Permit Application Status
B-18-346
In order to view fees, you need to be signed in. You will only be able to schedule inspections if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
Planning Review | Approved w/ Conditions | 07/27/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Planning sysadmin - Jun 5 2018 3:33PM - The following conditions of approval will need to be met prior to Building Permit issuance: 1. Authorization from Army Corps of Engineers is required prior to construction permit being approved for any phase of work impacting the wetlands. 5. The applicant, Steamboat Springs Redevelopment Authority, (“SSRA”) shall enter into agreements with the Steamboat Grand Resort Hotel Condominium Association, Inc., (“Grand HOA”), Steamboat Ski & Resort Corporation, (“SSRC”), and Save Arnold Barn, (“SAB”)prior to building permit issuance in order to guarantee the following project goals are achieved: a. Public access dedications for sidewalks, trails, and site improvements. b. Long term maintenance for all interpretive signs and drainage swales. c. Long term maintenance for site improvements including the barn and/or provisions for removal and reclamation of the site. d. For the duration of the project on the site, public access to the barn, sidewalks, trails and site improvements. 7. Project lighting shall be installed with timing technology and the applicant, Steamboat Springs Redevelopment Authority, (“SSRA”) shall enter into a development agreement with the Steamboat Grand Resort Hotel Condominium Association, Inc., (“Grand HOA”), and Steamboat Ski & Resort Corporation, (“SSRC”) to allow for future modification of the lighting schedule. sysadmin - Jun 5 2018 3:33PM - Civil construction plan approval is required prior to approval of construction permit. sysadmin - Jul 24 2018 2:43PM - The addendum and permit can be issued for Phase 1 only after the relevant agreements for Phase 1 as listed in conditions 5 and 7 below have been signed. 5. The applicant, Steamboat Springs Redevelopment Authority, (“SSRA”) shall enter into agreements with the Steamboat Grand Resort Hotel Condominium Association, Inc., (“Grand HOA”), Steamboat Ski & Resort Corporation, (“SSRC”), and Save Arnold Barn, (“SAB”)prior to building permit issuance in order to guarantee the following project goals are achieved: a. Public access dedications for sidewalks, trails, and site improvements. b. Long term maintenance for all interpretive signs and drainage swales. c. Long term maintenance for site improvements including the barn and/or provisions for removal and reclamation of the site. d. For the duration of the project on the site, public access to the barn, sidewalks, trails and site improvements. 7. Project lighting shall be installed with timing technology and the applicant, Steamboat Springs Redevelopment Authority, (“SSRA”) shall enter into a development agreement with the Steamboat Grand Resort Hotel Condominium Association, Inc., (“Grand HOA”), and Steamboat Ski & Resort Corporation, (“SSRC”) to allow for future modification of the lighting schedule. sysadmin - Jul 27 2018 9:51AM - Phase 1 agreements signed, reception numbers provided. No BP for phase 2 shall be issued until additional agreements have been executed. this sign off for phase 1 only. | |||
Engineering Review | Approved | 07/20/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Engineering Dept | |||
External Agencies Review | Approved w/ Conditions | 07/06/2018 | |
SysAdmin
|
|||
VP legacy plan review: YVEA sysadmin - Jul 6 2018 2:30PM - Meter and meter panels are to be located as described by YVEA. They shall not be enclosed, covered or concealed. Violation shall result in termination of service. sysadmin - Jul 6 2018 2:30PM - This approval addresses only the meter and service location. | |||
External Agencies Review | Approved | 06/16/2018 | |
SysAdmin
|
|||
VP legacy plan review: Atmos Energy sysadmin - Jun 14 2018 8:21AM - 2# Systems will not be allowed unless proof of an appliance requiring a MINIMUM of over 7" W.C. is provided to Atmos Energy COrp for personnel review. Meter location must be approved by an Atoms Energy Corp employee during a mandatory site visit to be scheduled after foundation is in place. Meters will not be allowed under a shedding roofline or where overhanging snow is a danger to the meter set. sysadmin - Jun 16 2018 8:48AM - Building Permit Approved | |||
Legacy Permitting Review | Approved | 06/16/2018 | |
SysAdmin
|
|||
VP legacy plan review: Routt Building sysadmin - Jun 1 2018 9:18AM - Plan review process started sysadmin - Jun 16 2018 8:50AM - Permit Approved | |||
Interim Construction Site Management | Approved | 06/12/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Construction Site Management sysadmin - Jun 4 2018 7:58AM - Applicant needs to submit a CSMP for both the construction of the proposed barn site and the moving of the barn from existing location. Also, please confirm that the planned work is less than a acre for stormwater purposes. | |||
Fire Code Review | Approved | 06/10/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Fire Dept | |||
Finance Department Review | Approved | 06/04/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Finance Dept sysadmin - Jun 4 2018 1:08PM - City Finance has approved City tax & permit fees of $8,900.00 on your project. This is the City’s portion, payable to the City and submitted to the Routt County Regional Building Department. At the end of the project, City Finance requires a construction use tax reconciliation be completed prior to Finance’s final signoff. | |||
GIS Land Development Review | Approved | 06/01/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Address | |||
Legacy Permitting Review | Complete | 06/01/2018 | |
SysAdmin
|
|||
VP legacy plan review: Mt Werner Water District | |||
Utilities Review - City | Complete | 06/01/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Water & Sewer | |||
Historic Preservation Review | Approved | 06/01/2018 | |
SysAdmin
|
|||
VP legacy plan review: Steamboat Historical Review sysadmin - Jun 1 2018 9:39AM - HPC previously reviewed and approved. |
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Foundation Inspection | Complete | 09/25/2018 | ||
SysAdmin | ||||
Foundation Inspection | Complete | 11/16/2018 | ||
SysAdmin | ||||
Building Final Inspection | Complete | 08/26/2019 | ||
SysAdmin | ||||
Building Final Inspection | Complete | 08/29/2019 | ||
SysAdmin |
There are no conditions for this permit application, or you are not authorized to view them.
Reference Number | Status | Type |
---|---|---|
E-18-506 | Closed | Electrical |
P-19-192 | Closed | Plumbing |
Date Uploaded | File Type | Name |
---|---|---|
Legacy Permit Document | CE-15-022 | |
05/30/2018 | Legacy Permit Document | 2017.09.20 - NWCC Iconic Entry Arnold Barn S&FI Report.pdf |
05/30/2018 | Legacy Permit Document | CDs.Permit.052518.pdf |
05/30/2018 | Legacy Permit Document | Site Lighting Cut Sheets.052518.pdf |
05/31/2018 | Legacy Permit Document | Permit Application TB-18-346.msg |
06/11/2018 | Legacy Permit Document | 2018.06.11 - Arnold Barn CSMP.pdf |
06/19/2018 | Legacy Permit Document | TB-18-346 Plan Review Ltr.doc |
07/20/2018 | Legacy Permit Document | CO20169 BARN Haul Rd Civil Plan Update 7-3-18.pdf |
07/20/2018 | Legacy Permit Document | DPF-17-11_Iconic_Entry_Civil_&_Landscape_Const_Plans_6-7-18.pdf |
08/06/2018 | Legacy Permit Document | B-18-346 RECORD SET.pdf |
09/20/2018 | Legacy Permit Document | 17079_Helical Pile Inspection.pdf |
10/08/2018 | Legacy Permit Document | #1715 Arnold Barn - Tax Exempt Cert - Vendors.pdf |
11/13/2019 | Legacy Permit Document | B-18-346 Arnold Barn CA.pdf |