Review Type | Outcome | Est. Completion Date | Completed |
---|---|---|---|
Construction Site Management Review | Approved | 06/05/2024 | 06/05/2024 |
Scott Slamal
|
|||
Miscellaneous
Outstanding
05/29/2024
Provide a CSMP plan for this phase of the overall project.
|
|||
Planning Review | Failed | 06/05/2024 | 06/04/2024 |
Kelly Douglas, AICP
|
|||
Miscellaneous
Resolved
06/04/2024
A Development Plan planning application is required. Please reach out to the Planning Department for assistance with the planning application: 970-871-8259.
|
|||
Miscellaneous
Outstanding
06/04/2024
PL20220662 has open conditions that require resolution prior to approval of a construction permit. Please see conditions in portal here: https://cityview.steamboatsprings.net/Portal/Planning/Status?planningId=7656
|
|||
Wall and landscaping consistent with PL20220662 plan set. [Kelly Douglas @ 06/04/2024 10:21 AM] | |||
Engineering Review | Approved | 05/16/2024 | 05/17/2024 |
Emrick Soltis, P.E., CFM
|
|||
Planning Review | Failed | 05/16/2024 | 05/16/2024 |
Darby Kenyon
|
|||
Miscellaneous
Carried Forward
05/29/2024
A Development Plan planning application is required. Please reach out to the Planning Department for assistance with the planning application: 970-871-8259.
|
|||
Construction Site Management Review | Failed | 05/16/2024 | 05/16/2024 |
Scott Slamal
|
|||
Miscellaneous
Carried Forward
05/29/2024
Provide a CSMP plan for this phase of the overall project.
|
|||
Building Code Review | Approved | 05/16/2024 | 05/10/2024 |
Ted Allen
|
|||
Utilities Review - Mt. Werner | Approved | 05/16/2024 | 05/09/2024 |
Beau Cahill
|
|||
Fire Code Review | Approved | 05/16/2024 | 05/06/2024 |
Charles Brookshire
|
|||
Full Permit. NB | |||
Finance Department Review | Approved | 05/16/2024 | 05/02/2024 |
Sondra Spratta
|
|||
There are no inspections for this permit application, or you are not authorized to view them.
Condition | Status | Category |
---|---|---|
Use Tax Reconciliation | Open | Prior to Issuance of CO/CC |
Finance
Use Tax Reconciliation [sspratta @ 05/02/2024 11:22 AM]
|
||
Miscellaneous Conditions | Open | Prior to Final Building Inspection |
Building Department
THE SPECIAL INSPECTOR SHALL SUBMIT A FINAL SIGNED REPORT WITHIN 10 DAYS OF THE FINAL SPECIAL INSPECTION STATING WHETHER THE WORK REQUIRING SPECIAL INSPECTION WAS, TO THE BEST OF THE INSPECTOR'S KNOWLEDGE, IN CONFORMANCE WITH THE APPROVED CONSTRUCTION DOCUMENTS AND THE APPLICABLE WORKMANSHIP PROVISIONS OF THE IBC. WORK NOT IN COMPLIANCE SHALL BE NOTED IN THE REPORT AS PER STRUCTURAL GENERAL NOTES S001. [Ted Allen @ 05/10/2024 10:34 AM]
|
||
Vested Approval Conditions | Open | |
Planning Department
Compliance with PL20220662 conditions of approval required. Please see conditions in portal here: https://cityview.steamboatsprings.net/Portal/Planning/Status?planningId=7656