There are no reviews for this permit application, or you are not authorized to view them.
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Final Construction Stormwater | Pending | |||
Scott Slamal | ||||
90 Day Inspection | Pending | 5/2/2025 | ||
Scott Slamal | ||||
45 Day Inspection | Failed | 9/24/2021 | 09/24/2021 | |
Scott Slamal | ||||
45 Day Inspection | Passed | 9/20/2021 | 09/27/2021 | |
Scott Slamal | ||||
45 Day Inspection | Failed | 10/11/2021 | 10/11/2021 | |
Scott Slamal | ||||
45 Day Inspection | Failed | 10/13/2021 | 10/13/2021 | |
Scott Slamal | ||||
45 Day Inspection | Failed | 10/26/2021 | 10/26/2021 | |
Scott Slamal | ||||
45 Day Inspection | Failed | 11/4/2021 | 11/04/2021 | |
Scott Slamal | ||||
45 Day Inspection | Failed | 4/22/2022 | 04/22/2022 | |
Scott Slamal | ||||
Corrections:
Sediment Discharges
Carried Forward
04/26/2022
Install additional rocks socks to increase capacity and filtration at inlet across from old Preview Lift. Email photos of corrections once completed to Scott Slamal.
|
||||
45 Day Inspection | Failed | 5/3/2022 | 05/03/2022 | |
Scott Slamal | ||||
Corrections:
Sediment Discharges
Resolved
05/03/2022
|
||||
Inlet Protection
Carried Forward
05/03/2022
Install additional Dandy Bag inlet protection at the two inlets adjacent to the new gondola terminal.
|
||||
Sediment Discharges
Carried Forward
05/03/2022
Control measure implementation was inadequate to control sediment discharges to Burgess Creek.
|
||||
45 Day Inspection | Failed | 6/2/2022 | 06/02/2022 | |
Scott Slamal | ||||
Corrections:
Inlet Protection
Resolved
06/03/2022
Install additional Dandy Bag inlet protection at the two inlets adjacent to the new gondola terminal.
|
||||
Sediment Discharges
Resolved
06/03/2022
Control measure implementation was inadequate to control sediment discharges to Burgess Creek.
|
||||
Maintenance activities
Resolved
06/08/2022
Sediment accumulation at check dams along drainage swale at base area and at inlets needs to be removed to restore capacity at these locations. Email Scott Slamal photos once corrections are completed. Corrections made 6/3-6/7 see photo document showing corrections.
|
||||
45 Day Inspection | Passed | 7/12/2022 | 07/07/2022 | |
Scott Slamal | ||||
Corrections:
Maintenance activities
Resolved
07/08/2022
Sediment accumulation at check dams along drainage swale at base area and at inlets needs to be removed to restore capacity at these locations.
|
||||
45 Day Inspection | Passed | 8/18/2022 | 08/21/2022 | |
Scott Slamal | ||||
45 Day Inspection | Passed | 9/29/2022 | 08/31/2022 | |
Scott Slamal | ||||
45 Day Inspection | Failed | 11/19/2022 | 10/05/2022 | |
Scott Slamal | ||||
Corrections:
Inlet Protection
Carried Forward
10/05/2022
Install inlet protection at newly installed inlet at base of wild blue gondola terminal.
|
||||
45 Day Inspection | Failed | 12/19/2022 | 11/01/2022 | |
Scott Slamal | ||||
Corrections:
Inlet Protection
Carried Forward
11/04/2022
Install inlet protection at newly installed inlet at base of wild blue gondola terminal.
|
||||
Vehicle tracking
Carried Forward
11/04/2022
FODs tracking pad was in need of maintenance.
Sediment tracking was observed on Ski Time Square Dr.
|
||||
45 Day Inspection | Passed | 4/26/2023 | 05/04/2023 | |
Scott Slamal | ||||
Corrections:
Inlet Protection
Resolved
05/04/2023
Install inlet protection at newly installed inlet at base of wild blue gondola terminal.
|
||||
Vehicle tracking
Resolved
05/04/2023
FODs tracking pad was in need of maintenance.
Sediment tracking was observed on Ski Time Square Dr.
|
||||
45 Day Inspection | Passed | 6/18/2023 | 06/16/2023 | |
Scott Slamal | ||||
45 Day Inspection | Passed | 7/31/2023 | 07/27/2023 | |
Scott Slamal | ||||
45 Day Inspection | Passed | 9/10/2023 | 09/08/2023 | |
Scott Slamal | ||||
90 Day Inspection | Failed | 5/3/2024 | 05/15/2024 | |
Scott Slamal | ||||
Corrections:
Miscellaneous
Carried Forward
05/15/2024
The practice of cleaning out accumulated sediment from check dams along the Right of Way trail while runoff is occurring is causing sediment to discharge from the base area drainage to Burgess Creek. This practice needs to be re-evaluated and only occur when runoff is not occurring in the ditch. Please respond with a narrative outlining how this will be addressed in the future.
|
||||
90 Day Inspection | Partial Pass | 8/13/2024 | 08/14/2024 | |
Scott Slamal | ||||
Corrections:
Miscellaneous
Carried Forward
08/14/2024
The practice of cleaning out accumulated sediment from check dams along the Right of Way trail while runoff is occurring is causing sediment to discharge from the base area drainage to Burgess Creek. This practice needs to be re-evaluated and only occur when runoff is not occurring in the ditch. Please respond with a narrative outlining how this will be addressed in the future.
|
There are no conditions for this engineering permit application, or you are not authorized to view them.
There are no related items for this engineering permit application.