SPRAB210782
| Date Returned | Name |
|---|---|
| 06/15/2023 | 2643 Copper Ridge Circle Architectural REV 1 (Stamped) |
| 02/03/2022 | Note to 2643 Copper Ridge Circle Soils report (Received) (Stamped) |
| 02/03/2022 | 2643_CopperRidge Circle Site Plan1 (Received) (Stamped) |
| Review Type | Outcome | Est. Completion Date | Completed |
|---|---|---|---|
| COO Review - Planning | Approved | 06/10/2025 | 06/03/2025 |
| COO Review - Building Code | Approved | 12/08/2023 | 12/01/2023 |
| Building Code Review | Approved | 06/19/2023 | 06/15/2023 |
| COO Review - Building Code | Failed | 10/06/2022 | 10/07/2022 |
| COO Review - Planning | TCO Approved | 10/06/2022 | 10/03/2022 |
| Building Code Review | Approved | 01/31/2022 | 01/26/2022 |
| Planning Review | Approved | 01/31/2022 | 01/26/2022 |
| Fire Code Review | Approved | 01/31/2022 | 01/25/2022 |
| Electrical Review | Approved | 01/31/2022 | 01/24/2022 |
| Finance Department Review | Approved | 01/31/2022 | 01/24/2022 |
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Building Final Inspection | Failed | 9/29/2022 | 9/29/2022 | 09/29/2022 |
| Silas Ebbert | ||||
| Building Final Inspection | Passed | 12/1/2023 | 12/1/2023 | 12/01/2023 |
| Silas Ebbert | ||||
| Condition | Status | Category |
|---|---|---|
| Use Tax Reconciliation | Resolved | Prior to Issuance of CO/CC |
|
Finance
Use Tax Reconciliation - The City of Steamboat Springs Finance Department has approved sign-off on the Certificate of Completion for this project. A construction use tax reconciliation is not required. Thank you for your time and cooperation! Please let me know if you have questions. Have a wonderful day!
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
|
Planning Department
At the time of project completion, request certificate of occupancy inspections from the Department of Planning and Community Development to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, landscaping and revegetation, outdoor lighting, parking and parking lot striping, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
|
||
| Miscellaneous Conditions | Resolved | Prior to Issuance of CO/CC |
|
Planning Department
Two trees and fence required to be installed so site is consistent with approved plans prior to full CO/CC.
|
||
| Reference Number | Status | Type |
|---|---|---|
| SPRAB210713 | Closed | Accessory Building |
| SPREL210745 | Closed | Electrical |
| Date Uploaded | File Type | Name |
|---|---|---|
| Letter | 30-DAY ADVANCE NOTICE OF PERMIT EXPIRATION.PDF | |
| Letter | CERTIFICATE OF COMPLETION.PDF | |
| Letter | INCOMPLETE APPLICATION NOTICE.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Letter | PERMIT - DETAILED.PDF | |
| 12/18/2021 | Receipt | Receipt for transaction:2021-000624 |
| 01/21/2022 | APPROVAL | |
| 02/03/2022 | Plans | 2643 Copper Ridge Circle engineering (Received) |
| 02/03/2022 | Study | Note to 2643 Copper Ridge Circle Soils report (Received) (Stamped) |
| 02/03/2022 | Plans | 2643_CopperRidge Circle Site Plan1 (Received) (Stamped) |
| 02/03/2022 | Receipt | Receipt for transaction:2022-000113 |
| 02/07/2022 | 4109929_17_BOP_Acord25_3 | |
| 06/15/2023 | Plans | 2643 Copper Ridge Circle Architectural REV 1 (Stamped) |