- Home
- City of Steamboat Springs Web Portal
SPRSW240543
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
Construction Stormwater Review | Approved | 06/10/2024 | 06/14/2024 |
Scott Slamal
|
|||
Miscellaneous
Outstanding
06/05/2024
The following is either missing, deficient from the SWMP or not compliant with Engineering Standards Chapter 8 SWMP requirements:
SWMP description references Phase 1 to include Building 7, and internal roads, however, this is not reflected in the schedule on page 5. Revise project description and phasing schedule.
Phasing plan does not appear to accurately depict the area of disturbances per phase, including slopes below Building 7. Please confirm that grading this slope will not occur.
Section 1.5 Page 6: States, "some" off site work with appropriate controls is planned on the Ski Inn and Ski Trails Properties, as shown on the civil and landscaping drawings. Define "some" and identify where this work will occur.
Identify temporary sediment basins A and C on site map.
Reference civils identifying sediment basin volume, size, dimensions, soil stabilization method, outfall structure and discharge location.
Note that ERBs shall be used on all slopes steeper the 3H:1V.
Note if FODs are not used then aggregate tracking pads shall meet city Engineering Chapter 8 standards.
Describe how Gondola Lane will be stabilized before November 1.
Note in schedule when landscaping will be completed at building 7.
|
|||
Construction Stormwater Review | Failed | 06/10/2024 | 05/24/2024 |
Scott Slamal
|
|||
Miscellaneous
Carried Forward
06/05/2024
The following is either missing, deficient from the SWMP or not compliant with Engineering Standards Chapter 8 SWMP requirements:
SWMP description references Phase 1 to include Building 7, and internal roads, however, this is not reflected in the schedule on page 5. Revise project description and phasing schedule.
Phasing plan does not appear to accurately depict the area of disturbances per phase, including slopes below Building 7. Please confirm that grading this slope will not occur.
Section 1.5 Page 6: States, "some" off site work with appropriate controls is planned on the Ski Inn and Ski Trails Properties, as shown on the civil and landscaping drawings. Define "some" and identify where this work will occur.
Identify temporary sediment basins A and C on site map.
Reference civils identifying sediment basin volume, size, dimensions, soil stabilization method, outfall structure and discharge location.
Note that ERBs shall be used on all slopes steeper the 3H:1V.
Note if FODs are not used then aggregate tracking pads shall meet city Engineering Chapter 8 standards.
Describe how Gondola Lane will be stabilized before November 1.
Note in schedule when landscaping will be completed at building 7.
|
|||
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Interim Construction Stormwater | Pending | |||
Scott Slamal | ||||
Final Construction Stormwater | Pending | |||
Scott Slamal |
There are no conditions for this engineering permit application, or you are not authorized to view them.
There are no related items for this engineering permit application.
Date Uploaded | File Type | Name |
---|---|---|
Permit | PERMIT - DETAILED CONSTRUCTION STORMWATER.PDF | |
05/17/2024 | Plans | SWMP Plans |
05/17/2024 | Plans | SWMP Plans |
05/17/2024 | Plans | SWMP Control Measure Specifications |
05/24/2024 | Letter | Permit Review Corrections Notice (Generate/Send Correction Notice) |
05/24/2024 | Plans | SWMP Control Measure Details (Received) |