Permit Application Status
SPRMU250884
| Review Type | Outcome | Est. Completion Date | Completed |
|---|---|---|---|
| Fire Code Review | Approved | 04/01/2025 | 01/08/2026 |
| Utilities Review - Mt. Werner | Failed | 05/15/2025 | 05/15/2025 |
| Engineering Review | Approved | 05/15/2025 | 05/14/2025 |
| Construction Site Management Review | Approved | 05/15/2025 | 05/12/2025 |
| Building Code Review | Failed | 05/15/2025 | 05/12/2025 |
| Planning Review | Approved | 04/18/2025 | 04/24/2025 |
| Engineering Review | Failed | 04/18/2025 | 04/22/2025 |
| GIS Land Development Review | Approved | 04/18/2025 | 04/21/2025 |
| External Agencies Review | Approved | 04/18/2025 | 04/18/2025 |
| Construction Site Management Review | Failed | 04/18/2025 | 04/18/2025 |
| Utilities Review - Mt. Werner | Failed | 04/18/2025 | 04/18/2025 |
| Building Code Review | Failed | 04/18/2025 | 04/14/2025 |
| Electrical Review | Approved | 04/18/2025 | 04/14/2025 |
| Fire Code Review | Approved | 04/18/2025 | 04/10/2025 |
| Finance Department Review | Approved | 04/18/2025 | 04/01/2025 |
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Foundation/Under Slab Insulation | Pending | |||
| Footing Inspection | Pending | |||
| Water Service Inspection | Pending | |||
| Amber Gregory | ||||
| Sewer Service Inspection | Pending | |||
| Amber Gregory | ||||
| Interim Construction Site Management | Pending | |||
| Scott Slamal | ||||
| Roofing Inspection | Pending | |||
| Final Planning Department Site Improvement | Pending | |||
| Final Construction Site Management | Pending | |||
| Scott Slamal | ||||
| Building Final Inspection | Pending | |||
| Structural Inspection | Pending | |||
| Lath/Veneer Inspection | Pending | |||
| Radon Piping | Pending | |||
| Shower Pan | Pending | |||
| Foundation Inspection | Pending | |||
| Drywall Inspection | Pending | |||
| Framing Inspection | Pending | |||
| Wall/Roof Sheeting | Pending | |||
| Insulation Inspection | Pending | |||
| Foundation Inspection | Partial Pass | 07/29/2025 | ||
| Ron Norton | ||||
| Foundation Drain Inspection | Passed | 8/12/2025 | 8/12/2025 | 08/12/2025 |
| Jeff Yeiser | ||||
| Foundation Water Proofing | Passed | 8/12/2025 | 8/12/2025 | 08/12/2025 |
| Jeff Yeiser | ||||
| Drywall Inspection | Partial Pass | 2/12/2026 | 2/12/2026 | 02/12/2026 |
| Jeff Yeiser | ||||
| Framing Inspection | Partial Pass | 2/12/2026 | 2/12/2026 | 02/12/2026 |
| Jeff Yeiser | ||||
| Wall/Roof Sheeting | Partial Pass | 2/25/2026 | 2/26/2026 | 02/26/2026 |
| Silas Ebbert | ||||
| Wall/Roof Sheeting | Partial Pass | 3/17/2026 | 3/17/2026 | 03/17/2026 |
| Ron Norton | ||||
| Insulation Inspection | Partial Pass | 3/24/2026 | 3/25/2026 | 03/25/2026 |
| Ron Norton | ||||
| Condition | Status | Category |
|---|---|---|
| Building Department Conditions to be Completed | Resolved | Prior to Full Building Permit Issuance |
|
Building Department
Building Department will change the Application Type of this permit to Single Family Residence and create seven additional permits, one for each unit. [Malea Michael-Ferrier @ 03/26/2025 7:29 AM] See Todd Carr before making changes and creating new permits, to discuss civil plans on large projects like this.
