City of Steamboat Springs Web Portal

Engineering Permit Application Status

SPRSW231375


In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

SPRSW231375
Construction Stormwater
Permit(s) Issued
GRAY STONE, LLC
New
Holiday Inn Express, New construction of a 63,527 GSF 4-story, 90 unit hotel
09/25/2023
12/15/2023
06/12/2024

Locations

Property
307800001

Address
3300 S LINCOLN AVE

Permits

Permit Number: SPRSW231375-SW1

Construction Stormwater
Issued

Permit Number: SPRSW231375-LD1

Land Disturbance
Expired

Reviews

Review Type Outcome Est. Completion Date Completed
Construction Stormwater Review Approved 10/16/2023 11/15/2023
Construction Stormwater Review Failed 10/16/2023 11/07/2023
Construction Stormwater Review Failed 10/16/2023 10/24/2023
Construction Stormwater Review Failed 10/16/2023 10/11/2023

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Final Construction Stormwater Pending
Scott Slamal
Interim Construction Stormwater Pending
Scott Slamal
45 Day Inspection Pending 5/30/2025
Scott Slamal
Corrections:


Miscellaneous
Outstanding
04/16/2025
Trash and building particles were observed at various locations around the site identified during the inspection. Trash is required to be picked up throughout the site daily and disposed of properly.

Miscellaneous
Outstanding
04/16/2025
Installation of additional temporary stabilization was needed along the barren section of slope along the road on the east perimeter between the top of the road and the edge of the currently installed erosion control blanket. Temporary soil stabilization is required on all portions of the site where grading and land disturbing activities are complete and on any portion of the site that is inactive for at least 14 days

45 Day Inspection Failed 4/4/2024 04/04/2024
Scott Slamal
Interim Construction Stormwater Failed 4/5/2024 04/05/2024
Scott Slamal
Interim Construction Stormwater Failed 4/11/2024 04/11/2024
Scott Slamal
Interim Construction Stormwater Passed 4/12/2024 04/12/2024
Scott Slamal
45 Day Inspection Failed 4/25/2024 04/25/2024
Scott Slamal
Interim Construction Stormwater Passed 5/3/2024 05/03/2024
Scott Slamal
Interim Construction Stormwater Failed 5/20/2024 05/20/2024
Scott Slamal
Interim Construction Stormwater Failed 6/3/2024 06/03/2024
Scott Slamal
Interim Construction Stormwater Failed 6/4/2024 06/04/2024
Scott Slamal
Interim Construction Stormwater Passed 6/4/2024 06/07/2024
Scott Slamal
45 Day Inspection Failed 7/17/2024 07/17/2024
Scott Slamal
Corrections:


Trash
Carried Forward
07/18/2024
Trash must be picked up daily and disposed of correctly into trash receptacles.

Tracking
Carried Forward
07/18/2024
Vehicle tracking controls were not adequate. Proper measures must be implemented immediately to minimizing tracking.

45 Day Inspection Failed 8/26/2024 08/30/2024
Scott Slamal
Corrections:


Trash
Carried Forward
09/03/2024
Trash must be picked up daily and disposed of correctly into trash receptacles. Trash was noted floating in the ponding dewatering water and at other locations on the southeast corner of the project.

Tracking
Carried Forward
09/03/2024
Vehicle tracking controls were not adequate. Proper measures must be implemented immediately to minimizing tracking. Aggregate tracking pads for commercial, industrial, and multifamily sites, shall be constructed of three-inch to eight-inch angular aggregate.

45 Day Inspection Failed 12/8/2024 09/26/2024
Scott Slamal
Corrections:


Trash
Carried Forward
10/24/2024
Trash must be picked up daily and disposed of correctly into trash receptacles. Trash was noted floating in the ponding dewatering water and at other locations on the southeast corner of the project.

Tracking
Carried Forward
10/24/2024
Vehicle tracking controls were not adequate. Proper measures must be implemented immediately to minimizing tracking. Aggregate tracking pads for commercial, industrial, and multifamily sites, shall be constructed of three-inch to eight-inch angular aggregate.

45 Day Inspection Failed 1/24/2025 12/10/2024
Scott Slamal
45 Day Inspection Failed 5/31/2025 04/16/2025
Scott Slamal
Corrections:


Miscellaneous
Carried Forward
04/16/2025
Trash and building particles were observed at various locations around the site identified during the inspection. Trash is required to be picked up throughout the site daily and disposed of properly.

Miscellaneous
Carried Forward
04/16/2025
Installation of additional temporary stabilization was needed along the barren section of slope along the road on the east perimeter between the top of the road and the edge of the currently installed erosion control blanket. Temporary soil stabilization is required on all portions of the site where grading and land disturbing activities are complete and on any portion of the site that is inactive for at least 14 days

Conditions

There are no conditions for this engineering permit application, or you are not authorized to view them.

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images

Date Uploaded File Type Name
Letter INCOMPLETE APPLICATION NOTICE.PDF
Letter INCOMPLETE APPLICATION NOTICE.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Report INSPECTION REPORT.PDF
Permit PERMIT - DETAILED CONSTRUCTION STORMWATER.PDF
PERMIT - DETAILED CONSTRUCTION STORMWATER.PDF
10/24/2023 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
11/07/2023 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
08/30/2024 IMG_0451
08/30/2024 IMG_0467
08/30/2024 IMG_0453
08/30/2024 IMG_0468
08/30/2024 IMG_0465
08/30/2024 IMG_0464
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
12/10/2024 November 22, 2024
04/16/2025 IMG_1200
04/16/2025 IMG_1197
04/16/2025 IMG_1195
04/16/2025 IMG_1194
04/16/2025 IMG_1193
04/16/2025 IMG_1192
04/16/2025 IMG_1186
04/16/2025 IMG_1203
04/16/2025 IMG_1202
04/16/2025 IMG_1201
04/16/2025 IMG_1196
04/16/2025 IMG_1190
04/16/2025 IMG_1189
04/16/2025 IMG_1188
04/16/2025 IMG_1198
04/16/2025 IMG_1191
04/16/2025 IMG_1187
04/16/2025 IMG_1199