Permit(s) Issued | Plumbing |
| SPRMH251500 | Permit(s) Issued | Mechanical |
| SPRPL251590 | Permit(s) Issued | Plumbing |
| SPRMH260105 | Permit(s) Issued | Mechanical |
| Date Uploaded | File Type | Name |
|---|---|---|
| 3 INCH FOAM.PDF | ||
| Plans | CENTRAL PARK HOTEL SUBMITTAL.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT0.PDF | |
| Report | INSPECTION REPORT1.PDF | |
| Permit | PERMIT - DETAILED.PDF | |
| PERMIT REVIEW CORRECTIONS NOTICE WITH ACTIONS.PDF | ||
| Letter | PERMIT REVIEW CORRECTIONS NOTICE.PDF | |
| POOL & SPA COVERS.PDF | ||
| Plans | POOL (STAMPED).PDF | |
| POOL0.PDF |