|
||
| Blower Door Test Results | Open | Prior to Certificate of Occupancy/Completion |
|
Building Department
Blower Door Test Results [Todd Carr @ 03/27/2025 7:12 AM]
|
||
| Heat Loss Calculations Deferred Submittal | Open | Prior to Mechanical Permit Issuance for Heat |
|
Building Department
Heat Load Calculations must be submitted, Reviewed and approved prior to any heating equipment being installed. [Todd Carr @ 03/27/2025 7:13 AM]
|
||
| Use Tax Reconciliation | Open | Prior to Issuance of CO/CC |
|
Finance
Use Tax Reconciliation
|
||
| Miscellaneous Conditions | Resolved | Prior to Rough Building Wall Inspections |
|
Fire Prevention
1/6/26 Full Permit - Kevin Kopasz, GC emailed: As discussed, Terrain at Walton Creek consists of a 3-unit building, and a 5-unit building. All units are three story or less IRC single family town homes, which fall under the RCRBD code adoption not requiring Fire Sprinkler Systems and Monitored Fire Alarm Systems. We are not planning to install Fire Sprinkler Systems on this project, and we will be providing live voltage combo smoke/CO detectors within each unit. The design documents were originally submitted noting the units were to have Fire Sprinkler Systems installed, which the design team has since revised with recent resubmittals issued to RCRBD. [Mike Middleton @ 01/06/2026 4:41 PM]
Conditionally Approved –NO INSPECTIONS deferred submittal until RECEIPT of Fire Alarm/Sprinkler plan/permits by sub-contractor to Fire Prevention. See www.steamboatsprings.net/Fire and EMS Services/Fire Prevention/Downloadable Permits and Forms NB [Nick Brookshire @ 04/10/2025 3:27 PM]
|
||
| Final Fire Inspection Required | Resolved | Prior to Issuance of TCO/CO/CC |
|
Fire Prevention
Final Fire Alarm and Sprinkler Inspections Required. [Shannon Yaconiello @ 04/10/2025 3:28 PM] No sprinkler or alarm system see ADDENDUM 11.11.25- see attached narrative. [Mike Middleton @ 01/08/2026 11:21 AM]
|
||
| Miscellaneous Conditions | Resolved | Prior to Rough Building Wall Inspections |
|
Building Department
If service is 400 amps or over engineered one-line drawings prior to rough inspection
Received and approved by Tom Cook. Resolved. [Malea Michael-Ferrier @ 02/11/2026 9:21 AM]
|
||
| Truss Drawings Deferred Submittal | Resolved | Prior to Issuance of TCO/CO/CC |
|
Building Department
Truss drawings (include truss layout plan) shall be submitted, reviewed and approved prior to installation and inspections.
Received, reviewed and resolved- see SPRMU250307. [Malea Michael-Ferrier @ 02/11/2026 1:30 PM]
|
||
| MF/Com/I Planning CO Review | Open | Prior to Issuance of TCO/CO/CC |
|
Planning Department
At the time an applicant requests a “Final Building Inspection”, prior to issuance of a Certificate of Occupancy/Completion, the Department of Planning and Community Development will contact the applicant to inspect the site to ensure the project has been built in accordance with the approved plans and the Community Development Code. The inspection may include but is not limited to general site planning and grading, outdoor lighting, parking, retaining walls, building height and location, number of dwelling units, and consistency with approved building design.
|
||
| Vested Approval Conditions | Open | Prior to Issuance of CO/CC |
|
Planning Department
Compliance with XXXX conditions of approval required.
|
||
| FLC Submittal | Open | Prior to Rough Site Inspection |
|
Planning Department
Foundation location certificate shall be provided
|
||
| Miscellaneous Conditions | Resolved | Prior to Full Building Permit Issuance |
|
Planning Department
Project must receive substantial conformance approval from planning prior to full building permit issuance.
|
||
| Miscellaneous Conditions | Open | Prior to Issuance of TCO/CO/CC |
|
Mount Werner Water & Sanitation
Water and sewer infrastructure must be installed, observed and tested per MWW Rules, Regs, Specifications and license agreement for detention pond within sewer easement must be executed prior to any issuance of occupancy.
|
||
| Engineering Com/Ind/MF CO Review | Open | Prior to Issuance of TCO/CO/CC |
|
Engineering
At the time of project completion, an Improvement Summary Letter or Completion Letter signed and sealed by the Engineer of Record shall be uploaded to the associated building permit in CityView Portal against the applicable condition. Upon receipt of the letter, Engineering will review and perform a Final Site Inspection for the TCO/CO request.
|
||
| Miscellaneous Conditions | Resolved | Prior to Full Building Permit Issuance |
|
Mount Werner Water & Sanitation
Payment of Plant Investment Fees to Mount Werner Water must be satisfied prior to permit issuance.
|
||
| Reference Number | Status | Type |
|---|---|---|
| SPRPL251364 | Permit(s) Issued | Plumbing |
| Date Uploaded | File Type | Name |
|---|---|---|
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Report | INSPECTION REPORT.PDF | |
| Permit | PERMIT - DETAILED.PDF |