| Review Type | Outcome | Est. Completion Date | Completed |
|---|---|---|---|
| Utilities Review - Mt. Werner | Approved | 10/11/2024 | 10/07/2024 |
| Planning Review | Approved | 10/02/2024 | 10/02/2024 |
| Utilities Review - Mt. Werner | Failed | 10/02/2024 | 10/02/2024 |
| Building Code Review | Approved | 10/02/2024 | 09/30/2024 |
| Fire Code Review | Approved | 08/20/2024 | 08/22/2024 |
| Planning Review | Failed | 08/20/2024 | 08/20/2024 |
| Utilities Review - Mt. Werner | Failed | 08/20/2024 | 08/20/2024 |
| Building Code Review | Failed | 08/20/2024 | 08/15/2024 |
| GIS Land Development Review | Approved | 08/20/2024 | 08/14/2024 |
| Finance Department Review | Approved | 08/20/2024 | 08/13/2024 |
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Footing Inspection | Pending | |||
| Framing Inspection | Pending | |||
| Insulation Inspection | Pending | |||
| Drywall Inspection | Pending | |||
| Building Final Inspection | Pending | |||
| Structural Inspection | Pending | |||
| Wall/Roof Sheeting | Pending | |||
| Condition | Status | Category |
|---|---|---|
| Use Tax Reconciliation | Open | Prior to Issuance of CO/CC |
|
Finance
Use Tax Reconciliation
|
||
| Fire Assemblies Deferred Submittal | Open | Prior to Rough Building Wall Inspections |
|
Fire Prevention
Conditionally Approved – NO INSPECTIONS pending deferred submittal of hood suppression system plans/permit by sub-contractor to Fire Prevention. See www.steamboatsprings.net [Matt Workman @ 08/22/2024 4:56 PM]
|
||
| Fire Assemblies Deferred Submittal | Open | Prior to Rough Building Wall Inspections |
|
Fire Prevention
Conditionally Approved – NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms [Matt Workman @ 08/22/2024 4:57 PM]
|
||
| Final Fire Inspection Required | Open | Prior to Issuance of TCO/CO/CC |
|
Fire Prevention
Final Fire Alarm, Sprinkler & Hood Inspections Required. [Shannon Yaconiello @ 08/22/2024 4:58 PM]
|
||
| Miscellaneous Conditions | Open | Prior to Issuance of TCO/CO/CC |
|
Building Department
Routt County Environmental Health Retail Food pre-operational inspection required. All equipment must be operational and required supplies must be on-site. Contact rmelzer@co.routt.co.us or call (970) 870-5588 to schedule.
|
||
| Building Department Conditions to be Completed | Resolved | Prior to Full Building Permit Issuance |
|
Building Department
Applicant must Pay PIF Fees to Mt Werner Water and Sanitation Prior to Permit Issuance.
MWW fees have been paid in full - [bcahill @ 10/17/2024 1:10 PM]
|
||
| Reference Number | Status | Type |
|---|---|---|
| SPRPL241751 | Permit(s) Issued | Plumbing |